Opening the dossier…
Opening the dossier…
Contractor dossier
27 projects on file, including joint ventures this contractor is part of.
Total projects
27
Total budget
₱114.7M
Average progress
100.0%
Completion rate
100.0%
Average risk score
21.3
Low risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 27 | ₱114.7M | 21.3 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 15 | ₱59.4M | 15.3 | 0 | 100.0% |
| Roads | 9 | ₱47.4M | 26.3 | 0 | 100.0% |
| Flood Control and Drainage | 2 | ₱2.9M | 12.1 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱4.9M | 83.8 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CH0050IMPROVEMENT OF ROAD, PHASE 1, BARANGAY HACIENDA DOLORES, PORAC, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱4.9M | 100% | High risk84 | —-0.032 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25CH0050IMPROVEMENT OF ROAD, PHASE 1, BARANGAY HACIENDA DOLORES, PORAC, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱4.9M | 100% | High risk84 | —-0.032 |
| 2 | 19CH0121CONSTRUCTION OF MULTI-PURPOSE BUILDING COVERED COURT BRGY. PULUNG MASLE, GUAGUA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱4.8M | 100% | Medium risk32 | —-0.105 |
| 3 | 20CH0021CONSTRUCTION OF MULTI-PURPOSE BUILDING, LUBAO, PAMPANGA, LUBAO, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱5.8M | 100% | Medium risk32 | —-0.105 |
| 4 | 23CH0129IMPROVEMENT/REHABILITATION OF A. TWO (2) CLASSROOM SCHOOL BUILDING WITH COMFORT ROOM AT SAN PABLO 2ND ELEMENTARY SCHOOL, LUBAO, PAMPANGA B. THREE (3) CLASSROOM SCHOOL BUILDING WITH COMFORT ROOM AT DELA PAZ ELEMENTARY SCHOOL, LUBAO, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱5.4M | 100% | Medium risk32 | —-0.105 |
| 5 | 19CH0126CONCRETING OF ROAD AT LOURDES BRGY. ROAD, LUBAO, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱4.8M | 100% | Medium risk32 | —-0.103 |
| 6 | 21CH0071LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS - REHABILITATION OF SAN NICOLAS - FORTUNA ROAD, SAN NICOLAS AND FORTUNA, FLORIDABLANCA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱4.9M | 100% | Medium risk31 | —-0.104 |
| 7 | 19CH0135CONCRETING OF ROAD, SAN JOSE ST. STA. CRUZ, PORAC, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱9.5M | 100% | Medium risk30 | —-0.103 |
| 8 | 24CH0076CONSTRUCTION OF ROAD, BRGY. CALZADANG BAYU, PORAC, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱5M | 100% | Low risk30 | —-0.102 |
| 9 | 25CH0043CONSTRUCTION OF ROAD, BARANGAY NATIVIDAD, GUAGUA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱4.9M | 100% | Low risk30 | —-0.103 |
| 10 | 19CH0114CONCRETING OF ROAD AT SAN ROQUE ARBOL, LUBAO, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱4.7M | 100% | Low risk30 | —-0.102 |
| 11 | 22CH0018CONSTRUCTION OF ROAD WITH LINED CANAL, BARANGAY STA. MONICA, STA. RITA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱7.9M | 100% | Low risk30 | —-0.104 |
| 12 | 19CG0171CONSTRUCTION OF TWO (2) - STOREY, FOUR (4) CLASSROOM SCHOOL BUILDING AT SAN PEDRO ES, CITY OF SAN FERNANDO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱8.6M | 100% | Low risk25 | —-0.053 |
| 13 | 19CH0140CONSTRUCTION OF TWO-STOREY (4 CLASSROOM) SCHOOL BUILDING GUAGUA ES, GUAGUA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱12.2M | 100% | Low risk24 | —-0.052 |
| 14 | 21CH0050LOCAL INFRASTRUCTURE PROGRAM-LOCAL ROADS AND BRIDGES-LOCAL ROADS-CONCRETING OF ROAD IN BARANGAY PIAS, PORAC, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱2.9M | 100% | Low risk13 | —-0.098 |
| 15 | 21CH0074LOCAL INFRASTRUCTURE PROGRAM - FLOOD CONTROL AND DRAINAGE - DRAINAGE/PROTECTION WORKS - CONSTRUCTION OF CONCRETE CANAL, PUROK 2 & 4, SAN NICOLAS 2ND, GUAGUA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱2M | 100% | Low risk13 | —-0.089 |
| 16 | 19CH0088CONSTRUCTION (CONCRETING) OF ROAD KIRATAK ROAD, SAN BASILIO, STA. RITA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱2.8M | 100% | Low risk12 | —-0.100 |
| 17 | 19CH0081CONSTRUCTION OF BOX CULVERT AT SITIO TABUN, PUROK 6 SAN ISIDRO, FLORIDABLANCA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱958.3K | 100% | Low risk12 | —-0.085 |
| 18 | 20CH0067CONSTRUCTION OF MULTI-PURPOSE BUILDING BRGY. SAN BASILIO, STA. RITA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱2.9M | 100% | Low risk11 | —-0.103 |
| 19 | 23CG0147BASIC INFRASTRUCTURE PROGRAM: MULTI-PURPOSE BUILDING/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION (CONSTRUCTION) OF MULTI-PURPOSE BUILDING, SAN JUAN, STA. ANA, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.8M | 100% | Low risk11 | —-0.104 |
| 20 | 21CG0271CONSTRUCTION/ COMPLETION OF (2STY4CL) SAN PEDRO ES, SAN FERNANDO CITY, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱4.4M | 100% | Low risk9 | —-0.052 |
| 21 | 21CH0121COMPLETION OF TWO-STOREY (4 CLASSROOM) SCHOOL BUILDING GUAGUA ES, GUAGUA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱3.7M | 100% | Low risk9 | —-0.052 |
| 22 | 20CG0159LOCAL INFRASTRUCTURE PROGRAM: MULTIPURPOSE/ FACILITIES - REHABILITATION OF MULTI-PURPOSE BUILDING, STO. NIÑO ELEMENTARY SCHOOL, SAN LUIS, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱1.9M | 100% | Low risk8 | —-0.104 |
| 23 | 20CG0180CONSTRUCTION/ REPAIR/ REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/ FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. PANGATLAN, MEXICO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱1.9M | 100% | Low risk8 | —-0.100 |
| 24 | 20CG0169LOCAL INFRASTRUCTURE PROGRAM: MULTIPURPOSE/ FACILITIES - CONSTRUCTION OF MULTI-PURPOSE COVERED COURT AREA WITH REINFORCED CONCRETE SLAB, SAN ROQUE, STA. ANA, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱1.9M | 100% | Low risk8 | —-0.103 |
| 25 | 24CG0103BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, SAN JOSE MATULID, MEXICO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱1.9M | 100% | Low risk8 | —-0.103 |