Contractor dossier
52 projects on file, including joint ventures this contractor is part of.
Total projects
52
Total budget
₱7.4B
Average progress
81.5%
Completion rate
46.2%
Below 70%
Average risk score
63.2
High risk on average, out of 100
Flagged as unusual
8
15.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 18 | ₱1.7B | 57.5 | 0 | 72.3% |
| Region VI | 10 | ₱1.6B | 61.8 | 2 | 93.3% |
| Region VII | 9 | ₱1.2B | 65.4 | 1 | 94.3% |
| Region IV-A | 7 | ₱392.1M | 63.3 | 1 | 75.0% |
| Central Office | 4 | ₱2B | 75.0 | 1 | 96.5% |
| Region II | 3 | ₱409.2M | 81.8 | 3 | 48.2% |
| Cordillera Administrative Region | 1 | ₱124.6M | 56.4 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 15 | ₱3B | 63.9 | 2 | 86.2% |
| Roads | 15 | ₱1.6B | 56.3 | 1 | 83.2% |
| Buildings and Facilities | 7 | ₱984.5M | 62.4 | 1 | 59.0% |
| Bridges | 6 | ₱531.7M | 57.5 | 0 | 96.4% |
| OTHER | 4 | ₱716M | 82.2 | 3 | 70.9% |
| Bridges, Roads | 3 | ₱596.5M | 64.5 | 0 | 100.0% |
| GAA 2025 OO-1 | 2 | ₱67.9M | 90.3 | 1 | 61.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DO0051ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS - MARIKINA-INFANTA RD - K0051+665 - K0051+685, K0052+ | Region IV-A | Rizal 2nd DEO | On-Going | ₱30.1M | 38% | High risk91 | Flagged0.001 |
| 24BD0230OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF BASI FLOOD CONTROL SYSTEM, PACKAGE 1, BASI, SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱95.5M | 34% | High risk91 | Flagged0.075 |
| 24H00175CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP)-PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF LEVEL III WATER SYSTEM, MADRIDEJOS, CEBU | Region VII | Region VII | On-Going | ₱197.7M | 60% | High risk91 | Flagged0.080 |
| 25DO0052ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - MANILA EAST RD - K0064+450 - K0064+700 | Region IV-A | Rizal 2nd DEO | On-Going | ₱37.7M | 85% | High risk90 | —-0.013 |
| 24B00072OO1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - CONSTRUCTION OF NEW BRIDGES - POBLACION - BAGUNOT BRIDGE, BAGGAO, CAGAYAN | Region II | Region II | On-Going | ₱218.3M | 90% | High risk84 | Flagged0.036 |
| 17Z00011REHABILITATION OF NAPINDAN HYDRAULIC CONTROL STRUCTURES THROUGH DESIGN AND BUILD SCHEME, BRGY. BUTING, PASIG CITY | Central Office | Flood Control Management Cluster | Completed | ₱849.1M | 100% | High risk77 | —-0.006 |
| 18Z00031UPGRADING OF SPINE PUMPING STATION, NAVOTAS CITY | Central Office | Flood Control Management Cluster | Completed | ₱385M | 100% | High risk76 | —-0.038 |
| 22O00068UPGRADING OF TAPAYAN PUMPING STATION, TAGUIG CITY | Central Office | Flood Control Management Cluster | Completed | ₱389.3M | 100% | High risk76 | —-0.037 |
| 18Z00027FLOOD RISK MANGEMENT PROJECT FOR CAGAYAN DE ORO RIVER (FRIMP-CDOR), JICA LOAN NO. PH-P259, CONTRACT PACKAGE 1 (BONBON-KAUSWAGAN) | Central Office | Flood Control Management Cluster | On-Going | ₱371.1M | 86% | High risk71 | Flagged0.029 |
| 24BD0229OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF CENTRO FLOOD CONTROL SYSTEM, PACKAGE 1, CENTRO, SOLANA | Region II | Cagayan 3rd DEO | On-Going | ₱95.4M | 21% | High risk71 | Flagged0.048 |
