68 projects on file, including joint ventures this contractor is part of.
Total projects
68
Total budget
₱1.8B
Average progress
87.1%
Completion rate
63.2%
Below 70%
Average risk score
51.3
Medium risk on average, out of 100
Flagged as unusual
3
4.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 68 | ₱1.8B | 51.3 | 3 | 87.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 28 | ₱1.1B | 50.8 | 0 | 88.4% |
| Roads | 27 | ₱409.7M | 47.9 | 0 | 89.1% |
| Water Provision and Storage | 4 | ₱27.3M | 36.2 | 0 | 93.5% |
| GAA 2025 OO-2 | 3 | ₱142.3M | 89.9 | 0 | 31.9% |
| OTHER | 3 | ₱67.1M | 79.2 | 3 | 90.2% |
| Buildings and Facilities | 3 | ₱37.7M | 40.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DN0013CONSTRUCTION OF FLOOD CONTROL STRUCTURE, ONDOY CREEK, PHASE 2, BARANGAY SAN JOSE, ANTIPOLO CITY, RIZAL (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱49M | 71% | High risk91 | —-0.021 |
| 25DN0004CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, CALAWIS RIVER (UPSTREAM) PHASE 5, BARANGAY CALAWIS, ANTIPOLO CITY, RIZAL (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱46.7M | 12% | High risk89 | —-0.008 |
| 25DN0003CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, CALAWIS RIVER (DOWNSTREAM) PHASE 4, BARANGAY CALAWIS, ANTIPOLO CITY, RIZAL (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱46.6M | 13% | High risk89 | —-0.008 |
| 19DN0226CONCRETING OF PUROK CANUMAY, SITIO SAN YSIRO, BRGY. SAN JOSE FMR, PHASE II, BRGY. SAN JOSE ANTIPOLO CITY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱9.7M | 100% | High risk83 | Flagged0.003 |
| 19DN0227CONCRETING OF SITIO APIA - MANADIAM, BRGY. CALAWIS FMR, PHASE II, BRGY. CALAWIS ANTIPOLO CITY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱9.6M | 100% | High risk83 | Flagged0.003 |
| 24DN0088CONSTRUCTION OF BOX CULVERT, MANADLAM SITIO APIA, BARANGAY CALAWIS ANTIPOLO CITY, RIZAL (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱47.8M | 70% | High risk72 | Flagged0.003 |
| 25DN0012CONSTRUCTION OF FLOOD CONTROL STRUCTURE, TINAPANTAY RIVER, PHASE 5, BARANGAY SAN JOSE, ANTIPOLO CITY, RIZAL (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱49M | 75% | High risk72 | —-0.019 |
| 25DN0026CONSTRUCTION OF FLOOD CONTROL STRUCTURE, LIBIS CREEK, PHASE 3, BARANGAY SAN JOSE, ANTIPOLO CITY, RIZAL (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱47M | 29% | High risk70 | —-0.010 |
| 25DN0005CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, CUPANG RIVER (DOWNSTREAM) PHASE 4, BARANGAY CUPANG, ANTIPOLO CITY, RIZAL (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱46.9M | 79% | High risk70 | —-0.021 |
| 25DN0037ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - CORAZON C. AQUINO AVE. - K0030+375 - K0031+669, ANTIPOLO CITY (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱49.6M | 50% | High risk69 | —-0.033 |
| 25DN0002CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BINAYOYO RIVER (DOWNSTREAM) PHASE 7, BARANGAY CALAWIS, ANTIPOLO CITY, RIZAL (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱46.7M | 21% | High risk69 | —-0.007 |
| 25DN0077ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - CORAZON C. AQUINO AVE. - K0028+500 - K0031+669, ANTIPOLO CITY (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱28.5M | 0% | High risk67 | —-0.020 |
| 20DN0014ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS, MARIKINA-INFANTA RD., - K0031+900 - K0032+293, ANTIPOLO CITY, RIZAL (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱42.6M | 100% | High risk66 | —-0.071 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24DN0088CONSTRUCTION OF BOX CULVERT, MANADLAM SITIO APIA, BARANGAY CALAWIS ANTIPOLO CITY, RIZAL (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱47.8M | 70% | High risk72 | Flagged0.003 |
| 19DN0226CONCRETING OF PUROK CANUMAY, SITIO SAN YSIRO, BRGY. SAN JOSE FMR, PHASE II, BRGY. SAN JOSE ANTIPOLO CITY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱9.7M | 100% | High risk83 | Flagged0.003 |
