Contractor dossier
224 projects on file, including joint ventures this contractor is part of.
Total projects
224
Total budget
₱7.1B
Average progress
96.7%
Completion rate
90.2%
Average risk score
37.2
Medium risk on average, out of 100
Flagged as unusual
4
1.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 163 | ₱6B | 33.9 | 1 | 97.3% |
| Region I | 49 | ₱828.2M | 47.1 | 3 | 93.9% |
| National Capital Region | 8 | ₱35.3M | 36.0 | 0 | 100.0% |
| Region IV-A | 4 | ₱154.3M | 50.8 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 95 | ₱4.3B | 40.5 | 2 | 97.8% |
| Roads | 74 | ₱2.2B | 36.1 | 1 | 96.7% |
| Buildings and Facilities | 50 | ₱372.1M | 32.0 | 1 | 94.4% |
| Bridges | 3 | ₱22.4M | 35.4 | 0 | 100.0% |
| OTHER | 2 | ₱113.5M | 50.7 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CD0076REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG MARILAO RIVER, SAOG - LAMBAKIN SECTION, STA. 08+600 - STA. 08+860, MARILAO, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱47.5M | 94% | High risk74 | —-0.033 |
| 25CD0075REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG MARILAO RIVER, SAOG - LAMBAKIN SECTION, STA. 08+500 - STA. 08+680, MARILAO, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱47.5M | 95% | High risk74 | —-0.035 |
| 22CJ0152CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM - TIKAS) CONSTRUCTION OF OFFICERS QUARTERS AND EP BARRACKS, ISAFP, CAMP SERVILLANO AQUINO, TARLAC CITY | Region III | Tarlac DEO | Completed | ₱9.7M | 100% | High risk71 | —-0.071 |
| 22CJ0117CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM - TIKAS) CONSTRUCTION OF AFP RESERVE CENTERS (AFPRCENS), CAMP SERVILLANO AQUINO, TARLAC CITY | Region III | Tarlac DEO | Completed | ₱14.5M | 100% | High risk70 | —-0.069 |
| 20CJ0070NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADS STA. IGNACIA - GUIMBA ROAD VIA GERONA PURA, (STA. IGNACIA SECTION), PACKAGE 2, TARLAC | Region III | Tarlac DEO | Completed | ₱65.3M | 100% | High risk70 | —-0.035 |
| 25CD0071REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG MARILAO RIVER, SAOG - LAMBAKIN SECTION, STA. 08+860 - STA. 09+040, MARILAO, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱25.2M | 100% | High risk69 | —-0.037 |
| 16CK0176ASSETS PRESERV. OF NATL RDS- CONST/UPGR/REHAB OF DRAINAGE ALONG MANILA NORTH ROAD, BAMBAN AND CAPAS, | Region III | Tarlac 2nd DEO | Completed | ₱14M | 100% | High risk68 | —-0.068 |
| 17AJ0024CONSTRUCTION OF PROTECTION WORKS ALONG INGALERA RIVER, LASIP-BUTAO CREEK (TRIBUTARY), MALASIQUI, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱16M | 100% | High risk65 | —-0.049 |
| 18CJ0020CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG RIO CHICO RIVER, VICTORIA, TARLAC | Region III | Tarlac DEO | Completed | ₱28.4M | 100% | High risk65 | —-0.060 |
| 24D00027CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGOS RIVER, BARANGAY MAIGANG, GENERAL NAKAR, QUEZON | Region IV-A | Region IV-A | On-Going | ₱96.5M | 100% | High risk64 | —-0.038 |
| 21CL0107CONCRETING OF BRGY. BOLINTIN FMR, BRGY. BOLINTIN, MASINLOC, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱12.1M | 100% | High risk62 | —-0.004 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24C00647BASIC EDUCATIONAL FACILITIES FUND (BEFF) BATCH 1 - CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATION FACILITIES FUND - CONSTRUCTION OF 2 STOREY 8 -CLASSROOM SCHOOL BUILDING IN SIBUL ELEMENTARY SCHOOL, SAN MIGUEL, BUL. | Region III | Region III | On-Going | ₱37.8M | 0% | Medium risk48 | Flagged0.034 |
