75 projects on file, including joint ventures this contractor is part of.
Total projects
75
Total budget
₱340.1M
Average progress
91.4%
Completion rate
66.7%
Below 70%
Average risk score
42.3
Medium risk on average, out of 100
Flagged as unusual
8
10.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region II | 75 | ₱340.1M | 42.3 | 8 | 91.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 55 | ₱250.6M | 37.4 | 1 | 92.9% |
| Roads | 9 | ₱32M | 33.7 | 0 | 99.6% |
| GAA 2025 SSP | 6 | ₱32.9M | 95.9 | 6 | 64.7% |
| Flood Control and Drainage | 3 | ₱12.3M | 41.1 | 0 | 100.0% |
| OTHER | 1 | ₱9.9M | 85.8 | 1 | 61.6% |
| Water Provision and Storage | 1 | ₱2.3M | 28.5 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25BD0077BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DASSUN, SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱4.9M | 72% | High risk97 | Flagged0.013 |
| 25BD0165BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, SOLANA, CAGAYAN - PHASE II | Region II | Cagayan 3rd DEO | On-Going | ₱4.8M | 91% | High risk97 | Flagged0.007 |
| 25BD0072BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (CONVERTIBLE TO EVACUATION CENTER), BARANGAY FURAGUI, SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱4.9M | 40% | High risk97 | Flagged0.023 |
| 25BD0164SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - STRUCTURAL AND RESILIENCE PROGRAM - CONSTRUCTION OF MULTI-PURPOSE BUILDING, CSU CARIG, TUGUEGARAO CITY, CAGAYAN - PHASE II | Region II | Cagayan 3rd DEO | On-Going | ₱9.6M | 6% | High risk96 | Flagged0.036 |
| 25BD0171SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROADS AND DRAINAGES AT MUNICIPALITY OF SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱6.7M | 80% | High risk96 | Flagged0.011 |
| 25BD0117BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDING, LANNA ELEMENTARY SCHOOL, SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱1.9M | 100% | High risk93 | Flagged0.002 |
| 24BD0198CONSTRUCTION OF 2-STOREY 6-CLASSROOM SCHOOL BUILDING (PHASE 1) IN LAGUM INEGRATED SCHOOL, BARANGAY NABBABALAYAN, PEÑABLANCA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱9.9M | 62% | High risk86 | Flagged0.058 |
| 25BD0155BASIC INFRASTRUCTURE PROGRAM (BIP) -MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING(CONVERTIBLE TO EVACUATION CENTER), BARANGAY CENTRO SOUTHEAST, SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱4.8M | 0% | High risk68 | Flagged0.004 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24BD0198CONSTRUCTION OF 2-STOREY 6-CLASSROOM SCHOOL BUILDING (PHASE 1) IN LAGUM INEGRATED SCHOOL, BARANGAY NABBABALAYAN, PEÑABLANCA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱9.9M | 62% | High risk86 | Flagged0.058 |
| 25BD0164SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - STRUCTURAL AND RESILIENCE PROGRAM - CONSTRUCTION OF MULTI-PURPOSE BUILDING, CSU CARIG, TUGUEGARAO CITY, CAGAYAN - PHASE II | Region II | Cagayan 3rd DEO | On-Going | ₱9.6M | 6% | High risk96 | Flagged0.036 |
| 25BD0072BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (CONVERTIBLE TO EVACUATION CENTER), BARANGAY FURAGUI, SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱4.9M | 40% | High risk97 | Flagged0.023 |
| 25BD0077BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DASSUN, SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱4.9M | 72% | High risk97 | Flagged0.013 |
| 25BD0171SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROADS AND DRAINAGES AT MUNICIPALITY OF SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱6.7M | 80% | High risk96 | Flagged0.011 |
| 25BD0165BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, SOLANA, CAGAYAN - PHASE II | Region II | Cagayan 3rd DEO | On-Going | ₱4.8M | 91% | High risk97 | Flagged0.007 |
| 25BD0155BASIC INFRASTRUCTURE PROGRAM (BIP) -MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING(CONVERTIBLE TO EVACUATION CENTER), BARANGAY CENTRO SOUTHEAST, SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱4.8M | 0% | High risk68 | Flagged0.004 |
| 25BD0117BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDING, LANNA ELEMENTARY SCHOOL, SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱1.9M | 100% | High risk93 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25BD0077BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DASSUN, SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱4.9M | 72% | High risk97 | Flagged0.013 |
| 2 | 25BD0165BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, SOLANA, CAGAYAN - PHASE II | Region II | Cagayan 3rd DEO | On-Going | ₱4.8M | 91% | High risk97 | Flagged0.007 |
| 3 | 25BD0072BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (CONVERTIBLE TO EVACUATION CENTER), BARANGAY FURAGUI, SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱4.9M | 40% | High risk97 | Flagged0.023 |
| 4 | 25BD0164SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - STRUCTURAL AND RESILIENCE PROGRAM - CONSTRUCTION OF MULTI-PURPOSE BUILDING, CSU CARIG, TUGUEGARAO CITY, CAGAYAN - PHASE II | Region II | Cagayan 3rd DEO | On-Going | ₱9.6M | 6% | High risk96 | Flagged0.036 |
