Contractor dossier
117 projects on file, including joint ventures this contractor is part of.
Total projects
117
Total budget
₱4.5B
Average progress
97.5%
Completion rate
91.5%
Average risk score
48.7
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 73 | ₱2.6B | 50.1 | 0 | 98.6% |
| National Capital Region | 35 | ₱1.5B | 48.9 | 0 | 95.1% |
| Region III | 8 | ₱361.7M | 36.0 | 0 | 98.2% |
| Region II | 1 | ₱44.1M | 43.8 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 74 | ₱3.7B | 50.0 | 0 | 96.4% |
| Roads | 39 | ₱805.2M | 46.2 | 0 | 99.4% |
| OTHER | 2 | ₱52.6M | 70.5 | 0 | 100.0% |
| Buildings and Facilities | 2 | ₱7.7M | 29.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 18DN0065OO1-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-TERTIARY ROADS-MARIKINA-INFANTA ROAD, K0034+000-K0034+330, K0035+000-K0035+160, ANTIPOLO CITY, 2ND LD | Region IV-A | Rizal 1st DEO | Completed | ₱23.3M | 100% | High risk71 | —-0.041 |
| 17DN0025MFO-1 NATIONAL ROAD NETWORK SERVICES-ASSET PRESERVATION OF NAT'L. RDS. PREVENTIVE MAINT. BASED ON PAVEMENT MANAGEMENT SYSTEM/HWY. DEVELOPMENT AND MANAGEMENT-4 (HDM-4), MARIKINA-INFANTA ROAD, K0034+426-K0035+658, ANTIPOLO CITY 2ND LD | Region IV-A | Rizal 1st DEO | Completed | ₱29.4M | 100% | High risk70 | —-0.038 |
| 17DN0043MFO-1 NATIONAL ROAD NETWORK SERVICES-ASSET PRESERVATION OF NAT'L. RDS. PREVENTIVE MAINT. BASED ON PAVEMENT MANAGEMENT SYSTEM/HWY. DEV'T. AND MANAGEMENT-4 (HDM-4) CAINTA-KAYTICKLING-ANTIPOLO-TERESA-MORONG ROAD, K0027+062-K0028+892, K0030+400-K0030+780, ANT | Region IV-A | Rizal 1st DEO | Completed | ₱20.7M | 100% | High risk66 | —-0.070 |
| 17DN0010MFO-1 NAT'L. ROAD NETWORK SERVICES-ASSET PRESERVATION OF NAT'L. ROADS PREVENTIVE MAINT. BASED ON PAVEMENT MANAGEMENT SYSTEM/HWY. DEV'T. AND MANAGEMENT-4 (HDM-4) CABRERA-ANTIPOLO ROAD, K0026+(-554)-K0026+000, TAYTAY, RIZAL, 1ST LD. | Region IV-A | Rizal 1st DEO | Completed | ₱14.3M | 100% | High risk66 | —-0.067 |
| 17DN0011MFO-1 NAT'L. ROAD NETWORK SERVICES-ASSET PRESERVATION OF NAT'L. ROADS PREVENTIVE MAINT. BASED ON PAVEMENT MANAGEMENT SYSTEM/HWY. DEV'T. AND MANAGEMENT-4 (HDM-4) ANTIPOLO CIRCUMFERENTIAL ROAD A, K0026+010-K0026+510, ANTIPOLO CITY, 2ND LD | Region IV-A | Rizal 1st DEO | Completed | ₱12.7M | 100% | High risk66 | —-0.069 |
| 22DN0031REHABILITATION OF FLOOD CONTROL STRUCTURE, SUCABEN RIVER, PHASE 4, ANTIPOLO CITY (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱93.1M | 80% | High risk65 | —-0.013 |
| 22DN0065REHABILITATION OF FLOOD CONTROL STRUCTURES, BULAO RIVER, ANTIPOLO CITY (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱93.1M | 100% | High risk65 | —-0.067 |
| 22DN0036REHABILITATION OF FLOOD CONTROL STRUCTURE, MUNTINDILAW RIVER, ANTIPOLO CITY (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱93.1M | 89% | High risk65 | —-0.014 |
| 22DN0026REHABILITATION OF FLOOD CONTROL STRUCTURE, BRGY. MAMBUGAN AND BRGY. MUNTINDILAW, ANTIPOLO CITY (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱93.1M | 100% | High risk65 | —-0.074 |
| 24OB0183CONSTRUCTION OF SLOPE PROTECTION ALONG TAGUIG RIVER (PHASE 2), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱94.6M | 100% | High risk64 | —-0.040 |
