Contractor dossier
117 projects on file, including joint ventures this contractor is part of.
Total projects
117
Total budget
₱4.5B
Average progress
97.5%
Completion rate
91.5%
Average risk score
48.7
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 73 | ₱2.6B | 50.1 | 0 | 98.6% |
| National Capital Region | 35 | ₱1.5B | 48.9 | 0 | 95.1% |
| Region III | 8 | ₱361.7M | 36.0 | 0 | 98.2% |
| Region II | 1 | ₱44.1M | 43.8 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 74 | ₱3.7B | 50.0 | 0 | 96.4% |
| Roads | 39 | ₱805.2M | 46.2 | 0 | 99.4% |
| OTHER | 2 | ₱52.6M | 70.5 | 0 | 100.0% |
| Buildings and Facilities | 2 | ₱7.7M | 29.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 18DN0065OO1-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-TERTIARY ROADS-MARIKINA-INFANTA ROAD, K0034+000-K0034+330, K0035+000-K0035+160, ANTIPOLO CITY, 2ND LD | Region IV-A | Rizal 1st DEO | Completed | ₱23.3M | 100% | High risk71 | —-0.041 |
| 17DN0025MFO-1 NATIONAL ROAD NETWORK SERVICES-ASSET PRESERVATION OF NAT'L. RDS. PREVENTIVE MAINT. BASED ON PAVEMENT MANAGEMENT SYSTEM/HWY. DEVELOPMENT AND MANAGEMENT-4 (HDM-4), MARIKINA-INFANTA ROAD, K0034+426-K0035+658, ANTIPOLO CITY 2ND LD | Region IV-A | Rizal 1st DEO | Completed | ₱29.4M | 100% | High risk70 | —-0.038 |
| 17DN0043MFO-1 NATIONAL ROAD NETWORK SERVICES-ASSET PRESERVATION OF NAT'L. RDS. PREVENTIVE MAINT. BASED ON PAVEMENT MANAGEMENT SYSTEM/HWY. DEV'T. AND MANAGEMENT-4 (HDM-4) CAINTA-KAYTICKLING-ANTIPOLO-TERESA-MORONG ROAD, K0027+062-K0028+892, K0030+400-K0030+780, ANT | Region IV-A | Rizal 1st DEO | Completed | ₱20.7M | 100% | High risk66 | —-0.070 |
| 17DN0010MFO-1 NAT'L. ROAD NETWORK SERVICES-ASSET PRESERVATION OF NAT'L. ROADS PREVENTIVE MAINT. BASED ON PAVEMENT MANAGEMENT SYSTEM/HWY. DEV'T. AND MANAGEMENT-4 (HDM-4) CABRERA-ANTIPOLO ROAD, K0026+(-554)-K0026+000, TAYTAY, RIZAL, 1ST LD. | Region IV-A | Rizal 1st DEO | Completed | ₱14.3M | 100% | High risk66 | —-0.067 |
| 17DN0011MFO-1 NAT'L. ROAD NETWORK SERVICES-ASSET PRESERVATION OF NAT'L. ROADS PREVENTIVE MAINT. BASED ON PAVEMENT MANAGEMENT SYSTEM/HWY. DEV'T. AND MANAGEMENT-4 (HDM-4) ANTIPOLO CIRCUMFERENTIAL ROAD A, K0026+010-K0026+510, ANTIPOLO CITY, 2ND LD | Region IV-A | Rizal 1st DEO | Completed | ₱12.7M | 100% | High risk66 | —-0.069 |
| 22DN0031REHABILITATION OF FLOOD CONTROL STRUCTURE, SUCABEN RIVER, PHASE 4, ANTIPOLO CITY (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱93.1M | 80% | High risk65 | —-0.013 |
| 22DN0065REHABILITATION OF FLOOD CONTROL STRUCTURES, BULAO RIVER, ANTIPOLO CITY (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱93.1M | 100% | High risk65 | —-0.067 |
| 22DN0036REHABILITATION OF FLOOD CONTROL STRUCTURE, MUNTINDILAW RIVER, ANTIPOLO CITY (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱93.1M | 89% | High risk65 | —-0.014 |
| 22DN0026REHABILITATION OF FLOOD CONTROL STRUCTURE, BRGY. MAMBUGAN AND BRGY. MUNTINDILAW, ANTIPOLO CITY (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱93.1M | 100% | High risk65 | —-0.074 |
| 24OB0183CONSTRUCTION OF SLOPE PROTECTION ALONG TAGUIG RIVER (PHASE 2), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱94.6M | 100% | High risk64 | —-0.040 |
| 24OB0195CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG LABASAN RIVER (EAST BANK) PACKAGE 2, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱94.6M | 100% | High risk64 | —-0.076 |