| 5 | 25BD0171SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROADS AND DRAINAGES AT MUNICIPALITY OF SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱6.7M | 80% | High risk96 | Flagged0.011 |
| 6 | 25BD0117BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDING, LANNA ELEMENTARY SCHOOL, SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱1.9M | 100% | High risk93 | Flagged0.002 |
| 7 | 24BD0198CONSTRUCTION OF 2-STOREY 6-CLASSROOM SCHOOL BUILDING (PHASE 1) IN LAGUM INEGRATED SCHOOL, BARANGAY NABBABALAYAN, PEÑABLANCA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱9.9M | 62% | High risk86 | Flagged0.058 |
| 8 | 25BD0155BASIC INFRASTRUCTURE PROGRAM (BIP) -MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING(CONVERTIBLE TO EVACUATION CENTER), BARANGAY CENTRO SOUTHEAST, SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱4.8M | 0% | High risk68 | Flagged0.004 |
| 9 | 25BD0033BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (CONVERTIBLE TO EVACUATION CENTER), BARANGAY CATTARAN, SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱4.8M | 69% | Medium risk55 | —-0.040 |
| 10 | 24BD0172BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDING/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDING, CENTRO, SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱19.8M | 100% | Medium risk54 | —-0.046 |
| 11 | 24BD0225BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDING/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDING, CSU CARIG CAMPUS, TUGUEGARAO CITY, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱19.8M | 100% | Medium risk54 | —-0.046 |
| 12 | 23BD0122BASIC INFRASTRUCTURE PROGRAM/MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (IMPROVEMENT) OF MULTI-PURPOSE FACILITY (COVERED COURT), BRGY. SOLANA NORTHEAST, SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱4.9M | 72% | Medium risk54 | —-0.026 |
| 13 | 22BD0079BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF TANZA MULTI-PURPOSE BUILDING (CONVERTIBLE TO EVACUATION CENTER), TUGUEGARAO CITY, CAGAYAN | Region II | Cagayan 3rd DEO | Completed | ₱4.9M | 100% | Medium risk54 | —-0.085 |
| 14 | 23BD0094BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION (IMPROVEMENT) OF MULTI-PURPOSE BUILDING (HOME ECONOMICS BUILDING), SOLANA SOUTH CENTRAL SCHOOL, SOLANA, CAGAYAN (PHASE 2) | Region II | Cagayan 3rd DEO | Completed | ₱4.9M | 100% | Medium risk54 | —-0.086 |
| 15 | 24BD0021BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF MULTI - PURPOSE BUILDING (CONVERTIBLE TO EVACUATION CENTER), BRGY. LINAO NORTE, TUGUEGARAO CITY, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱7.9M | 74% | Medium risk53 | —-0.032 |
| 16 | 24BD0010BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI- PURPOSE BUILDING (CONVERTIBLE TO EVACUATION CENTER), BRGY. LINAO WEST, TUGUEGARAO CITY, CAGAYAN | Region II | Cagayan 3rd DEO | Completed | ₱7.9M | 100% | Medium risk53 | —-0.085 |
| 17 | 22BD0073LOCAL PROGRAM - NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES MULTIPURPOSE / FACILITIES - CONSTRUCTION OF PROFESSIONAL REGULATION COMMISSION RO2 TRAINING CENTER, TUGUEGARAO CITY, CAGAYAN | Region II | Cagayan 3rd DEO | Completed | ₱9.7M | 100% | Medium risk53 | —-0.080 |
| 18 | 23BD0093BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (HOME ECONOMICS BUILDING), SOLANA NORTH CENTRAL SCHOOL, SOLANA, CAGAYAN (PHASE I) | Region II | Cagayan 3rd DEO | Completed | ₱4.9M | 100% | Medium risk53 | —-0.085 |
| 19 | 24BD0125LOCAL PROGRAM - NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES - COMPLETION OF PHILIPPINE COAST GUARD BUILDING, TUGUEGARAO CITY, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱9.8M | 96% | Medium risk53 | —-0.042 |
| 20 | 21BD0101LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - CONSTRUCTION OF SENIOR CITIZEN BUILDING, TUGUEGARAO CITY | Region II | Cagayan 3rd DEO | Completed | ₱4.9M | 100% | Medium risk53 | —-0.083 |
| 21 | 23BD0141SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES -CONSTRUCTION OF MULTI-PURPOSE BUILDING AT CENTRO NORTHWEST, SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱5.9M | 100% | Medium risk53 | —-0.041 |
| 22 | 22BD0043SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTIPURPOSE BUILDING CARIG SUR, TUGUEGARAO CITY, CAGAYAN | Region II | Cagayan 3rd DEO | Completed | ₱6.9M | 100% | Medium risk53 | —-0.084 |
| 23 | 24BD0069BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI- PURPOSE BUILDING, BRGY. MALABBAC, IGUIG, CAGAYAN | Region II | Cagayan 3rd DEO | Completed | ₱4.9M | 100% | Medium risk53 | —-0.084 |
| 24 | 25BD0168SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - STRUCTURAL AND RESILIENCE PROGRAM- CONSTRUCTION OF MULTI-PURPOSE BUILDING, CSU SOLANA, SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱12.7M | 44% | Medium risk53 | —-0.032 |
| 25 | 24BD0017LOCAL PROGRAM - NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES - CONSTRUCTION OF DEPARTMENT OF LABOR AND EMPLOYMENT REGIONAL OFFICE, REGIONAL GOVERNMENT CENTER, TUGUEGARAO CITY, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱14.6M | 79% | Medium risk53 | —-0.035 |