Contractor dossier
591 projects on file, including joint ventures this contractor is part of.
Total projects
591
Total budget
₱19.7B
Average progress
96.8%
Completion rate
91.5%
Average risk score
46.5
Medium risk on average, out of 100
Flagged as unusual
14
2.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 286 | ₱7.2B | 41.4 | 3 | 100.0% |
| Negros Island Region | 99 | ₱3B | 48.8 | 4 | 91.4% |
| Region V | 68 | ₱3.4B | 55.8 | 0 | 99.6% |
| Region IV-A | 34 | ₱1B | 50.0 | 0 | 87.0% |
| Region VI | 30 | ₱1.7B | 54.6 | 7 | 82.7% |
| Region X | 27 | ₱1.7B | 48.5 | 0 | 99.2% |
| Region IX | 25 | ₱955.5M | 56.6 | 0 | 100.0% |
| Region IV-B | 13 | ₱466.9M | 39.6 | 0 | 100.0% |
| Region VII | 6 | ₱120.4M | 47.2 | 0 | 100.0% |
| National Capital Region | 3 | ₱79.4M | 46.1 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 212 | ₱8.8B | 49.5 | 1 | 96.4% |
| Buildings and Facilities | 117 | ₱2.1B | 35.0 | 2 | 97.6% |
| Bridges | 112 | ₱3.2B | 47.6 | 5 | 95.3% |
| Flood Control and Drainage | 111 | ₱4.4B | 49.3 | 1 | 99.6% |
| Water Provision and Storage | 17 | ₱64.8M | 23.1 | 0 | 100.0% |
| OTHER | 12 | ₱531.4M | 76.7 | 0 | 100.0% |
| Bridges, Roads | 5 | ₱510.1M | 61.5 | 1 | 83.4% |
| GAA 2025 SSP | 4 | ₱39.4M | 89.8 | 4 | 59.1% |
| GAA 2025 OO-1 | 1 | ₱22.1M | 86.1 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25GN0064CONSTRUCTION OF ROAD AT BARANGAY GUINTORILAN, SAN ENRIQUE, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 4th DEO | On-Going | ₱9.9M | 36% | High risk94 | Flagged0.022 |
| 25GL0102CONSTRUCTION OF MUNICIPAL HALL - ANNEX BUILDING, ISABELA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | On-Going | ₱9.9M | 70% | High risk93 | Flagged0.013 |
| 25RD0095CONSTRUCTION OF ROADS (SITIO LIBOT LIBOT BRGY. PANDAN UP TO BRGY. PROPER), PONTEVEDRA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 4th DEO | On-Going | ₱9.8M | 78% | High risk93 | Flagged0.011 |
| 25GQ0016REHABILITATION/RECONSTRUCTION OF ROAD WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS, BACOLOD-MURCIA-DS BENEDICTO-SN CARLOS CITY RD. - K0049+092 - K0049+157 | Negros Island Region | Negros Occidental 5th DEO | Completed | ₱22.1M | 100% | High risk86 | —-0.030 |
| 20IB0083CONSTRUCTION OF MISSING LINKS/NEW ROADS ARTECHE - BRGY. CATUMSAN - JIPAPAD - LAS NAVAS - CATUBIG - RAWIS ROAD, JIPAPAD, EASTERN SAMAR | Region VIII | Eastern Samar DEO | Completed | ₱96.9M | 100% | High risk83 | —-0.023 |
| 20IF0011WIDENING OF PERMANENT BRIDGES, BACAN BR. (B00582LT) ALONG ORMOC-BAYBAY SOUTHERN LEYTE BDRY. ROAD | Region VIII | Leyte 4th DEO | Completed | ₱69.6M | 100% | High risk81 | —-0.035 |
| 17IL0071MAASIN CITY BYPASS ROAD CUM SEA WALL, MAASIN CITY, SOUTHERN LEYTE | Region VIII | Southern Leyte 1st DEO | Completed | ₱49M | 100% | High risk80 | —-0.036 |
