194 projects on file, including joint ventures this contractor is part of.
Total projects
194
Total budget
₱3.8B
Average progress
96.3%
Completion rate
87.1%
Average risk score
46.1
Medium risk on average, out of 100
Flagged as unusual
2
1.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region V | 174 | ₱3.6B | 47.1 | 1 | 96.2% |
| Region IV-B | 7 | ₱39.6M | 29.9 | 0 | 100.0% |
| Region IV-A | 6 | ₱43.7M | 51.5 | 0 | 100.0% |
| National Capital Region | 6 | ₱90.5M | 36.5 | 1 | 90.7% |
| Region VII | 1 | ₱4.5M | 19.6 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 75 | ₱534.9M | 39.1 | 1 | 97.8% |
| Flood Control and Drainage | 58 | ₱1.9B | 48.9 | 0 | 95.6% |
| Roads | 54 | ₱1.2B | 50.2 | 0 | 96.5% |
| OTHER | 3 | ₱89.1M | 74.6 | 0 | 100.0% |
| Bridges | 2 | ₱5.7M | 32.1 | 0 | 98.8% |
| GAA 2025 SSP | 1 | ₱37.4M | 95.1 | 1 | 15.0% |
| GAA 2025 OO-2 | 1 | ₱96.6M | 93.3 | 0 | 74.7% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25F00418CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG- ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, BARANGAY LANGGA S | Region V | Region V | On-Going | ₱37.4M | 15% | High risk95 | Flagged0.022 |
| 25F00412ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITH ROAD ALONG DAET RIVER, BARANGAY | Region V | Region V | On-Going | ₱96.6M | 75% | High risk93 | —-0.011 |
| 23F00304ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-SECONDARY ROADS-TAGAS-DAET POBLACION-MAGANG RD-K0341+000-K0341+784, K0341+000-K0341+784 OF TAGAS-DAET POBLACION-MAGANG RD, DAET, CAMA | Region V | Region V | Completed | ₱14.5M | 100% | High risk76 | —-0.036 |
| 23F00412ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS DAANG MAHARLIKA-TAGAS-DAET POBLACION ROAD LINK, CAMARINES NORTE, DAET, CAMARINES NORTE (2ND LEGISLATIVE D | Region V | Region V | Completed | ₱34.7M | 100% | High risk76 | —-0.035 |
| 22FC0113CONSTRUCTION OF DIVERSION/BY-PASS ROAD OF CORY AQUINO BOULEVARD, BARANGAY SABANG, VINZONS, CAMARINES NORTE | Region V | Camarines Norte DEO | Completed | ₱39.9M | 100% | High risk72 | —-0.028 |
| 20DO0075LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM - BUILDING AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT GEN. LUNA ST. BRGY. DULONG BAYAN 1, SAN MATEO, RIZAL | Region IV-A | Rizal 2nd DEO | Completed | ₱9.7M | 100% | High risk69 | —-0.074 |
| 24F00235ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF BINATAGAN RIVER CONTROL STRUCTURE W/ ROAD (PHASE I)BARA | Region V | Region V | On-Going | ₱93.6M | 28% | High risk66 | —-0.024 |
| 17FC0415CONST./REPAIR/REHAB. OF MULTI-PURPOSE BLDG., VINZONS PILOT HS, POB. 1 VINZONS CAMS. NORTE | Region V | Camarines Norte DEO | Completed | ₱9.7M | 100% | High risk62 | —-0.065 |
| 20FC0134CONSTRUCTION OF DAET RIVER CONTROL (CAMAMBUGAN SECTION), BRGY. CAMAMBUGAN, DAET, 2ND DISTRICT, CAMARINES NORTE | Region V | Camarines Norte DEO | Completed | ₱57.8M | 100% | High risk61 | —-0.027 |
| 25F00419CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, BARANGAY MAMPILI T | Region V | Region V | On-Going | ₱65.2M | 51% | High risk61 | —-0.057 |