| 24OB0195CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG LABASAN RIVER (EAST BANK) PACKAGE 2, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱94.6M | 100% | High risk64 | —-0.076 |
| 22OB0093CONSTRUCTION/REHABILITATION OF DRAINAGE SYSTEM ALONG M. ALMEDA ST. AND VICINITY, PATEROS, METRO MANILA | National Capital Region | Metro Manila 1st DEO | Completed | ₱96.5M | 100% | High risk64 | —-0.072 |
| 22DN0051REHABILITATION OF FLOOD CONTROL STRUCTURES ALONG MUNTINDILAW RIVER (DOWNSTREAM), (PHASE 4) ANTIPOLO CITY (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱92.9M | 100% | High risk63 | —-0.073 |
| 20DN0035CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG MUNTINDILAW RIVER (DOWNSTREAM) ANTIPOLO CITY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱92.2M | 98% | High risk62 | —-0.070 |
| 20DN0036CONSTRUCTION OF FLOOD CONTROL STRUCTURES, HALANG CREEK TO MUNTINDILAW RIVER, ALONG MARIKINA DIVERSION ROAD TO MARIKINA - INFANTA ROAD, ANTIPOLO CITY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱92.1M | 100% | High risk62 | —-0.073 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 22DO0031CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY SAN JOSE, RODRIGUEZ, RIZAL | Region IV-A | Rizal 2nd DEO | Completed | ₱19.8M | 100% | Medium risk47 | —-0.102 |
| 77 | 24DN0089ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - CORAZON C. AQUINO AVE. - K0019+075 - K0019+680 RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱20.3M | 100% | Medium risk47 | —-0.101 |
| 78 | 18DN0012001-ASSET PRESERVATION-PREVENTIVE MAINTENANCE-PRIMARY ROADS CAINTA-KAYTICKLING-ANTIPOLO-TERESA-MORONG ROAD (S01741LZ) K0021+230-K0023+057, TAYTAY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱23.2M | 100% | Medium risk47 | —-0.101 |
| 79 | 22DN0046OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - CAINTA-KAYTICKLING-ANTIPOLO-TERESA-MORONG RD - K0019+000-K0019+512, K0020+391-K0020+571, K0020+800-K0019+000, K0021+(-152)-K0021+720 RIZAL ( | Region IV-A | Rizal 1st DEO | Completed | ₱24.2M | 100% | Medium risk47 | —-0.101 |
| 80 | 18DN0001001-ASSET PRESERVATION-PREVENTIVE MAINTENANCE-TERTIARY ROADS CABRERA-ANTIPOLO ROAD (S01589LZ) K0027+000-KOO29+105, TAYTAY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱20.4M | 100% | Medium risk47 | —-0.102 |
| 81 | 18DN0013001-ASSET PRESERVATION-PREVENTIVE MAINTENANCE-SECONDARY ROADS MARIKINA-VICTORIA VALLEY-ANTIPOLO ROAD (S04428LZ), K0030+249-K0031+172, ANTIPOLO CITY, 2ND LD | Region IV-A | Rizal 1st DEO | Completed | ₱21.9M | 100% | Medium risk47 | —-0.104 |
| 82 | 23DN0060ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - MANILA EAST RD - K0034+631 - K0034+949, K0034+956 - K0035+286 BINANGONAN, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱17.2M | 100% | Medium risk47 | —-0.102 |
| 83 | 22DN0019CONSTRUCTION OF BOX CULVERT WITH APPROACHES/ SLOPE PROTECTION, SITIO LIBIS, BRGY. SAN JOSE ANTIPOLO CITY (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱14.1M | 100% | Medium risk47 | —-0.089 |
| 84 | 18DN0045CONSTRUCTION OF SLOPE PROTECTION AT KAYSAKAT NHS, BRGY. SAN JOSE, ANTIPOLO CITY | Region IV-A | Rizal 1st DEO | Completed | ₱18.6M | 100% | Medium risk46 | —-0.089 |