| 25RE0012CONSTRUCTION OF ROAD OF BARANGAY CRUZ PASSING THRU BARANGAY MACASILAO, CALATRAVA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 5th DEO | On-Going | ₱9.9M | 52% | High risk79 | Flagged0.018 |
| 17FG0038INDV. PROJECT PAVING OF SHOULDERS WITH DRAINAGE IMPROVEMENT ALONG NABUA BALATAN ROAD, NABUA BALATAN, CAMARINES SUR K0 477+177 - K0477+440, K0483+000 - 483+591, K0 488+649 - K0 488+801, K0489+590 - K0489+800, K0491+332 - K0 491+622, K0 492+450 - KO 493+000 | Region V | Camarines Sur 5th DEO | Completed | ₱48.2M | 100% | High risk78 | —-0.037 |
| 17IC0024IMPROVEMENT/WIDENING OF NATIONAL ROADS ALONG DAANG MAHARLIKA (LT) (S00024LT) K0930+123 - K 0930+816, K0930+824 - K0930+911, K0930+921 - K0931+509, TELEGRAFO, TOLOSA, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱38.4M | 100% | High risk77 | —-0.038 |
| 19IF0098CONSTRUCTION OF MULTI-PURPOSE (MUNICIPAL) BUILDING, PHASE I, MATAG-OB, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱8.9M | 100% | High risk77 | —-0.038 |
| 17FG0039INDV. PROJ. REHAB./RECONST./UPGRADING DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE ALONG IRIGA CITY-SAN ISIDRO-SAGRADA-SAN RAMON-HANAWAN ROAD, IRIGA CITY K0 484+(-031.40)-K0 484+455, K0 485+(-020.80)-K0 485+108.80, K0 486+333-K0 487+000 | Region V | Camarines Sur 5th DEO | Completed | ₱18.6M | 100% | High risk76 | —-0.036 |
| 17FG0044INDV. PROJ. - CONCRETING OF MONTE-CALVARIO-IGBAC BARANGAY ROAD, MONTE-CALVARIO AND IGBAC, BUHI, CAMARINES SUR STA. 00+000-STA. 00+105, STA. 00+165-STA. 00+298, STA. 00+379-STA. 00+733 | Region V | Camarines Sur 5th DEO | Completed | ₱9.4M | 100% | High risk76 | —-0.035 |
| 18JI0054RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES AT SAN JOSE BR. (B00481MN) ALONG LANAO-PAGADIAN-ZAMBOANGA CITY RD | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱33.2M | 100% | High risk76 | —-0.029 |
| 21FJ0017OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, APP - REHAB/RECONSTRUCTION OF NATIONAL ROADS W/ SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - MASBATE-CATAINGAN-PLACER RD - K0072+984 - K0073+498 | Region V | Masbate 3rd DEO | Completed | ₱33.3M | 100% | High risk74 | —-0.033 |
| 17D00039MFO-1 NATIONAL ROAD NETWROK SERVICES CONST. & MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS REPLACEMENT OF PERMANENT WEAK BRIDGES PRINCESA BR. (B02425LZ) ALONG LUCENA-TAYABAS-LUCBAN-SAMPALOC-MAUBAN PORT ROAD, QUEZON | Region IV-A | Region IV-A | Completed | ₱86.8M | 100% | High risk74 | —-0.009 |
| 17G00058CONST. OF CONCRETE ROAD - BRGY. SAN ANTONIO - CONDEZ - SAN LUIS - SAN VICENTE - FLORES ROAD LEADING | Region VI | Region VI | Completed | ₱134.8M | 100% | High risk73 | —-0.010 |
| 18J00012CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS, LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - ACCESS ROAD AT SITIO ANULING, PAMUCUTAN TO STA. RITA IN SUPPORT OF HIGH VALUE CROPS (ABACA, CACAO, RUBBER AND COFFEE) UPPER LA PAZ, ZAMBOANGA CITY | Region IX | Region IX | Completed | ₱118M | 100% | High risk73 | —-0.049 |
