Contractor dossier
187 projects on file, including joint ventures this contractor is part of.
Total projects
187
Total budget
₱8.2B
Average progress
95.7%
Completion rate
89.3%
Average risk score
48.1
Medium risk on average, out of 100
Flagged as unusual
8
4.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 164 | ₱7.7B | 48.7 | 7 | 95.5% |
| Cordillera Administrative Region | 16 | ₱338.2M | 41.6 | 0 | 96.0% |
| Region II | 7 | ₱176.6M | 48.4 | 1 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 72 | ₱3.6B | 46.8 | 0 | 95.9% |
| Flood Control and Drainage | 67 | ₱3B | 48.6 | 1 | 99.4% |
| Buildings and Facilities | 28 | ₱185.8M | 39.7 | 0 | 99.3% |
| Bridges | 10 | ₱888.6M | 59.0 | 4 | 65.3% |
| OTHER | 4 | ₱214.3M | 79.6 | 2 | 87.5% |
| Bridges, Roads | 3 | ₱300.4M | 60.1 | 0 | 100.0% |
| Water Provision and Storage | 2 | ₱6.3M | 34.4 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱4.9M | 96.1 | 1 | 49.1% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25AB0148BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI PURPOSE BUILDING, BRGY. BUNGRO, PINILI, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | On-Going | ₱4.9M | 49% | High risk96 | Flagged0.033 |
| 24AC0105CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY SAGPAT, BANTAY, ILOCOS SUR | Region I | Ilocos Sur 1st DEO | On-Going | ₱96.4M | 95% | High risk88 | Flagged0.061 |
| 24AB0106CONSTRUCTION OF 4- STOREY 12-CLASSROOM SCHOOL BUILDING IN SAN NICOLAS NATIONAL HIGH SCHOOL, BARANGAY 24, MUNICIPALITY OF SAN NICOLAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | On-Going | ₱39.4M | 55% | High risk88 | Flagged0.067 |
| 24A00290CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF QUIAOIT RIVER DIVERSION CANAL, PAOAY, ILOCOS NORTE | Region I | Region I | Completed | ₱115.8M | 100% | High risk75 | —-0.021 |
| 17AI0030IMPVT/WIDENING OF NATL RD ALONG PNER, KO 180+417 - KO 181+745; KO 183+929-KO184+062 | Region I | Pangasinan 3rd DEO | Completed | ₱46.4M | 100% | High risk72 | —-0.031 |
| 18AD0012CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS , MANILA NORTH ROAD, K0386+000-K0389+000(R/S) | Region I | Ilocos Sur 2nd DEO | Completed | ₱32.1M | 100% | High risk70 | —-0.024 |
| 23AA0031CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONST. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVER ALONG LAOAG (SARRAT) RIVER, BARANGAY 10, SAN MIGUEL, SARRAT, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱19.6M | 100% | High risk70 | —-0.068 |
| 24A00124WIDENING OF PERMANENT BRIDGES, BADOC PARALLEL BR. ALONG MANILA NORTH ROAD | Region I | Region I | On-Going | ₱39.6M | 1% | High risk69 | Flagged0.017 |
| 24A00360CONSTRUCTION OF MISSING LINKS/NEW ROADS, ROAD CONNECTING SANTA-RANCHO ROAD (S00089LZ) AND SANTA-CAOAYAN ROAD, ILOCOS SUR | Region I | Region I | Completed | ₱149.7M | 100% | High risk68 | —-0.002 |
| 23A00164CONSTRUCTION OF MISSING LINKS/ NEW ROADS - CABUGAO-NUEVA ERA-DANGLAS ROAD, CABUGAO SECTION, ILOCOS SUR | Region I | Region I | Completed | ₱60.7M | 100% | High risk66 | —-0.046 |
| 17AE0034REHABILITATION AND IMPROVEMENT OF AMBURAYAN RIVER AT BRGY. NAMALTUGAN, SUDIPEN, LA UNION | Region I | La Union 1st DEO | Completed | ₱19.6M | 100% | High risk65 | —-0.045 |
| 23A00050CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MADUNGON RIVER, BOTH BANK, BARANGAY BAGBAGO, SOLSONA, ILOCOS NORTE | Region I | Region I | Completed | ₱96.5M | 100% | High risk64 | —-0.052 |
| 24A00012CONSTRUCTION OF MISSING LINKS/NEW ROADS, BANTAY (ILOCOS SUR) - SAN QUINTIN - LANGIDEN (ABRA) ROAD, ILOCOS SUR (PACKAGE 5) | Region I | Region I | Completed | ₱154M | 100% | High risk63 | —-0.024 |
| 16AD0142CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES: CONSTRUCTION OF BREAKWATER/HEXAPODS OF SANTA SEAWALL,SANTA, ILOCOS SUR 2ND LD | Region I | Ilocos Sur 2nd DEO | Completed | ₱29.4M | 100% | High risk63 | —-0.040 |
