Contractor dossier
17 projects on file, including joint ventures this contractor is part of.
Total projects
17
Total budget
₱1.2B
Average progress
93.0%
Completion rate
76.5%
Average risk score
55.9
Medium risk on average, out of 100
Flagged as unusual
3
17.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 10 | ₱441.9M | 46.0 | 1 | 97.2% |
| Region V | 6 | ₱591.6M | 74.2 | 2 | 84.9% |
| Region XII | 1 | ₱188.8M | 45.5 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 6 | ₱82M | 42.0 | 0 | 97.0% |
| Roads | 5 | ₱734.8M | 56.7 | 0 | 100.0% |
| OTHER | 3 | ₱270.8M | 82.9 | 2 | 70.3% |
| Flood Control and Drainage | 1 | ₱93.3M | 67.7 | 0 | 100.0% |
| Water Provision and Storage | 1 | ₱14.4M | 49.9 | 0 | 100.0% |
| Bridges | 1 | ₱26.9M | 49.1 | 1 | 88.4% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25FO0098BASIC EDUCATIONAL FACILITIES FUND (BEFF) - CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS - CONSTRUCTION OF SCHOOL BUILDING, MULADBUCAD GRANDE ELEMENTARY SCHOOL, BRGY. MULADBUCAD GRANDE, GUINOBATAN, ALBAY | Region V | Albay 3rd DEO | On-Going | ₱19.3M | 11% | High risk88 | Flagged0.060 |
| 17F00054NETWORK DEVELOPMENT-IMPROVEMENT/WIDENING OF NATIONAL ROADS-CONSTRUCTION OF MISSING GAPS CONNECTING NATIONAL ROADS, INCLUDING ROW-BACON-MANITO ROAD INCLUDING BRIDGE AND SLOPE PROTECTION, ROAD: K0595+514.35-K0596+763.35 (BANASI);K0599+370-K0599+780 (OSIAO); | Region V | Region V | Completed | ₱144.2M | 100% | High risk81 | Flagged0.001 |
| 16F00109MFO1-NATIONAL ROAD NETWORK SERVICES, NETWORK DEVELOPMENT: CONSTRUCTION OF MISSING GAPS CONNECTING NATIONAL ROADS, INCLUDING ROW, BACON-MANITO ROAD, BRIDGE COMPONENT, BACON, SORSOGON 1ST LD | Region V | Region V | Completed | ₱107.2M | 100% | High risk80 | —-0.007 |
| 20FA0011REHABILITATION OF SAN VICENTE FLOOD CONTROL, TABACO CITY, ALBAY | Region V | Albay 1st DEO | Completed | ₱93.3M | 100% | High risk68 | —-0.077 |
| 21I00049CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - CONSTRUCTION OF ROAD, BONGA - PAMAMAS-AN LINOOBAN - MARARANGSI - CALUYAHAN, STA. 0+000 TO STA. 1+570, STA. 7+100 TO STA. 10+327.44, MOTIONG, SAMAR | Region VIII | Region VIII | Completed | ₱207.2M | 100% | High risk66 | —-0.053 |
| 21I00053CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - CONSTRUCTION OF ROAD, BRGY. IBOL - BRGY. JIAN-AN, BRGY. PANGDAN, JIABONG AND CATBALOGAN CITY, SAMAR | Region VIII | Region VIII | Completed | ₱141M | 100% | High risk66 | —-0.073 |
| 17F00048MFO3-MAINT. & CONST. SERVICES OF OTHER INFRASTRUCTURES CONST./IMPR. OF ACCESS ROAD LEADING TO DECLARED TOURISM DESTINATIONS, CONST OF CONCRETE ROAD-CAGRARAY CIRCUMFERENTIAL ROAD, TAMBILAGAO-LANGATON AND CABASAN-NAPAO-TANAGA SECTION, ALBAY 1ST LD | Region V | Region V | Completed | ₱193M | 100% | High risk65 | —-0.022 |
| 22FB0163LOCAL PROGRAM: CONSTRUCTION OF EVACUATION CENTER/MULTI-PURPOSE BUILDING AT DARAGA COMMUNITY COLLEGE, DARAGA, ALBAY | Region V | Albay 2nd DEO | On-Going | ₱34.4M | 99% | High risk64 | —-0.043 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25FO0098BASIC EDUCATIONAL FACILITIES FUND (BEFF) - CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS - CONSTRUCTION OF SCHOOL BUILDING, MULADBUCAD GRANDE ELEMENTARY SCHOOL, BRGY. MULADBUCAD GRANDE, GUINOBATAN, ALBAY | Region V | Albay 3rd DEO | On-Going | ₱19.3M | 11% | High risk88 | Flagged0.060 |
| 21IK0036CONST. OF NEW BRIDGE-BURI BRIDGE ALONG BURI ACCESS ROAD, BRGY. SILANGA, CATBALOGAN CITY | Region VIII | Samar 2nd DEO | On-Going | ₱26.9M | 88% | Medium risk49 | Flagged0.006 |
| 17F00054NETWORK DEVELOPMENT-IMPROVEMENT/WIDENING OF NATIONAL ROADS-CONSTRUCTION OF MISSING GAPS CONNECTING NATIONAL ROADS, INCLUDING ROW-BACON-MANITO ROAD INCLUDING BRIDGE AND SLOPE PROTECTION, ROAD: K0595+514.35-K0596+763.35 (BANASI);K0599+370-K0599+780 (OSIAO); | Region V | Region V | Completed | ₱144.2M | 100% | High risk81 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25FO0098BASIC EDUCATIONAL FACILITIES FUND (BEFF) - CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS - CONSTRUCTION OF SCHOOL BUILDING, MULADBUCAD GRANDE ELEMENTARY SCHOOL, BRGY. MULADBUCAD GRANDE, GUINOBATAN, ALBAY | Region V | Albay 3rd DEO | On-Going | ₱19.3M | 11% | High risk88 | Flagged0.060 |