| 18H00047ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT, CONSTRUCTION OF FLYOVERS/INTERCHANGES/UNDERPASSES/LONG SPAN BRIDGES-PANGLAO-TAGBILARAN CITY OFFSHORE BRIDGE CONNECTOR, STA.1+878.140-STA.2+623.194, BOHOL PROVINC | Region VII | Region VII | Completed | ₱333.5M | 100% | High risk66 | —-0.008 |
| 24OB0298CONSTRUCTION OF RFU-NCR MEGA LABORATORY BUILDING PHASE II, 1ST QUADRANT OF CAMP BAGONG DIWA ALONG GEN. SANTOS AVE., BICUTAN, TAGUIG CITY (PHASE 3) | National Capital Region | Metro Manila 1st DEO | On-Going | ₱143.3M | 94% | High risk65 | —-0.036 |
| 24OB0299CONSTRUCTION OF RFU-NCR MEGA LABORATORY BUILDING PHASE II, 1ST QUADRANT OF CAMP BAGONG DIWA ALONG GEN. SANTOS AVE., BICUTAN, TAGUIG CITY (PHASE 4) | National Capital Region | Metro Manila 1st DEO | On-Going | ₱143.3M | 95% | High risk65 | —-0.037 |
| 20H00033ORGANIZATIONAL OUTCOME 2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS /FLOOD MANAGEMENT PROGRAM CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEM CONSTRUCTION OF FLOOD CONTROL STRUCTURE/SHORE PROTECTION AT POBLACION, SIQUIJOR | Region VII | Region VII | Completed | ₱123.5M | 100% | High risk65 | —-0.048 |
| 24OB0321CONSTRUCTION OF RFU-NCR MEGA LABORATORY BUILDING PHASE II, 1ST QUADRANT OF CAMP BAGONG DIWA ALONG GEN. SANTOS AVE., BICUTAN, TAGUIG CITY (PHASE 2) | National Capital Region | Metro Manila 1st DEO | On-Going | ₱238.7M | 78% | High risk65 | —-0.023 |
| 25OB0334CONSTRUCTION OF MULTI-PURPOSE FACILITY, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 1) | National Capital Region | Metro Manila 1st DEO | On-Going | ₱145M | 0% | High risk65 | —-0.010 |
| 25OI0054CONSTRUCTION OF FLOOD CONTROL STRUCTURE, MANGANGATE RIVER, MUNTINLUPA CITY | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱94.1M | 0% | High risk65 | —-0.020 |
| 25OI0078CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SOUTHVILLE 3, BARANGAY POBLACION, MUNTINLUPA CITY | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱94.6M | 86% | High risk65 | —-0.044 |
| 21HH0164OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM- CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF FLOOD MITIGATION STRUCTURE WITH DESILTING ALONG BUTUANON RIVER, CEBU CITY | Region VII | Cebu City DEO | Completed | ₱95.1M | 100% | High risk65 | —-0.069 |
| 21HF0003CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT COMBADO RIVER ALONG TOLEDO-TABUELAN-SAN REMEGIO ROAD, BRGY. CANTUOD, BALAMBAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱93.6M | 100% | High risk64 | —-0.064 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24H00175CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP)-PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF LEVEL III WATER SYSTEM, MADRIDEJOS, CEBU | Region VII | Region VII | On-Going | ₱197.7M | 60% | High risk91 | Flagged0.080 |
| 24BD0230OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF BASI FLOOD CONTROL SYSTEM, PACKAGE 1, BASI, SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱95.5M | 34% | High risk91 | Flagged0.075 |
| 24BD0229OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF CENTRO FLOOD CONTROL SYSTEM, PACKAGE 1, CENTRO, SOLANA | Region II | Cagayan 3rd DEO | On-Going | ₱95.4M | 21% | High risk71 | Flagged0.048 |
| 24B00072OO1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - CONSTRUCTION OF NEW BRIDGES - POBLACION - BAGUNOT BRIDGE, BAGGAO, CAGAYAN | Region II | Region II | On-Going | ₱218.3M | 90% | High risk84 | Flagged0.036 |