| 16AD0143CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES: CONSTRUCTION OF ABRA RIVER CONTROL,SANTA, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱19.6M | 100% | High risk63 | —-0.042 |
| 23A00145WIDENING OF PERMANENT BRIDGES - BADOC PARALLEL BR. (B00564LZ) ALONG MANILA NORTH RD | Region I | Region I | Completed | ₱153.4M | 100% | High risk63 | —-0.023 |
| 25AB0024BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PANGIL, CURRIMAO, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | On-Going | ₱4.8M | 80% | High risk62 | —-0.037 |
| 22A00260CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL MITIGATION FACILITIES ALONG AMBURAYAN RIVER BASIN AT BARANGAYS BUCAO WEST, BUCAO EAST, LANTAG, BARITAO AND TARANGOTON | Region I | Region I | Completed | ₱241.2M | 100% | High risk62 | —-0.033 |
| 16BB0099CONSTRUCTION OF CASAMBALANGAN RIVER CONTROL PROJECT CASAMBALANGAN, STA. ANA, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱20M | 100% | High risk62 | —-0.033 |
| 16BB0101CONSTRUCTION OF PALAWIG RIVER CONTROL PROJECT STA. ANA, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱20.1M | 100% | High risk62 | —-0.036 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24AB0106CONSTRUCTION OF 4- STOREY 12-CLASSROOM SCHOOL BUILDING IN SAN NICOLAS NATIONAL HIGH SCHOOL, BARANGAY 24, MUNICIPALITY OF SAN NICOLAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | On-Going | ₱39.4M | 55% | High risk88 | Flagged0.067 |
| 24AC0105CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY SAGPAT, BANTAY, ILOCOS SUR | Region I | Ilocos Sur 1st DEO | On-Going | ₱96.4M | 95% | High risk88 | Flagged0.061 |
| 25AB0148BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI PURPOSE BUILDING, BRGY. BUNGRO, PINILI, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | On-Going | ₱4.9M | 49% | High risk96 | Flagged0.033 |
| 24A00124WIDENING OF PERMANENT BRIDGES, BADOC PARALLEL BR. ALONG MANILA NORTH ROAD | Region I | Region I | On-Going | ₱39.6M | 1% | High risk69 | Flagged0.017 |
| 25A00438SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), CONSTRUCTION OF ROAD CONNECTING TO SANTA-RANCHO (S00089LZ) TO SANTA-CAOAYAN ROAD (PHASE 2), ILOCOS SUR | Region I | Region I | On-Going | ₱93.6M | 25% | High risk62 | Flagged0.011 |
| 17BI0126REHABILITATION/IMPROVEMENT OF BAKIR FLOOD CONTROL STRUCTURES (STA.0+000-STA. 0+507.10), BAGABAG, NUEVA VIZCAYA | Region II | Nueva Vizcaya DEO | Completed | ₱18.6M | 100% | Medium risk57 | Flagged0.002 |
| 25A00106CONSTRUCTION OF MISSING LINKS/ NEW ROADS - BANTAY (ILOCOS SUR) - SAN QUINTIN-LANGIDEN (ABRA) ROAD, ILOCOS SUR (PACKAGE 6) | Region I | Region I | On-Going | ₱94.5M | 50% | High risk62 | Flagged0.001 |
| 25A00424CONSTRUCTION OF MISSING LINKS/ NEW ROADS, ROAD CONNECTING SANTA-RANCHO ROAD (S00089LZ) AND SANTA-CAOAYAN ROAD, ILOCOS SUR (PACKAGE 3) | Region I | Region I | On-Going | ₱89.8M | 54% | Medium risk55 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 151 | 19AC0098CONST. OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING, ILOCOS SUR NATIONAL H/S, VIGAN CITY | Region I | Ilocos Sur 1st DEO | Completed | ₱11.1M | 100% | Medium risk43 | —-0.036 |
| 152 | 18AC0025CONSTRUCTION OF SEAWALL, PARATONG, STA. CATALINA, ILOCOS SUR | Region I | Ilocos Sur 1st DEO | Completed | ₱11.8M | 100% | Medium risk43 | —-0.068 |
| 153 | 18AC0007CONSTRUCTION OF SEAWALL, SUBEC, STA. CATALINA, ILOCOS SUR | Region I | Ilocos Sur 1st DEO | Completed | ₱11.8M | 100% | Medium risk43 | —-0.068 |
| 154 | 18AD0050CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT/OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS LOCAL ROAD AND BRIDGES-CONSTRUCTION SUGPON ROAD LEADING TO SUGPON-SUDIPEN ROAD, SUGPON, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱18.6M | 100% | Medium risk43 | —-0.087 |