| 2 | 17F00054NETWORK DEVELOPMENT-IMPROVEMENT/WIDENING OF NATIONAL ROADS-CONSTRUCTION OF MISSING GAPS CONNECTING NATIONAL ROADS, INCLUDING ROW-BACON-MANITO ROAD INCLUDING BRIDGE AND SLOPE PROTECTION, ROAD: K0595+514.35-K0596+763.35 (BANASI);K0599+370-K0599+780 (OSIAO); | Region V | Region V | Completed | ₱144.2M | 100% | High risk81 | Flagged0.001 |
| 3 | 16F00109MFO1-NATIONAL ROAD NETWORK SERVICES, NETWORK DEVELOPMENT: CONSTRUCTION OF MISSING GAPS CONNECTING NATIONAL ROADS, INCLUDING ROW, BACON-MANITO ROAD, BRIDGE COMPONENT, BACON, SORSOGON 1ST LD | Region V | Region V | Completed | ₱107.2M | 100% | High risk80 | —-0.007 |
| 4 | 20FA0011REHABILITATION OF SAN VICENTE FLOOD CONTROL, TABACO CITY, ALBAY | Region V | Albay 1st DEO | Completed | ₱93.3M | 100% | High risk68 | —-0.077 |
| 5 | 21I00049CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - CONSTRUCTION OF ROAD, BONGA - PAMAMAS-AN LINOOBAN - MARARANGSI - CALUYAHAN, STA. 0+000 TO STA. 1+570, STA. 7+100 TO STA. 10+327.44, MOTIONG, SAMAR | Region VIII | Region VIII | Completed | ₱207.2M | 100% | High risk66 | —-0.053 |
| 6 | 21I00053CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - CONSTRUCTION OF ROAD, BRGY. IBOL - BRGY. JIAN-AN, BRGY. PANGDAN, JIABONG AND CATBALOGAN CITY, SAMAR | Region VIII | Region VIII | Completed | ₱141M | 100% | High risk66 | —-0.073 |
| 7 | 17F00048MFO3-MAINT. & CONST. SERVICES OF OTHER INFRASTRUCTURES CONST./IMPR. OF ACCESS ROAD LEADING TO DECLARED TOURISM DESTINATIONS, CONST OF CONCRETE ROAD-CAGRARAY CIRCUMFERENTIAL ROAD, TAMBILAGAO-LANGATON AND CABASAN-NAPAO-TANAGA SECTION, ALBAY 1ST LD | Region V | Region V | Completed | ₱193M | 100% | High risk65 | —-0.022 |
| 8 | 22FB0163LOCAL PROGRAM: CONSTRUCTION OF EVACUATION CENTER/MULTI-PURPOSE BUILDING AT DARAGA COMMUNITY COLLEGE, DARAGA, ALBAY | Region V | Albay 2nd DEO | On-Going | ₱34.4M | 99% | High risk64 | —-0.043 |
| 9 | 20I00085CONSTRUCTION OF EVACUATION CENTER, BARANGAY TINAGO, CALBIGA, SAMAR | Region VIII | Region VIII | Completed | ₱34.7M | 100% | Medium risk56 | —-0.088 |
| 10 | 20IK0052CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. BURAY, PARANAS, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱5.8M | 100% | Medium risk51 | —-0.096 |
| 11 | 20IK0047CONSTRUCTION OF LEVEL III WATER SUPPLY SYSTEM, HINABANGAN, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱14.4M | 100% | Medium risk50 | —-0.057 |
| 12 | 21IK0036CONST. OF NEW BRIDGE-BURI BRIDGE ALONG BURI ACCESS ROAD, BRGY. SILANGA, CATBALOGAN CITY | Region VIII | Samar 2nd DEO | On-Going | ₱26.9M | 88% | Medium risk49 | Flagged0.006 |
| 13 | 18M00007ROAD WIDENING SARANGANI-DAVAO DEL SUR COASTAL ROADK1658+783-K1663+311, K1664+630-K1666+908, ALABEL AND MALAPATAN, SARANGANI PROVINCE | Region XII | Region XII | Completed | ₱188.8M | 100% | Medium risk45 | —-0.022 |
| 14 | 20IK0100REBLOCKING OF MUNICIPAL ROADS, BRGYS. BAYBAY, SALUD, LAWAAN, PALAYPAY, MERCADO, LOYO, BASEY, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱4.8M | 100% | Medium risk42 | —-0.044 |
| 15 | 20IK0053CONSTRUCTION OF BRGY. HALL, BRGY. TULAY, STA. RITA, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱2.4M | 84% | Low risk27 | —-0.021 |
| 16 | 20IK0054CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. POBLACION 6 , PARANAS, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱2.4M | 100% | Low risk27 | —-0.095 |
| 17 | 20IK0056REHAB. OF MULTI-PURPOSE BUILDING, BRGY. SAN PASCUAL, PARANAS, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱2.2M | 100% | Low risk26 | —-0.096 |