Contractor dossier
224 projects on file, including joint ventures this contractor is part of.
Total projects
224
Total budget
₱7.1B
Average progress
96.7%
Completion rate
90.2%
Average risk score
37.2
Medium risk on average, out of 100
Flagged as unusual
4
1.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 163 | ₱6B | 33.9 | 1 | 97.3% |
| Region I | 49 | ₱828.2M | 47.1 | 3 | 93.9% |
| National Capital Region | 8 | ₱35.3M | 36.0 | 0 | 100.0% |
| Region IV-A | 4 | ₱154.3M | 50.8 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 95 | ₱4.3B | 40.5 | 2 | 97.8% |
| Roads | 74 | ₱2.2B | 36.1 | 1 | 96.7% |
| Buildings and Facilities | 50 | ₱372.1M | 32.0 | 1 | 94.4% |
| Bridges | 3 | ₱22.4M | 35.4 | 0 | 100.0% |
| OTHER | 2 | ₱113.5M | 50.7 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CD0076REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG MARILAO RIVER, SAOG - LAMBAKIN SECTION, STA. 08+600 - STA. 08+860, MARILAO, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱47.5M | 94% | High risk74 | —-0.033 |
| 25CD0075REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG MARILAO RIVER, SAOG - LAMBAKIN SECTION, STA. 08+500 - STA. 08+680, MARILAO, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱47.5M | 95% | High risk74 | —-0.035 |
| 22CJ0152CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM - TIKAS) CONSTRUCTION OF OFFICERS QUARTERS AND EP BARRACKS, ISAFP, CAMP SERVILLANO AQUINO, TARLAC CITY | Region III | Tarlac DEO | Completed | ₱9.7M | 100% | High risk71 | —-0.071 |
| 22CJ0117CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM - TIKAS) CONSTRUCTION OF AFP RESERVE CENTERS (AFPRCENS), CAMP SERVILLANO AQUINO, TARLAC CITY | Region III | Tarlac DEO | Completed | ₱14.5M | 100% | High risk70 | —-0.069 |
| 20CJ0070NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADS STA. IGNACIA - GUIMBA ROAD VIA GERONA PURA, (STA. IGNACIA SECTION), PACKAGE 2, TARLAC | Region III | Tarlac DEO | Completed | ₱65.3M | 100% | High risk70 | —-0.035 |
| 25CD0071REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG MARILAO RIVER, SAOG - LAMBAKIN SECTION, STA. 08+860 - STA. 09+040, MARILAO, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱25.2M | 100% | High risk69 | —-0.037 |
| 16CK0176ASSETS PRESERV. OF NATL RDS- CONST/UPGR/REHAB OF DRAINAGE ALONG MANILA NORTH ROAD, BAMBAN AND CAPAS, | Region III | Tarlac 2nd DEO | Completed | ₱14M | 100% | High risk68 | —-0.068 |
| 17AJ0024CONSTRUCTION OF PROTECTION WORKS ALONG INGALERA RIVER, LASIP-BUTAO CREEK (TRIBUTARY), MALASIQUI, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱16M | 100% | High risk65 | —-0.049 |
| 18CJ0020CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG RIO CHICO RIVER, VICTORIA, TARLAC | Region III | Tarlac DEO | Completed | ₱28.4M | 100% | High risk65 | —-0.060 |
| 24D00027CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGOS RIVER, BARANGAY MAIGANG, GENERAL NAKAR, QUEZON | Region IV-A | Region IV-A | On-Going | ₱96.5M | 100% | High risk64 | —-0.038 |
| 21CL0107CONCRETING OF BRGY. BOLINTIN FMR, BRGY. BOLINTIN, MASINLOC, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱12.1M | 100% | High risk62 | —-0.004 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24C00647BASIC EDUCATIONAL FACILITIES FUND (BEFF) BATCH 1 - CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATION FACILITIES FUND - CONSTRUCTION OF 2 STOREY 8 -CLASSROOM SCHOOL BUILDING IN SIBUL ELEMENTARY SCHOOL, SAN MIGUEL, BUL. | Region III | Region III | On-Going | ₱37.8M | 0% | Medium risk48 | Flagged0.034 |
| 25AI0148CONCRETING OF FMR AT BRGY. CAMANANG, URDANETA CITY, PANGASINAN | Region I | Pangasinan 3rd DEO | On-Going | ₱9.6M | 0% | Medium risk45 | Flagged0.029 |
| 17AI0032REPAIR/REHAB OF DAMAGED RIVER BANK PROTECTION ALONG LAGASIT RIVER CONTROL PROJ BRGY. STA. CRUZ, STA. | Region I | Pangasinan 3rd DEO | Completed | ₱17.1M | 100% | Medium risk58 | Flagged0.003 |
| 17AI0034REPAIR/REHABILITATION OF DAMAGED RIVER BANK PROTECTION ALONG CABULANDAYAN RCP, BRGY. NINING, SAN NIC | Region I | Pangasinan 3rd DEO | Completed | ₱13.4M | 100% | Medium risk57 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 22AI0137CONSTRUCTION OF SLOPE PROTECTION ALONG BANILA RIVER, BALUNGAO-ROSALES, PANGASINAN (PACKAGE 1) | Region I | Pangasinan 3rd DEO | Completed | ₱45.5M | 100% | Medium risk48 | —-0.074 |
| 52 | 22AI0148CONSTRUCTION OF SLOPE PROTECTION ALONG BANILA RIVER, BALUNGAO-ROSALES, PANGASINAN (PACKAGE 2) | Region I | Pangasinan 3rd DEO | Completed | ₱45.4M | 100% | Medium risk48 | —-0.073 |