| 22OB0093CONSTRUCTION/REHABILITATION OF DRAINAGE SYSTEM ALONG M. ALMEDA ST. AND VICINITY, PATEROS, METRO MANILA | National Capital Region | Metro Manila 1st DEO | Completed | ₱96.5M | 100% | High risk64 | —-0.072 |
| 22DN0051REHABILITATION OF FLOOD CONTROL STRUCTURES ALONG MUNTINDILAW RIVER (DOWNSTREAM), (PHASE 4) ANTIPOLO CITY (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱92.9M | 100% | High risk63 | —-0.073 |
| 20DN0035CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG MUNTINDILAW RIVER (DOWNSTREAM) ANTIPOLO CITY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱92.2M | 98% | High risk62 | —-0.070 |
| 20DN0036CONSTRUCTION OF FLOOD CONTROL STRUCTURES, HALANG CREEK TO MUNTINDILAW RIVER, ALONG MARIKINA DIVERSION ROAD TO MARIKINA - INFANTA ROAD, ANTIPOLO CITY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱92.1M | 100% | High risk62 | —-0.073 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 18DN0065OO1-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-TERTIARY ROADS-MARIKINA-INFANTA ROAD, K0034+000-K0034+330, K0035+000-K0035+160, ANTIPOLO CITY, 2ND LD | Region IV-A | Rizal 1st DEO | Completed | ₱23.3M | 100% | High risk71 | —-0.041 |
| 2 | 17DN0025MFO-1 NATIONAL ROAD NETWORK SERVICES-ASSET PRESERVATION OF NAT'L. RDS. PREVENTIVE MAINT. BASED ON PAVEMENT MANAGEMENT SYSTEM/HWY. DEVELOPMENT AND MANAGEMENT-4 (HDM-4), MARIKINA-INFANTA ROAD, K0034+426-K0035+658, ANTIPOLO CITY 2ND LD | Region IV-A | Rizal 1st DEO | Completed | ₱29.4M | 100% | High risk70 | —-0.038 |
| 3 | 17DN0043MFO-1 NATIONAL ROAD NETWORK SERVICES-ASSET PRESERVATION OF NAT'L. RDS. PREVENTIVE MAINT. BASED ON PAVEMENT MANAGEMENT SYSTEM/HWY. DEV'T. AND MANAGEMENT-4 (HDM-4) CAINTA-KAYTICKLING-ANTIPOLO-TERESA-MORONG ROAD, K0027+062-K0028+892, K0030+400-K0030+780, ANT | Region IV-A | Rizal 1st DEO | Completed | ₱20.7M | 100% | High risk66 | —-0.070 |
| 4 | 17DN0010MFO-1 NAT'L. ROAD NETWORK SERVICES-ASSET PRESERVATION OF NAT'L. ROADS PREVENTIVE MAINT. BASED ON PAVEMENT MANAGEMENT SYSTEM/HWY. DEV'T. AND MANAGEMENT-4 (HDM-4) CABRERA-ANTIPOLO ROAD, K0026+(-554)-K0026+000, TAYTAY, RIZAL, 1ST LD. | Region IV-A | Rizal 1st DEO | Completed | ₱14.3M | 100% | High risk66 | —-0.067 |
| 5 | 17DN0011MFO-1 NAT'L. ROAD NETWORK SERVICES-ASSET PRESERVATION OF NAT'L. ROADS PREVENTIVE MAINT. BASED ON PAVEMENT MANAGEMENT SYSTEM/HWY. DEV'T. AND MANAGEMENT-4 (HDM-4) ANTIPOLO CIRCUMFERENTIAL ROAD A, K0026+010-K0026+510, ANTIPOLO CITY, 2ND LD | Region IV-A | Rizal 1st DEO | Completed | ₱12.7M | 100% | High risk66 | —-0.069 |
| 6 | 22DN0031REHABILITATION OF FLOOD CONTROL STRUCTURE, SUCABEN RIVER, PHASE 4, ANTIPOLO CITY (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱93.1M | 80% | High risk65 | —-0.013 |
| 7 | 22DN0065REHABILITATION OF FLOOD CONTROL STRUCTURES, BULAO RIVER, ANTIPOLO CITY (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱93.1M | 100% | High risk65 | —-0.067 |
| 8 | 22DN0036REHABILITATION OF FLOOD CONTROL STRUCTURE, MUNTINDILAW RIVER, ANTIPOLO CITY (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱93.1M | 89% | High risk65 | —-0.014 |
| 9 | 22DN0026REHABILITATION OF FLOOD CONTROL STRUCTURE, BRGY. MAMBUGAN AND BRGY. MUNTINDILAW, ANTIPOLO CITY (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱93.1M | 100% | High risk65 | —-0.074 |