| 25AI0148CONCRETING OF FMR AT BRGY. CAMANANG, URDANETA CITY, PANGASINAN | Region I | Pangasinan 3rd DEO | On-Going | ₱9.6M | 0% | Medium risk45 | Flagged0.029 |
| 17AI0032REPAIR/REHAB OF DAMAGED RIVER BANK PROTECTION ALONG LAGASIT RIVER CONTROL PROJ BRGY. STA. CRUZ, STA. | Region I | Pangasinan 3rd DEO | Completed | ₱17.1M | 100% | Medium risk58 | Flagged0.003 |
| 17AI0034REPAIR/REHABILITATION OF DAMAGED RIVER BANK PROTECTION ALONG CABULANDAYAN RCP, BRGY. NINING, SAN NIC | Region I | Pangasinan 3rd DEO | Completed | ₱13.4M | 100% | Medium risk57 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 23CJ0349CONSTRUCTION OF BY-PASS AND DIVERSION ROADS CRUZ-CALIBUNGAN DIVERSION ROAD, VICTORIA, TARLAC | Region III | Tarlac DEO | Completed | ₱47.1M | 100% | Medium risk35 | —-0.034 |
| 102 | 18CJ0264REHABILITATION/ CONSTRUCTION OF PROVINCIAL ROAD, BRGY. BIRBIRA - BRGY. BACSAY SECTION, CAMILING, TARLAC | Region III | Tarlac DEO | Completed | ₱46.3M | 100% | Medium risk35 | —-0.097 |
| 103 | 19CC0136CONSTRUCTION OF REVETMENT AT TIBAG, PULILAN, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱57.3M | 100% | Medium risk35 | —-0.090 |
| 104 | 23CJ0208BASIC INFRASTRUCTURE PROGRAM (BIP) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION OF ROAD SLOPE PROTECTION ALONG SAN JOSE, TARLAC-PALAUIG, ZAMBALES ROAD (PACKAGE 5), SAN JOSE, TAR | Region III | Tarlac DEO | Completed | ₱19.6M | 100% | Medium risk34 | —-0.100 |
| 105 | 23CJ0014FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF SLOPE PROTECTION WITH STEEL SHEET PILE FOUNDATION ALONG DELINQUENTE CREEK, BACABAC SECTION (PACKAGE 1), CAMILING, TARLAC | Region III | Tarlac DEO | Completed | ₱48.1M | 100% | Medium risk34 | —-0.084 |
| 106 | 22CJ0015FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CAMILING RIVER (LEFT BANK), LIBUEG-BACABAC SECTION (PACKAGE D), STA. 0+249 - | Region III | Tarlac DEO | Completed | ₱48.4M | 100% | Medium risk34 | —-0.086 |
| 107 | 21CJ0076CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS CONSTRUCTION OF TACTICAL HEADQUARTERS BUILDING AT TACTICAL OPERATIONS GROUP 3, TARLAC | Region III | Tarlac DEO | Completed | ₱23.4M | 100% | Medium risk34 | —-0.100 |
| 108 | 23CJ0229BASIC INFRASTRUCTURE PROGRAM (BIP) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION OF ROAD, BARANGAY SAPANG MARAGUL, TARLAC CITY, TARLAC | Region III | Tarlac DEO | Completed | ₱33.9M | 100% | Medium risk34 | —-0.101 |
| 109 | 25CJ0047CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG RIO CHICO RIVER, SEGMENT 27, VICTORIA, TARLAC | Region III | Tarlac DEO | Completed | ₱64.4M | 100% | Medium risk34 | —-0.088 |
| 110 | 19CJ0074NETWORK DEVELOPMENT PROGRAM ROAD WIDENING CAPAS-SAN JOSE-MAYANTOC-MALACAMPA RD - K0136 + 808 - K0138 + 343 | Region III | Tarlac DEO | Completed | ₱28.6M | 100% | Medium risk34 | —-0.099 |
| 111 | 18CJ0147NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MNR TO TARLAC-SAN MIGUEL VIA. MACABULOS ROAD, INCL. DRAINAGE, TARLAC | Region III | Tarlac DEO | Completed | ₱46.6M | 100% | Medium risk34 | —-0.098 |
| 112 | 23CJ0133FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS CONSTRUCTION OF SLOPE PROTECTION WITH STEEL SHEET PILE FOUNDATION ALONG CAMILING RIVER RIGHT BANK, CACAMILINGAN SUR-CACAMIL | Region III | Tarlac DEO | Completed | ₱49M | 100% | Medium risk34 | —-0.086 |