| 18FC0042ASSET PRESERVATION PROGRAM - PREVENTIVE MAINT.-TERTIARY ROADS DAET-MERCEDES ROAD K0343+(-255.50)-K03 | Region V | Camarines Norte DEO | Completed | ₱74M | 100% | High risk61 | —-0.094 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25F00418CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG- ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, BARANGAY LANGGA S | Region V | Region V | On-Going | ₱37.4M | 15% | High risk95 | Flagged0.022 |
| 23O00079CONSTRUCTION OF MULTI-PURPOSE BUILDING (ACADEMIC CENTER) PUP RIZAL CAMPUS, LEPANTO, MANILA, PHASE II | National Capital Region | National Capital Region | On-Going | ₱67.9M | 44% | Medium risk55 | Flagged0.015 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 21FC0140CONSTRUCTION OF ADMINISTRATION BUILDING, 501CDC, 5RCDG, ARESCOM, BRGY. BAGASBAS, DAET, CAMARINES NORTE | Region V | Camarines Norte DEO | Completed | ₱19.6M | 100% | Medium risk53 | —-0.095 |
| 52 | 20FC0023CONSTRUCTION OF A MULTI-PURPOSE BUILDING AND SITE DEVELOPMENT WORKS, DPWH COMPOUND, PASIG, DAET CAMS | Region V | Camarines Norte DEO | Completed | ₱13.9M | 100% | Medium risk53 | —-0.097 |
| 53 | 23F00444CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-IMPROVEMENT OF ROAD, TALISAY, CAMARINES NORTE, TALISAY, CAMARINES NORTE (2ND L | Region V | Region V | Completed | ₱6.9M | 100% | Medium risk53 | —-0.095 |
| 54 | 23F00313CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM(BIP)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF WIDENING ROAD IMPROVEMENT/UPGRADING TALISAY, CAMA | Region V | Region V | Completed | ₱6.9M | 100% | Medium risk53 | —-0.098 |
| 55 | 21FC0141ASSET PRESERVATION - REHABILITATION / RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS DAANG MAHARLIKA (LZ) - K0359+800 - K0360+024, K0360+100 - K0360+150, K0364+638 - K0364+748, BASUD, CAMARINES NORTE | Region V | Camarines Norte DEO | Completed | ₱19.6M | 100% | Medium risk52 | —-0.099 |
| 56 | 21FC0117CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS DAET-SAN VICENTE - SAN LORENZO ROAD LEADING TO DACULANG DANAW, MANANAP FALLS, MOUNTAIN RANGE & MAMPUROG RIVER, CAMARINES NORTE, SAN VICENTE, CAMARINES NORTE | Region V | Camarines Norte DEO | Completed | ₱9.8M | 100% | Medium risk52 | —-0.099 |
| 57 | 21FC0126CONSTRUCTION OF SEAWALL WITH ROADS (CONG. ELMER PANOTES BOULEVARD), LEADING TO CORY AQUINO BOULEVARD, LANOT SECTION, MERCEDES, CAMARINES NORTE | Region V | Camarines Norte DEO | Completed | ₱24.5M | 100% | Medium risk52 | —-0.099 |
| 58 | 19FC0208CONSTRUCTION OF ACCESS ROAD IN BARANGAY TUACA, BASUD CAMS. NORTE | Region V | Camarines Norte DEO | Completed | ₱9.3M | 100% | Medium risk52 | —-0.100 |
| 59 | 22FC0216CONSTRUCTION/IMPROVEMENT OF SLOPE PROTECTION ALONG ROY PADILLA HIGHWAY, SAN LORENZO RUIZ, CAMARINES NORTE | Region V | Camarines Norte DEO | Completed | ₱86.8M | 100% | Medium risk52 | —-0.070 |
| 60 | 24F00159ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE AL | Region V | Region V | Completed | ₱86.8M | 100% | Medium risk52 | —-0.077 |
| 61 | 18FF0047FY-2018 LOCAL INFRASTRUCTURE PROGRAM - REHABILITATION OF TINAMBAC-SIRUMA ROAD K0538+660.00 - K0538+778.40, K0548+520 - K0548+550.48 TINAMBAC AND SIRUMA, CAMARINES SUR | Region V | Camarines Sur 4th DEO | Completed | ₱9.3M | 100% | Medium risk52 | —-0.091 |