| 10 | 24OB0183CONSTRUCTION OF SLOPE PROTECTION ALONG TAGUIG RIVER (PHASE 2), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱94.6M | 100% | High risk64 | —-0.040 |
| 11 | 24OB0195CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG LABASAN RIVER (EAST BANK) PACKAGE 2, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱94.6M | 100% | High risk64 | —-0.076 |
| 12 | 22OB0093CONSTRUCTION/REHABILITATION OF DRAINAGE SYSTEM ALONG M. ALMEDA ST. AND VICINITY, PATEROS, METRO MANILA | National Capital Region | Metro Manila 1st DEO | Completed | ₱96.5M | 100% | High risk64 | —-0.072 |
| 13 | 22DN0051REHABILITATION OF FLOOD CONTROL STRUCTURES ALONG MUNTINDILAW RIVER (DOWNSTREAM), (PHASE 4) ANTIPOLO CITY (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱92.9M | 100% | High risk63 | —-0.073 |
| 14 | 20DN0035CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG MUNTINDILAW RIVER (DOWNSTREAM) ANTIPOLO CITY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱92.2M | 98% | High risk62 | —-0.070 |
| 15 | 20DN0036CONSTRUCTION OF FLOOD CONTROL STRUCTURES, HALANG CREEK TO MUNTINDILAW RIVER, ALONG MARIKINA DIVERSION ROAD TO MARIKINA - INFANTA ROAD, ANTIPOLO CITY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱92.1M | 100% | High risk62 | —-0.073 |
| 16 | 23OB0435CONSTRUCTION OF SLOPE PROTECTION AT TAGUIG RIVER LAGUNA LAKESHORE, TAGUIG CITY, PHASE III | National Capital Region | Metro Manila 1st DEO | Completed | ₱91.6M | 100% | Medium risk55 | —-0.076 |
| 17 | 21OB0078CONSTRUCTION OF SLOPE PROTECTION INCLUDING SITE DEVELOPMENT ALONG LAGUNA LAKESHORE (PACKAGE 3), LOWER BICUTAN, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱91.6M | 100% | Medium risk55 | —-0.077 |
| 18 | 22OB0153BANK IMPROVEMENT/PROTECTION ALONG C-6 OPEN CHANNEL (PHASE 3), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱89.8M | 100% | Medium risk54 | —-0.078 |
| 19 | 22OB0152BANK IMPROVEMENT/PROTECTION ALONG C-6 OPEN CHANNEL (PHASE 2), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱89.7M | 100% | Medium risk54 | —-0.079 |
| 20 | 19DN0013CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-IMPROVEMENT/CONSTRUCTION OF FLOOD CONTROL STRUCTURES, MUNTINDILAW RIVER ALONG MARIKINA DIVERSION ROAD, ANTIPOLO CITY (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱73.3M | 100% | Medium risk53 | —-0.080 |
| 21 | 19DN0137CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG MUNTINDILAW RIVER (DOWNSTREAM) ANTIPOLO CITY (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱68.7M | 100% | Medium risk53 | —-0.083 |
| 22 | 20DN0037CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG MUNTINDILAW RIVER (DOWNSTREAM), PHASE 3, ANTIPOLO CITY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱64.7M | 100% | Medium risk53 | —-0.083 |
| 23 | 24OF0141CONSTRUCTION DRAINAGE SYSTEMS AT BRGY. APOLONIO SAMSON, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱77.2M | 100% | Medium risk53 | —-0.085 |
| 24 | 25OF0169CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AT (PANTRANCO, MARCEL, ADEZVILLE), BARANGAY PASONG TAMO, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱56.7M | 48% | Medium risk53 | —-0.039 |
| 25 | 20DN0157IMPROVEMENT/CONSTRUCTION OF FLOOD CONTROL STRUCTURES OF KAMIAS CREEK (COGEO GATE 1), ANTIPOLO CITY, RIZAL | Region IV-A | Rizal 1st DEO | On-Going | ₱72.4M | 76% | Medium risk53 | —-0.006 |