| 53 | 22AI0094CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BANILA RIVER, BRGY. CABALITIAN, UMINGAN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱19.4M | 100% | Medium risk47 | —-0.071 |
| 54 | 18AI0131CONSTN/EXTENSION OF BANK PROTECTION, BRGY. LIBERTAD (TAYUG) - BURGOS (NATIVIDAD), PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱23.9M | 100% | Medium risk47 | —-0.074 |
| 55 | 18AI0141CONSTN/EXTENSION OF BANK PROTECTION, BRGY. STA. CRUZ, STA. MARIA, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱14.4M | 100% | Medium risk47 | —-0.076 |
| 56 | 20AI0040CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LAGASIT RIVER, BRGY. BALIGAYAN, SAN QUINTIN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱18.6M | 100% | Medium risk47 | —-0.073 |
| 57 | 18AI0146CONSTN OF TWO UNITS OF SPURDIKES USING GABIONS/MATTRESSES, AGNO RIVER CTRL PROJ, LEGASPI, TAYUG, PAN | Region I | Pangasinan 3rd DEO | Completed | ₱23.3M | 100% | Medium risk47 | —-0.075 |
| 58 | 19AI0135CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LAGASIT RIVER, BRGY. BALIGAYAN, SAN QUINTIN, PANGASINA | Region I | Pangasinan 3rd DEO | Completed | ₱18.6M | 100% | Medium risk47 | —-0.075 |
| 59 | 18AI0126CONSTN/EXTENSION OF BANK PROTECTION, BRGY. BANTOG-CASANTAMARIAAN, SAN QUINTIN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱19.1M | 100% | Medium risk47 | —-0.075 |
| 60 | 19AI0246CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DEPALO RIVER, BRGY. BANTOG, SAN QUINTIN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱18.6M | 100% | Medium risk47 | —-0.075 |
| 61 | 18AI0149CONSTN/EXTENSION OF BANK PROTECTION, AGNO RIVER CTRL PROJECT, BRGY. AGNO, TAYUG, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱24M | 100% | Medium risk47 | —-0.075 |
| 62 | 19AI0253CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LAGASIT RIVER, BRGY. STA. CRUZ, STA. MARIA, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱9.3M | 100% | Medium risk47 | —-0.076 |
| 63 | 24AI0035CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TOTONOGUEN RIVER, BRGY. ZONE 5, ROSALES, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱22.5M | 100% | Medium risk47 | —-0.075 |
| 64 | 19AI0036CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BANILA RIVER, BRGY. DECRETO, UMINGAN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱19.5M | 100% | Medium risk47 | —-0.075 |
| 65 | 18AI0159CONSTN/EXTENSION OF BANK PROTECTION, AGNO RIVER CTRL PROJ-BRGY. ZONE III-TOMANA EAST, ROSALES, PANGA | Region I | Pangasinan 3rd DEO | Completed | ₱22.3M | 100% | Medium risk47 | —-0.075 |
| 66 | 18DD0516LOCAL PROGRAM, CONSTRUCTION/REPAIR/REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, LOCAL ROADS AND BRIDGES, LOCAL ROADS, CONSTRUCTION/REHABILITATION OF ROAD AND DRAINAGE SYSTEM OF BRGYS. BANAY-BANAY 1, BANAY-BANAY 2, BALAGT | Region IV-A | Batangas 4th DEO | Completed | ₱19.4M | 100% | Medium risk47 | —-0.109 |
| 67 | 18DD0601ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION/ REHABILITATION OF DRAINAGE SYSTEM INCLUDING BOX CULVERT IN B | Region IV-A | Batangas 4th DEO | Completed | ₱19M | 100% | Medium risk46 | —-0.090 |
| 68 | 23AI0101CONCRETING/REHABILITATION OF ROADS, POBLACION-AGNO, TAYUG, PANGASINAN | Region I | Pangasinan 3rd DEO | On-Going | ₱24.5M | 84% | Medium risk46 | —-0.037 |
| 69 | 18DD0517LOCAL PROGRAM, CONSTRUCTION/REPAIR/REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, LOCAL ROADS AND BRIDGES, LOCAL ROADS, CONSTRUCTION/REHABILITATION OF ROAD AND DRAINAGE SYSTEM, BRGY. BANABA, BUKAL, CASTILLO, TANGOB, CAWONG | Region IV-A | Batangas 4th DEO | Completed | ₱19.4M | 100% | Medium risk46 | —-0.109 |
| 70 | 23AI0100CONSTRUCTION/REHABILITATION OF ROADS, POBLACION - CASARATAN, SAN NICOLAS, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱14.6M | 100% | Medium risk46 | —-0.091 |
| 71 | 18AI0200CONCRETING OF BRGY. SAN ROQUE-SAN JOSE FMR, BRGY. SAN ROQUE AND BRGY. SAN JOSE, SAN NICOLAS, PANGASI | Region I | Pangasinan 3rd DEO | Completed | ₱6.6M | 100% | Medium risk46 | —-0.037 |
| 72 | 24AI0100CONSTRUCTION OF ROAD, BRGY. BOLAOEN, URDANETA CITY, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱9.8M | 100% | Medium risk46 | —-0.091 |
| 73 | 22AI0158CONSTRUCTION/REHABILITATION OF ROADS, SAN NICOLAS, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱19M | 100% | Medium risk45 | —-0.089 |
| 74 | 25AI0148CONCRETING OF FMR AT BRGY. CAMANANG, URDANETA CITY, PANGASINAN | Region I | Pangasinan 3rd DEO | On-Going | ₱9.6M | 0% | Medium risk45 | Flagged0.029 |
| 75 | 18AJ0027CONSTRUCTION OF PROTECTION WORKS ALONG ANGALACAN RIVER, CORAL SECTION, MAPANDAN, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱23.3M | 100% | Medium risk45 | —-0.073 |