| 113 | 23CJ0134FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS CONSTRUCTION OF SLOPE PROTECTION WITH STEEL SHEET PILE FOUNDATION ALONG CAMILING RIVER, RIGHT BANK, SURGUI 1ST - CACAMILING | Region III | Tarlac DEO | Completed | ₱48M | 100% | Medium risk34 | —-0.086 |
| 114 | 18CJ0101CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS CONSTRUCTION OF BARANGAY SAN LUIS - BARANGAY SAN JOSE DE URQUICO ROAD, BARANGAYS SAN LUIS AND SAN JOSE DE URQUICO, TARLAC CITY | Region III | Tarlac DEO | Completed | ₱23.7M | 100% | Medium risk33 | —-0.103 |
| 115 | 23CJ0141BASIC INFRASTRUCTURE PROGRAM (BIP) FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES CONSTRUCTION OF SLOPE PROTECTION WITH STEEL SHEET PILE FOUNDATION AND ROAD COMPONENT ALONG CAMILING RIVER LEFT BANK, ANOLING 3RD TO PAO 1ST SECTION | Region III | Tarlac DEO | Completed | ₱48.1M | 100% | Medium risk33 | —-0.087 |
| 116 | 23CJ0139BASIC INFRASTRUCTURE PROGRAM (BIP) FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES CONSTRUCTION OF SLOPE PROTECTION WITH STEEL SHEET PILE FOUNDATION AND ROAD COMPONENT ALONG CAMILING RIVER LEFT BANK, ANOLING 3RD TO PAO 1ST SECTION | Region III | Tarlac DEO | Completed | ₱48M | 100% | Medium risk33 | —-0.087 |
| 117 | 23CJ0008FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF SLOPE PROTECTION WITH STEEL SHEET PILE FOUNDATION ALONG CAMILING RIVER, LEFT BANK, ANOLING 1ST TO PAO 1ST SECTION (PACKAGE A), CAMILING, | Region III | Tarlac DEO | Completed | ₱48.1M | 100% | Medium risk33 | —-0.087 |
| 118 | 23CJ0011FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS CONSTRUCTION OF SLOPE PROTECTION WITH STEEL SHEET PILE FOUNDATION ALONG CAMILING RIVER, LEFT BANK, ANOLING 1ST TO PAO 1ST S | Region III | Tarlac DEO | Completed | ₱48.1M | 100% | Medium risk33 | —-0.087 |
| 119 | 25CJ0035REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS MANILA NORTH RD - K0126 + 460 - K0127 + 337 | Region III | Tarlac DEO | On-Going | ₱45.9M | 98% | Medium risk33 | —-0.069 |
| 120 | 22CJ0014FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG TARLAC RIVER CONTROL (RIGHT DIKE), TAGUMBAO-DICOLOR SECTION (PACKAGE B), STA. 0+000 - STA. 0+313, GERONA | Region III | Tarlac DEO | Completed | ₱47.5M | 100% | Medium risk33 | —-0.087 |
| 121 | 23CJ0003FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF SLOPE PROTECTION WITH STEEL SHEET PILE FOUNDATION ALONG TARLAC RIVER CONTROL LEFT DIKE, BRILLANTE-RANG-AYAN SECTION (PACKAGE G | Region III | Tarlac DEO | Completed | ₱48.1M | 100% | Medium risk33 | —-0.087 |
| 122 | 23CJ0016FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS CONSTRUCTION OF SLOPE PROTECTION WITH STEEL SHEET PILE FOUNDATION ALONG TARLAC RIVER CONTROL LEFT DIKE, SAN JOSE-SAN BARTOL | Region III | Tarlac DEO | Completed | ₱48M | 100% | Medium risk33 | —-0.088 |
| 123 | 20CJ0067CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY CONSTRUCTION OF MULTIPURPOSE HALL, CAMP GENERAL SERVILLANO A. AQUINO, SAN MIGUEL, TARLAC CITY, TARLAC | Region III | Tarlac DEO | Completed | ₱16M | 100% | Medium risk33 | —-0.103 |
| 124 | 25CK0006ASSET PRESERVATION PROGRAM - CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS ALONG CONCEPCION - CAPAS ROAD, K0110 + 782 - K0111 + 528, CONCEPCION, TARLAC | Region III | Tarlac 2nd DEO | On-Going | ₱39.2M | 53% | Medium risk33 | —-0.057 |
| 125 | 23CK0038REHABILITATION OF EXISTING DIKE ALONG ARANGUREN CREEK, LEFT BANK, U/S OF CALUMPIT BRIDGE, CAPAS, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱49M | 100% | Medium risk32 | —-0.090 |