| 20F00021LOCAL PROGRAM: CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-LOCAL ROADS AND BRIDGES-LOCAL ROADS, CONSTRUCTION OF ROAD WITH SEAWALL, BARANGAY TABA-TABA TO BARANGAY MANGCAMAGONG, BASUD, CAMARINES NORTE, B | Region V | Region V | Completed | ₱144.8M | 100% | High risk72 | —-0.043 |
| 24GG0195CONSTRUCTION OF MULTI - PURPOSE FACILITY, BRGY. BADIANG, ANILAO, ILOILO | Region VI | Iloilo 2nd DEO | Completed | ₱12.8M | 100% | High risk70 | —-0.058 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 19G00109BACOLOD NEGROS OCCIDENTAL ECONOMIC HIGHWAY (BANOCEH), SEGMENT 3, INCLUDING ROW, BACOLOD CITY | Region VI | Region VI | On-Going | ₱85.3M | 14% | Medium risk56 | Flagged0.067 |
| 22G00062BACOLOD NEGROS OCCIDENTAL ECONOMIC HIGHWAY (BANOCEH), SEGMENT 3, BACOLOD CITY | Region VI | Region VI | On-Going | ₱69.4M | 50% | Medium risk53 | Flagged0.022 |
| 25GN0064CONSTRUCTION OF ROAD AT BARANGAY GUINTORILAN, SAN ENRIQUE, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 4th DEO | On-Going | ₱9.9M | 36% | High risk94 | Flagged0.022 |
| 25RE0012CONSTRUCTION OF ROAD OF BARANGAY CRUZ PASSING THRU BARANGAY MACASILAO, CALATRAVA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 5th DEO | On-Going | ₱9.9M | 52% | High risk79 | Flagged0.018 |
| 25GL0102CONSTRUCTION OF MUNICIPAL HALL - ANNEX BUILDING, ISABELA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | On-Going | ₱9.9M | 70% | High risk93 | Flagged0.013 |
| 25RD0095CONSTRUCTION OF ROADS (SITIO LIBOT LIBOT BRGY. PANDAN UP TO BRGY. PROPER), PONTEVEDRA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 4th DEO | On-Going | ₱9.8M | 78% | High risk93 | Flagged0.011 |
| 23G00044BACOLOD NEGROS OCCIDENTAL ECONOMIC HIGHWAY (BANOCEH), SECTION 1, SEGMENT 3, PHASE 4, TALISAY CITY, NEGROS OCCIDENTAL | Region VI | Region VI | On-Going | ₱67.7M | 62% | Medium risk53 | Flagged0.010 |
| 23G00055BACOLOD NEGROS OCCIDENTAL ECONOMIC HIGHWAY (BANOCEH), SECTION 2, BACOLOD CITY | Region VI | Region VI | On-Going | ₱104.8M | 17% | High risk64 | Flagged0.007 |
| 21G00051CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG ILOG - HILABANGAN RIVER, KABANKALAN CITY, NEGROS OCCIDENTAL | Region VI | Region VI | On-Going | ₱91.7M | 93% | Medium risk56 | Flagged0.005 |
| 18IB0193CONSTRUCTION OF VILLAHERMOSA BRIDGE, INCLUDING ROAD COMPONENT, DOLORES, MASLOG, EASTERN SAMAR | Region VIII | Eastern Samar DEO | Completed | ₱25.5M | 100% | Medium risk48 | Flagged0.005 |
| 18IB0191CONSTRUCTION OF HINOLASO BRIDGE II, INCLUDING ROAD COMPONENT, DOLORES, MASLOG, EASTERN SAMAR | Region VIII | Eastern Samar DEO | Completed | ₱22.5M | 100% | Medium risk48 | Flagged0.002 |
| 18IB0192CONSTRUCTION OF HINOLASO BRIDGE I, INCLUDING ROAD COMPONENT, DOLORES, MASLOG, EASTERN SAMAR | Region VIII | Eastern Samar DEO | Completed | ₱17.6M | 100% | Medium risk48 | Flagged0.001 |