| 62 | 24F00160ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE AL | Region V | Region V | Completed | ₱86.8M | 100% | Medium risk51 | —-0.077 |
| 63 | 24F00152ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BASUD RIVER, BARANGAY SAN | Region V | Region V | Completed | ₱86.8M | 100% | Medium risk51 | —-0.078 |
| 64 | 21F00070OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF DAET RIVER CONTROL STRUCTURE (CAMAMBUGAN SECTION), BRGY. CAMAMBUGAN, DAET, CAMARIN | Region V | Region V | Completed | ₱65.6M | 100% | Medium risk51 | —-0.084 |
| 65 | 24F00362CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUIDING (SENIOR CITIZENS CENTER), BARANGAY MAGANG, DAET, CAMARINES NORTE, DAET, CAMA | Region V | Region V | On-Going | ₱6.9M | 0% | Medium risk51 | —-0.026 |
| 66 | 19FC0030CONSTRUCTION OF MULTI-PURPOSE BUILDING AT SAN FRANCISCO NATIONAL HIGH SCHOOL, BRGY. SAN FRANCISCO, T | Region V | Camarines Norte DEO | Completed | ₱4.8M | 100% | Medium risk51 | —-0.097 |
| 67 | 24F00241CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF RIVER CONTROL STRUCTURE, CONGW. MARISOL C. PANOTES BOULEVARD, BARANGAY TACAD, | Region V | Region V | Completed | ₱74.2M | 100% | Medium risk51 | —-0.082 |
| 68 | 24F00242CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (CONGW. MARISOL C. PANOTES SEA VIEW PARK), BARANGA | Region V | Region V | Completed | ₱74.2M | 100% | Medium risk51 | —-0.082 |
| 69 | 18FC0083CONST. OF MULTI-PURPOSE BLDG., (COVERED COURT) JUANITA BALON ES, BRGY. CALANGCAWAN SUR, VINZONS CAMS | Region V | Camarines Norte DEO | Completed | ₱4.8M | 100% | Medium risk51 | —-0.098 |
| 70 | 20FC0069CONSTRUCTION/REHABILITATION/IMPROVEMENT OF MANGCAMAGONG -MATOOG-TOOG SEAWALL, BARANGAY MANGCAMAGONG, BASUD, CAMARINES NORTE AND BARANGAY MATOOG-TOOG, MERCEDES, CAMARINES NORTE | Region V | Camarines Norte DEO | Completed | ₱74.9M | 100% | Medium risk51 | —-0.082 |
| 71 | 23F00335CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING WITH (COVERED COURT), ALAWIHAO ELEMENTARY SCHOOL, BARANGAY ALAWIHAO, DA | Region V | Region V | On-Going | ₱4.8M | 100% | Medium risk51 | —-0.057 |
| 72 | 22FC0021CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. ALAWIHAO, DAET, CAMARINES NORTE | Region V | Camarines Norte DEO | Completed | ₱4.8M | 100% | Medium risk51 | —-0.098 |
| 73 | 24F00405CONSTRUCTION OF 2-STOREY 4-CLASSROOM SCHOOL BUILDING IN ALAWIHAO ELEMENTARY SCHOOL, BARANGAY ALAWIHAO, DAET, CAMARINES NORTE, BARANGAY ALAWIHAO, DAET, CAMARINES NORTE | Region V | Region V | On-Going | ₱19.9M | 96% | Medium risk51 | —-0.014 |
| 74 | 23F00317CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP )- EVACUATION CENTERS/QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES-CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BRGY. STO. DOMINGO, VINZONS, CAMARINES NORTE | Region V | Region V | Completed | ₱14.9M | 100% | Medium risk51 | —-0.097 |
| 75 | 20FC0094CONSTRUCTION OF MULTI-PURPOSE BUILDING, STA. CRUZ ELEMENTARY SCHOOL, BRGY. STA. CRUZ, TALISAY CAMARINES NORTE | Region V | Camarines Norte DEO | Completed | ₱4.8M | 100% | Medium risk51 | —-0.094 |