| 18Z00027FLOOD RISK MANGEMENT PROJECT FOR CAGAYAN DE ORO RIVER (FRIMP-CDOR), JICA LOAN NO. PH-P259, CONTRACT PACKAGE 1 (BONBON-KAUSWAGAN) | Central Office | Flood Control Management Cluster | On-Going | ₱371.1M | 86% | High risk71 | Flagged0.029 |
| 22G00151CONSTRUCTION OF MULTI-PURPOSE BUILDING, BACOLOD CITY GENERAL HOSPITAL, BRGY. VISTA ALEGRE, BACOLOD CITY, NEGROS OCCIDENTAL | Region VI | Region VI | On-Going | ₱193M | 54% | High risk63 | Flagged0.018 |
| 18G00055PANAY EAST - WEST ROAD (ILOILO SECTION), ILOILO | Region VI | Region VI | On-Going | ₱135.6M | 79% | High risk61 | Flagged0.003 |
| 25DO0051ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS - MARIKINA-INFANTA RD - K0051+665 - K0051+685, K0052+ | Region IV-A | Rizal 2nd DEO | On-Going | ₱30.1M | 38% | High risk91 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25DO0051ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS - MARIKINA-INFANTA RD - K0051+665 - K0051+685, K0052+ | Region IV-A | Rizal 2nd DEO | On-Going | ₱30.1M | 38% | High risk91 | Flagged0.001 |
| 2 | 24BD0230OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF BASI FLOOD CONTROL SYSTEM, PACKAGE 1, BASI, SOLANA, CAGAYAN | Region II | Cagayan 3rd DEO | On-Going | ₱95.5M | 34% | High risk91 | Flagged0.075 |
| 3 | 24H00175CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP)-PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF LEVEL III WATER SYSTEM, MADRIDEJOS, CEBU | Region VII | Region VII | On-Going | ₱197.7M | 60% | High risk91 | Flagged0.080 |
| 4 | 25DO0052ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - MANILA EAST RD - K0064+450 - K0064+700 | Region IV-A | Rizal 2nd DEO | On-Going | ₱37.7M | 85% | High risk90 | —-0.013 |
| 5 | 24B00072OO1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - CONSTRUCTION OF NEW BRIDGES - POBLACION - BAGUNOT BRIDGE, BAGGAO, CAGAYAN | Region II | Region II | On-Going | ₱218.3M | 90% | High risk84 | Flagged0.036 |
| 6 | 17Z00011REHABILITATION OF NAPINDAN HYDRAULIC CONTROL STRUCTURES THROUGH DESIGN AND BUILD SCHEME, BRGY. BUTING, PASIG CITY | Central Office | Flood Control Management Cluster | Completed | ₱849.1M | 100% | High risk77 | —-0.006 |
| 7 | 18Z00031UPGRADING OF SPINE PUMPING STATION, NAVOTAS CITY | Central Office | Flood Control Management Cluster | Completed | ₱385M | 100% | High risk76 | —-0.038 |
| 8 | 22O00068UPGRADING OF TAPAYAN PUMPING STATION, TAGUIG CITY | Central Office | Flood Control Management Cluster | Completed | ₱389.3M | 100% | High risk76 | —-0.037 |
| 9 | 18Z00027FLOOD RISK MANGEMENT PROJECT FOR CAGAYAN DE ORO RIVER (FRIMP-CDOR), JICA LOAN NO. PH-P259, CONTRACT PACKAGE 1 (BONBON-KAUSWAGAN) | Central Office | Flood Control Management Cluster | On-Going | ₱371.1M | 86% | High risk71 | Flagged0.029 |
| 10 | 24BD0229OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF CENTRO FLOOD CONTROL SYSTEM, PACKAGE 1, CENTRO, SOLANA | Region II | Cagayan 3rd DEO | On-Going | ₱95.4M | 21% | High risk71 | Flagged0.048 |
| 11 | 18H00047ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT, CONSTRUCTION OF FLYOVERS/INTERCHANGES/UNDERPASSES/LONG SPAN BRIDGES-PANGLAO-TAGBILARAN CITY OFFSHORE BRIDGE CONNECTOR, STA.1+878.140-STA.2+623.194, BOHOL PROVINC | Region VII | Region VII | Completed | ₱333.5M | 100% | High risk66 | —-0.008 |