| 16GB0215CONSTRUCTION OF 4 STOREY TWENTY FOUR(24) CLASSROOM SCHOOL BUILDING AT ANTIQUE NS, SAN JOSE(CAPITAL), | Region VI | Antique DEO | Completed | ₱34.7M | 100% | Medium risk50 | Flagged0.001 |
| 16GB0216CONSTRUCTION OF 4 STOREY TWENTY(20) CLASSROOM SCHOOL BUILDING AT ANTIQUE NS, SAN JOSE(CAPITAL), ANTI | Region VI | Antique DEO | Completed | ₱30.2M | 100% | Medium risk50 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 201 | 20IF0051CONSTRUCTION OF MULTI- PURPOSE BUILDING, BRGY. SAN JUAN, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱7.5M | 100% | Medium risk50 | —-0.098 |
| 202 | 21IF0044CONSTRUCTION OF MULTI-PURPOSE BUILDING-CONSTRUCTION OF EVACUATION CENTER, BARANGAY PUERTOBELLO, MERIDA, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱6.6M | 100% | Medium risk50 | —-0.098 |
| 203 | 21IF0067CONSTRUCTION OF MULTI-PURPOSE BUILDING- CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY CASILDA, MERIDA LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱9.4M | 100% | Medium risk50 | —-0.098 |
| 204 | 18IB0164CONSTRUCTION OF 9-UNITS, 1-STOREY WORKSHOP BUILDING (STANDARD TECHNICAL VOCATIONAL BUILDING) AT LAWAAN NATIONAL SCHOOL OF CRAFTMANSHIP AND INDUSTRIES, LAWAAN, EASTERN SAMAR | Region VIII | Eastern Samar DEO | Completed | ₱32.7M | 100% | Medium risk50 | —-0.045 |
| 205 | 21IF0027CONSTRUCTION OF MULTI-PURPOSE BUILDING - CONSTRUCTION OF MULTI-PURPOSE BUILDING, RURAL HEALTH UNIT, ISABEL MUNICIPAL HEALTH OFFICE, ISABEL, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱9.4M | 100% | Medium risk50 | —-0.098 |
| 206 | 21IA0072WIDENING OF PERMANENT BRIDGES- MOOG BRIDGE (B00029BR) ALONG BILIRAN CIRCUMFERENTIAL RD.(124.44945°, 11.48794°) | Region VIII | Biliran DEO | Completed | ₱30.6M | 100% | Medium risk50 | —-0.049 |
| 207 | 24GL0063ROAD WIDENING - JCT BAGONAWA-LA CASTELLANA-ISABELA RD - K0069 + 000 - K0070 + 290 | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱52M | 100% | Medium risk50 | —-0.088 |
| 208 | 18IL0168CONSTRUCTION OF 3 STY- 15 CL SCHOOL BUILDING @ LILOAN NATIONAL TECHNICAL VOCATIONAL HIGH SCHOOL (SCH. ID 313409)-BLDG. 2 | Region VIII | Southern Leyte 1st DEO | Completed | ₱46.8M | 100% | Medium risk50 | —-0.039 |
| 209 | 20G00020WIDENING OF BRIDGE - CAUAYAN BR. (B00227NR) ALONG BACOLOD SOUTH RD (KABANKALAN-HINOBAAN SECTION) | Region VI | Region VI | Completed | ₱50.7M | 100% | Medium risk50 | —-0.028 |
| 210 | 20KL0043CONSTRUCTION OF FLOOD CONTROL AT POBLACION LUGAIT, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | Completed | ₱66.5M | 100% | Medium risk50 | —-0.078 |
| 211 | 22IF0046CONSTRUCTION OF MULTI PURPOSE BUILDING -CONSTRUCTION OF EVACUATION CENTER, BRGY. CONSOLACION, ISABEL LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱6.9M | 100% | Medium risk50 | —-0.098 |
