112 projects on file, including joint ventures this contractor is part of.
Total projects
112
Total budget
₱1.5B
Average progress
91.4%
Completion rate
75.0%
Average risk score
43.0
Medium risk on average, out of 100
Flagged as unusual
1
0.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 112 | ₱1.5B | 43.0 | 1 | 91.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 88 | ₱1.3B | 43.6 | 0 | 91.0% |
| Buildings and Facilities | 14 | ₱71.5M | 37.1 | 1 | 90.8% |
| Flood Control and Drainage | 10 | ₱195.2M | 46.1 | 0 | 96.2% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23HG0068CONSTRUCTION OF 2STY4CL, DUMALAN NHS, DALAGUETE, CEBU | Region VII | Cebu 2nd DEO | On-Going | ₱11.3M | 31% | Medium risk45 | Flagged0.024 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 22HE0053CONVERGENCE ANS SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SOUTH POBLACION, SAN FERNANDO, CEBU | Region VII | Cebu 1st DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.095 |
| 27 | 25HE0070CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY CONALOM T | Region VII | Cebu 2nd DEO | On-Going | ₱21.2M | 0% | Medium risk47 | —-0.031 |
| 28 | 24HE0071CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BANLOT, SIBONGA, CEBU | Region VII | Cebu 1st DEO | Completed | ₱24.7M | 100% | Medium risk47 | —-0.096 |
| 29 | 24HG0048OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - N BACALSO AVE (CEBU SOUTH RD) K0057+(-845) - K0057+(-333) | Region VII | Cebu 2nd DEO | On-Going | ₱17.2M | 100% | Medium risk47 | —-0.056 |
| 30 | 24HE0021ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - N BACALSO AVE (CEBU SOUTH RD) - K0055+071 - K0055+116, K0055+170 - K0055+226, K0055+780 - K0055+932, SIBONGA, CEBU | Region VII | Cebu 1st DEO | Completed | ₱22.1M | 100% | Medium risk47 | —-0.096 |
| 31 | 24HE0043ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - N BACALSO AVE (CEBU SOUTH RD), K0048+727 - K0049+000, SIBONGA, CEBU | Region VII | Cebu 1st DEO | Completed | ₱24.5M | 100% | Medium risk47 | —-0.096 |
| 32 | 23HE0070ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - N BACALSO AVE (CEBU SOUTH RD) - K0034+295 - K0034+605, CARCAR CITY, CEBU | Region VII | Cebu 1st DEO | Completed | ₱26.2M | 100% | Medium risk47 | —-0.096 |
| 33 | 24HE0038ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - N BACALSO AVE (CEBU SOUTH RD) - K0034+735 - K0035+000, CARCAR CITY, CEBU | Region VII | Cebu 1st DEO | Completed | ₱20.3M | 100% | Medium risk47 | —-0.096 |
| 34 | 24HE0237ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHAB/RECONST/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - N BACALSO AVE (CEBU SOUTH RD) - K0034+295 - K0035+451, CARCAR CITY, CEBU | Region VII | Cebu 1st DEO | Completed | ₱21.3M | 100% | Medium risk47 | —-0.096 |
| 35 | 24HE0007ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - N BACALSO AVE (CEBU SOUTH RD) - K0041+459 - K0041+674, CARCAR, CEBU | Region VII | Cebu 1st DEO | Completed | ₱18M | 100% | Medium risk47 | —-0.096 |
| 36 | 24HE0172CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, COGON, CITY OF NAGA, CEBU | Region VII | Cebu 1st DEO | Completed | ₱24.7M | 100% | Medium risk47 | —-0.097 |
| 37 | 25HE0102CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - SITIO KABALAWAN ROAD LEADING TO MAG-UUGMAD FARM TOURISM AND MT. LANTOY, BRGY. TABAY | Region VII | Cebu 2nd DEO | On-Going | ₱4.8M | 0% | Medium risk46 | —-0.032 |
| 38 | 22HE0039CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - SUSTAINABLE INFRAS PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATL. ROADS/LEADING TO MAJOR /STRATEGIC PUBLIC BLDGS/FACILITIES - CONST ROAD, INCL DRAINAGE SYS, MINGLANILLA, CEBU | Region VII | Cebu 1st DEO | Completed | ₱19.6M | 100% | Medium risk46 | —-0.095 |
| 39 | 24HE0040ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - CONST./UPGRADING/REHAB. OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS - N BACALSO AVE (CEBU SOUTH RD) - (S00292CB) K0009+(-320) - K0009+467, (S00196C | Region VII | Cebu 1st DEO | Completed | ₱24.5M | 100% | Medium risk46 | —-0.097 |
| 40 | 24HG0005CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BINLOD ROAD LEADING TO BINLOD ES, BINLOD, ARG | Region VII | Cebu 2nd DEO | On-Going | ₱4.9M | 100% | Medium risk46 | —-0.055 |
| 41 | 24HG0018CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY LANGUB, ARGAO, CEBU | Region VII | Cebu 2nd DEO | On-Going | ₱4.9M | 100% | Medium risk46 | —-0.059 |
| 42 | 24HG0077CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, SITIO CAYAM OF BRGY. GUIWANON BARANGAY ROAD, | Region VII | Cebu 2nd DEO | On-Going | ₱4.9M | 100% | Medium risk46 | —-0.059 |
| 43 | 25HE0012CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, SITIO PROPER, BARANGAY MANDILIKIT, ARGAO, | Region VII | Cebu 2nd DEO | On-Going | ₱4.9M | 92% | Medium risk46 | —-0.061 |
| 44 | 25HE0007CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, SITIO PROPER, BARANGAY CAPIO-AN, ARGAO, CE | Region VII | Cebu 2nd DEO | On-Going | ₱4.9M | 100% | Medium risk46 | —-0.065 |
| 45 | 24HG0047CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, BRGY. MANLUM BARANGAY ROAD, BRGY. MANLUM, OSLOB | Region VII | Cebu 2nd DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.091 |
| 46 | 24HG0049CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, SITIO MALARID OF BRGY. NUG-AS BARANGAY ROAD, | Region VII | Cebu 2nd DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.093 |
| 47 | 25HE0008CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY SUMAGUAN, ARGAO, CEBU | Region VII | Cebu 2nd DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.094 |
| 48 | 24HE0184CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - IMPROVEMENT OF BANLOT ROAD, BARANGAY BANLOT, SIBONGA, CEBU | Region VII | Cebu 1st DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.094 |
| 49 | 20HE0107LOCAL ROADS AND BRIDGES - LOCAL ROADS - CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOSU INFRASTRUCTURE INCLUDING LOCAL PROJECTS - CONSTRUCTION OF ROAD, BRGY. POBLACION, SIBONGA, CEBU | Region VII | Cebu 1st DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.094 |
| 50 | 24HG0011CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, SITIO TIPOSO ROAD, BARANGAY TALOOT, ARGAO, CE | Region VII | Cebu 2nd DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.094 |