| 12 | 24OB0298CONSTRUCTION OF RFU-NCR MEGA LABORATORY BUILDING PHASE II, 1ST QUADRANT OF CAMP BAGONG DIWA ALONG GEN. SANTOS AVE., BICUTAN, TAGUIG CITY (PHASE 3) | National Capital Region | Metro Manila 1st DEO | On-Going | ₱143.3M | 94% | High risk65 | —-0.036 |
| 13 | 24OB0299CONSTRUCTION OF RFU-NCR MEGA LABORATORY BUILDING PHASE II, 1ST QUADRANT OF CAMP BAGONG DIWA ALONG GEN. SANTOS AVE., BICUTAN, TAGUIG CITY (PHASE 4) | National Capital Region | Metro Manila 1st DEO | On-Going | ₱143.3M | 95% | High risk65 | —-0.037 |
| 14 | 20H00033ORGANIZATIONAL OUTCOME 2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS /FLOOD MANAGEMENT PROGRAM CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEM CONSTRUCTION OF FLOOD CONTROL STRUCTURE/SHORE PROTECTION AT POBLACION, SIQUIJOR | Region VII | Region VII | Completed | ₱123.5M | 100% | High risk65 | —-0.048 |
| 15 | 24OB0321CONSTRUCTION OF RFU-NCR MEGA LABORATORY BUILDING PHASE II, 1ST QUADRANT OF CAMP BAGONG DIWA ALONG GEN. SANTOS AVE., BICUTAN, TAGUIG CITY (PHASE 2) | National Capital Region | Metro Manila 1st DEO | On-Going | ₱238.7M | 78% | High risk65 | —-0.023 |
| 16 | 25OB0334CONSTRUCTION OF MULTI-PURPOSE FACILITY, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 1) | National Capital Region | Metro Manila 1st DEO | On-Going | ₱145M | 0% | High risk65 | —-0.010 |
| 17 | 25OI0054CONSTRUCTION OF FLOOD CONTROL STRUCTURE, MANGANGATE RIVER, MUNTINLUPA CITY | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱94.1M | 0% | High risk65 | —-0.020 |
| 18 | 25OI0078CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SOUTHVILLE 3, BARANGAY POBLACION, MUNTINLUPA CITY | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱94.6M | 86% | High risk65 | —-0.044 |
| 19 | 21HH0164OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM- CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF FLOOD MITIGATION STRUCTURE WITH DESILTING ALONG BUTUANON RIVER, CEBU CITY | Region VII | Cebu City DEO | Completed | ₱95.1M | 100% | High risk65 | —-0.069 |
| 20 | 21HF0003CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT COMBADO RIVER ALONG TOLEDO-TABUELAN-SAN REMEGIO ROAD, BRGY. CANTUOD, BALAMBAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱93.6M | 100% | High risk64 | —-0.064 |
| 21 | 18G00052PANAY EAST-WEST ROAD (ANTIQUE SECTION), ANTIQUE | Region VI | Region VI | Completed | ₱137.5M | 100% | High risk64 | —-0.027 |
| 22 | 19G00055CONSTRUCTION OF GRAVEL ROAD - CONSTRUCTION OF PANDAN - IBAJAY ROAD, PANDAN, ANTIQUE | Region VI | Region VI | Completed | ₱193M | 100% | High risk64 | —-0.034 |
| 23 | 18G00073CONSTRUCTION OF SEAWALL/ESPLANADE INCLUDING ACCESS ROAD ALONG BARANGAY COMON - SAN PEDRO COASTAL ROAD LEADING TO SAN JOSE PORT AND BEACHES, RESORTS AND SUNSET VIEWING, SAN JOSE, ANTIQUE | Region VI | Region VI | Completed | ₱204.5M | 100% | High risk64 | —-0.015 |
| 24 | 18G00062SAN REMEGIO - BUGO - GEN. FULLON VALDERRAMA ROAD, ANTIQUE | Region VI | Region VI | Completed | ₱182.8M | 100% | High risk63 | —-0.028 |
| 25 | 18G00077ILOILO CIRCUMFERENTIAL ROAD 3 INCL. ROW, ILOILO | Region VI | Region VI | Completed | ₱125.5M | 100% | High risk63 | —-0.026 |