| 19DN0227CONCRETING OF SITIO APIA - MANADIAM, BRGY. CALAWIS FMR, PHASE II, BRGY. CALAWIS ANTIPOLO CITY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱9.6M | 100% | High risk83 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 23DN0011FY 2023 DPWH INFRASTRUCTURE PROGRAM - ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - MARIKINA - INFANTA RD - K0028+367 - K0028+578 ANTIPOLO CITY (SECOND DIST | Region IV-A | Rizal 1st DEO | Completed | ₱12.2M | 100% | Medium risk46 | —-0.104 |
| 52 | 21DN0013REHABILITATION OF ROADS WITH DRAINAGE SYSTEM, ANTIPOLO HILLS, ATIS ST., BARANGAY SAN LUIS ANTIPOLO CITY | Region IV-A | Rizal 1st DEO | Completed | ₱9.6M | 100% | Medium risk46 | —-0.108 |
| 53 | 21DN0009REHABILITATION OF ROADS WITH DRAINAGE SYSTEM MAAGAY UNO, BARANGAY INARAWAN, ANTIPOLO CITY | Region IV-A | Rizal 1st DEO | Completed | ₱9.6M | 100% | Medium risk46 | —-0.108 |
| 54 | 23DN0029ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD WITH DRAINAGE SYSTEM, SAN PEDRO AND SAN LORENZO RUIZ ST., BARANGAY DALIG, ANTIPOLO CITY, RIZAL (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱9.9M | 91% | Medium risk46 | —-0.056 |
| 55 | 24DN0061ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD WITH DRAINAGE SYSTEM, ST. VINCENT ST., BARANGAY DALIG ANTIPOLO CITY, RIZAL (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱5.8M | 100% | Medium risk46 | —-0.066 |
| 56 | 23DN0017ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD WITH DRAINAGE SYSTEM, KANTORAB (PHASE 2), BARANGAY SAN ROQUE ANTIPOLO CITY, RIZAL (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱5.9M | 100% | Medium risk46 | —-0.105 |
| 57 | 24DN0122ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - CORAZON C. AQUINO AVE. - K0029+000 - K0029+400 ANTIPOLO CITY (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱9.8M | 100% | Medium risk46 | —-0.108 |
| 58 | 19DN0180REHABILITATION OF CREEK ALONG FERRETVILLE TO SAGUINSIN, BARANGAY SAN ROQUE, ANTIPOLO CITY | Region IV-A | Rizal 1st DEO | Completed | ₱4.7M | 100% | Medium risk43 | —-0.088 |
| 59 | 20DN0199CONCRETING OF SITIO SAPINIT, BRGY. SAN JUAN FMR, BRGY. SAN JUAN ANTIPOLO CITY | Region IV-A | Rizal 1st DEO | Completed | ₱9.9M | 100% | Medium risk43 | —-0.055 |
| 60 | 20DN0183CONCRETING OF SITIO TANZA I, BRGY. SAN JOSE FMR PHASE 3, BRGY. SAN JOSE ANTIPOLO CITY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱11.6M | 100% | Medium risk43 | —-0.056 |
| 61 | 19DN0225CONCRETING OF SITIO TANZA I, BRGY. SAN JOSE FMR, BRGY. SAN JOSE ANTIPOLO CITY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱4.8M | 100% | Medium risk43 | —-0.054 |
| 62 | 20DN0182CONCRETING OF SITIO SAN JOSEPH, BRGY. SAN JOSE FMR, BRGY. SAN JOSE, ANTIPOLO CITY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱12M | 100% | Medium risk42 | —-0.055 |
| 63 | 20DN0181CONCRETING OF SAN YSIRO - SITIO LIBIS, BRGY. SAN JOSE FMR, BRGY. SAN JOSE, ANTIPOLO CITY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱12M | 100% | Medium risk42 | —-0.056 |
| 64 | 24DN0073ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROADS WITH DRAINAGE SYSTEM, MILAGROS SUBDIVISION BRGY. DALIG, ANTIPOLO CITY, (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱4.7M | 100% | Medium risk42 | —-0.066 |
| 65 | 21DN0014CONSTRUCTION OF SLOPE PROTECTION, MARCELINO M. SANTOS NHS, BARANGAY SAN JOSE, ANTIPOLO CITY | Region IV-A | Rizal 1st DEO | Completed | ₱4.7M | 100% | Low risk27 | —-0.088 |
| 66 | 20DN0146CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. BAGONG NAYON, ANTIPOLO CITY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱2.9M | 100% | Low risk26 | —-0.103 |
| 67 | 22DO0071CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM - RAINWATER COLLECTOR IN PUBLIC FACILITIES - CONSTRUCTION OF RAINWATER COLLECTORS AT VARIOUS SITES, PILILLA, RIZAL | Region IV-A | Rizal 2nd DEO | Completed | ₱3.3M | 100% | Low risk25 | —-0.069 |
| 68 | 21DO0088CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTORS CONATRUCTION OF RAINWATER COLLECTORS AT TERESA AND TANAY, RIZAL | Region IV-A | Rizal 2nd DEO | Completed | ₱4.4M | 100% | Low risk25 | —-0.067 |