| 212 | 21IA0087WIDENING OF PERMANENT BRIDGES- BUSALI BR. (B00030BR) ALONG BILIRAN CIRCUMFERENTIAL RD.(124.44816°, 11.49123°) | Region VIII | Biliran DEO | Completed | ₱20.5M | 100% | Medium risk49 | —-0.051 |
| 213 | 20IF0052CONSTRUCTION OF MULTI- PURPOSE BUILDING, BRGY. TOLINGON, ISABEL, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱7.5M | 100% | Medium risk49 | —-0.096 |
| 214 | 23G00048BACOLOD NEGROS OCCIDENTAL ECONOMIC HIGHWAY (BANOCEH), SECTION 2, PACKAGE A, BACOLOD CITY | Region VI | Region VI | On-Going | ₱50.2M | 39% | Medium risk49 | —-0.021 |
| 215 | 23GJ0012(RE-BID)-CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD - LA PAZ DEEP SEA WATER PORT RD. - (S00504PN) K0003+466.34 - K0004+037 | Region VI | Iloilo City DEO | On-Going | ₱48.5M | 79% | Medium risk49 | —-0.035 |
| 216 | 22IA0095WIDENING OF PERMANENT BRIDGES- DISPO BR. (B00053BR) ALONG NAVAL-CAIBIRAN CROSS COUNTRY RD. (124.414625, 11.569176) | Region VIII | Biliran DEO | Completed | ₱10.4M | 100% | Medium risk49 | —-0.055 |
| 217 | 25GK0154CONSTRUCTION OF BRIDGE AT BRGY. XI, VICTORIAS CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 1st DEO | On-Going | ₱49.3M | 51% | Medium risk49 | —-0.025 |
| 218 | 25GO0143INSTALLATION OF SOLAR PAVEMENT STUDS ALONG BACOLOD NORTH ROAD (S00078NR) - K0000 + 000 TO K0004 + 267 | Negros Island Region | Bacolod City DEO | On-Going | ₱48.8M | 52% | Medium risk49 | —-0.057 |
| 219 | 22G00051CONSTRUCTION OF FLOOD CONTROL STRUCTURE OF HIMOGA-AN RIVER ALONG BACOLOD NORTH ROAD, SAGAY CITY, NEGROS OCCIDENTAL | Region VI | Region VI | Completed | ₱48.3M | 100% | Medium risk49 | —-0.070 |
| 220 | 22G00066CONSTRUCTION OF REVETMENT WITH FLOODWALL INCLUDING IMPROVEMENT OF RIVERBANK (WITH ESPLANADE) IN CATMON CREEK, BACOLOD CITY | Region VI | Region VI | On-Going | ₱48.3M | 100% | Medium risk49 | —-0.014 |
| 221 | 25GO0144INSTALLATION OF SOLAR PAVEMENT STUDS ALONG BACOLOD SOUTH ROAD (S00132NR) - K0000 + 000 TO K0004 + 085 | Negros Island Region | Bacolod City DEO | On-Going | ₱48.8M | 32% | Medium risk49 | —-0.049 |
| 222 | 20IB0104PREVENTIVE MAINTENANCE - SECONDARY ROADS JCT. BUENAVISTA - LAWAAN - MARABUT ROAD K0952+(-828) - K0953+397 | Region VIII | Eastern Samar DEO | Completed | ₱29.4M | 100% | Medium risk49 | —-0.094 |
| 223 | 23KL0039CONSTRUCTION OF ROAD AT MANTICAO TO OPOL ROAD, MANTICAO, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | Completed | ₱49M | 100% | Medium risk49 | —-0.094 |
| 224 | 20IB0103REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, SECONDARY ROAD BORONGAN - GUIUAN ROAD, K01000+536 - K01000+714, K01001+728 - K01001+940 | Region VIII | Eastern Samar DEO | Completed | ₱30.9M | 100% | Medium risk49 | —-0.094 |
| 225 | 20GK0196CONSTRUCTION OF BRIDGE - CONSTRUCTION OF NANCA-CUDANGDANG BRIDGE, EB MAGALONA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 1st DEO | Completed | ₱49M | 100% | Medium risk49 | —-0.042 |