| 85 | 21DO0030LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM-LOCAL ROADS AND BRIDGES-LOCAL ROADS-ASPHALTING OF ROAD ALONG MARIKINA INFANTA ROAD BARANGAY CUYAMBAY AND BARANGAY SAMPALOC TANAY, RIZAL | Region IV-A | Rizal 2nd DEO | Completed | ₱19.8M | 100% | Medium risk46 | —-0.103 |
| 86 | 20DN0094REHABILITATION OF ROAD AND DRAINAGE SYSTEM, KAYSAKAT ROAD (PHASE 2), BRGY. SAN JOSE, ANTIPOLO CITY | Region IV-A | Rizal 1st DEO | Completed | ₱14.3M | 100% | Medium risk46 | —-0.107 |
| 87 | 20DN0106REHABILITATION OF ROAD AND DRAINAGE SYSTEM, ROAD LEADING TO KAYSAKAT ROAD (PHASE 2), BRGY. SAN JOSE, ANTIPOLO CITY | Region IV-A | Rizal 1st DEO | Completed | ₱14.3M | 100% | Medium risk46 | —-0.107 |
| 88 | 24OF0043IMPROVEMENT OF ROAD, BRGY. HOLY SPIRIT, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱24.5M | 100% | Medium risk46 | —-0.098 |
| 89 | 18OF0121IMPROVEMENT/ CONCRETING OF MAXIMO VIOLA ST., BRGY. BALINGASA, Q.C. | National Capital Region | Quezon City 1st DEO | Completed | ₱24.3M | 100% | Medium risk46 | —-0.100 |
| 90 | 19DO0078LOCAL PROGRAM-LOCAL ROADS AND BRIDGES- LOCAL ROADS- LOCAL INFRASTRUCTURE PROGRAM- ASPHALTING OF ROAD FROM BARANGAY STO. NINO TO BARANGAY SILANGAN, SAN MATEO, RIZAL | Region IV-A | Rizal 2nd DEO | Completed | ₱9.9M | 100% | Medium risk46 | —-0.104 |
| 91 | 18DN0003001- ASSET PRESERVATION-PREVENTIVE MAINTENANCE-TERTIARY ROADS MANILA EAST ROAD (S01744LZ) K0023+704-K0024+300, TAYTAY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱6.7M | 100% | Medium risk46 | —-0.102 |
| 92 | 18DN0005001-ASSET PRESERVATION-PREVENTIVE MAINTENANCE-TERTIARY ROADS CABRERA-ANTIPOLO ROAD (S01589LZ) K0029+172-K0029+720, K0030+556-K0031+133, ANTIPOLO CITY, 2ND LD | Region IV-A | Rizal 1st DEO | Completed | ₱11.1M | 100% | Medium risk46 | —-0.103 |
| 93 | 25OF0140CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT DARIO CREEK, BARANGAY TALIPAPA, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱35.7M | 32% | Medium risk46 | —-0.036 |
| 94 | 20OB0364IMPROVEMENT OF ROAD NETWORKS, BRGY. POBLACION, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱18.8M | 100% | Medium risk46 | —-0.100 |
| 95 | 21OF0029REHABILITATION OF MENDOZA STREET, BRGY. PALTOK, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱17.1M | 100% | Medium risk46 | —-0.101 |
| 96 | 21DN0050CONSTRUCTION OF ROAD AND DRAINAGE AT BARANGAY PUROK 3, 4 & 5, BARANGAY HABAGATAN, BINANGONAN, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱9.6M | 100% | Medium risk46 | —-0.107 |
| 97 | 20DN0093REHABILITATION OF ROAD AND DRAINAGE SYSTEM, ROAD LEADING TO KAYSAKAT (E/S), BRGY. SAN JOSE, ANTIPOLO CITY | Region IV-A | Rizal 1st DEO | Completed | ₱9.5M | 100% | Medium risk46 | —-0.107 |
| 98 | 21OB0099REHABILITATION/CONSTRUCTION OF SLOPE PROTECTION ALONG LAKESHORE PARK (PHASE III), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱39.3M | 100% | Medium risk46 | —-0.087 |
| 99 | 19OB0118BANK IMPROVEMENT/PROTECTION ALONG PATEROS RIVER, BRGY. AGUHO, (PHASE III), PATEROS, METRO MANILA | National Capital Region | Metro Manila 1st DEO | Completed | ₱45.6M | 100% | Medium risk46 | —-0.088 |
| 100 | 18OF0111CONSTRUCTION OF SLOPE PROTECTION PALTOK CREEK, Q.C. | National Capital Region | Quezon City 1st DEO | Completed | ₱14.3M | 100% | Medium risk46 | —-0.087 |