| 155 | 18AF0053REHAB/RECONST OF NAT RDS WITH SLIPS, SLOPE COLLAPSE & LANDSLIDE,2ND | Region I | La Union 2nd DEO | Completed | ₱17M | 100% | Medium risk43 | —-0.089 |
| 156 | 25A00213CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - VIGAN BOARDWALK ROAD LEADING TO THE HERITAGE VILLAGE, VIGAN CITY, ILOCOS SUR | Region I | Region I | On-Going | ₱9.4M | 81% | Medium risk43 | —-0.043 |
| 157 | 17AC0130CONSTRUCTION OF SCHOOL BUILDING, PANDAN ELEMENTARY SCHOOL, CAOAYAN, ILOCOS SUR | Region I | Ilocos Sur 1st DEO | Completed | ₱4.8M | 100% | Medium risk43 | —-0.017 |
| 158 | 21AB0047LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY SAN JOSE, SAN NICOLAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱2.9M | 100% | Medium risk43 | —-0.081 |
| 159 | 22AB0049CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAN BARTOLOME, SAN NICOLAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱2.9M | 100% | Medium risk43 | —-0.082 |
| 160 | 18AC0065CONSTRCUTION OF DRAINAGE CANAL ALONG SALOMAGUE PORT ROAD, K0436+000 - K0436+461 | Region I | Ilocos Sur 1st DEO | Completed | ₱8.5M | 100% | Medium risk42 | —-0.084 |
| 161 | 18AC0068SHOULDER PAVING / CONSTRUCTION OF SALOMAGUE PORT ROAD,CABUGAO, ILOCOS SUR, K0435+000 - K0435+666.70 | Region I | Ilocos Sur 1st DEO | Completed | ₱6.2M | 100% | Medium risk42 | —-0.084 |
| 162 | 23AB0046CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAN GUILLERMO (CATUGUING), SAN NICOLAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱4M | 100% | Medium risk42 | —-0.081 |
| 163 | 22AB0059CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY STA. CECILIA, SAN NICOLAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱2.9M | 100% | Medium risk41 | —-0.081 |
| 164 | 17AC0075CONST. OF RAINWATER COLLECTION SYSTEM, MASADAG E/S, SINAIT; STA. CRUZ E/S, SINAIT; ARNAP E/S, ETC. | Region I | Ilocos Sur 1st DEO | Completed | ₱3.1M | 100% | Medium risk41 | —-0.018 |
| 165 | 22AB0055CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAN GUILLERMO, SAN NICOLAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱3M | 100% | Medium risk41 | —-0.082 |
| 166 | 23AB0048CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAN PEDRO (BINGAO), SAN NICOLAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱3M | 100% | Medium risk40 | —-0.080 |
| 167 | 21BA0026REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE; UYUGAN - MAHATAO INTERIOR ROAD - K0026+583.5- K0026+639.5, K0026+648.7- K0026+694.1, K0027+152- K0027+200.5, BATAN ISLAND, BATANES | Region II | Batanes DEO | Completed | ₱42.7M | 100% | Medium risk40 | —-0.069 |
| 168 | 18AC0096CONCRETING OF BRGY. MALAMIN FMR, BRGY. MALAMIN, SAN JUAN, ILOCOS SUR | Region I | Ilocos Sur 1st DEO | Completed | ₱4.8M | 100% | Medium risk39 | —-0.031 |
| 169 | 20AB0045LOCAL INFRASTRUCTURE PROGRAM, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. 18, SAN PEDRO, SAN NICOLAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱2M | 100% | Medium risk37 | —-0.081 |
| 170 | 20AB0118CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. 23 STA. CECILIA, SAN NICOLAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱2M | 100% | Medium risk37 | —-0.081 |
| 171 | 20AB0046LOCAL INFRASTRUCTURE PROGRAM, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. 22, SAN GUILLERMO, SAN NICOLAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱2M | 100% | Medium risk37 | —-0.082 |
| 172 | 20AB0078LOCAL INFRASTRUCTURE PROGRAM, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PAGDILAO, PINILI, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱2M | 100% | Medium risk33 | —-0.083 |
| 173 | 19AC0008CONSTRUCTION OF FLOOD CONTROL ALONG CABUGAO RIVER, BRGY. CATUCDAAN, CABUGAO, ILOCOS SUR | Region I | Ilocos Sur 1st DEO | Completed | ₱4.7M | 100% | Low risk30 | —-0.066 |
| 174 | 21AC0082CONSTRUCTION OF MULTI-PURPOSE BUILDING TAY-AC NATIONAL HIGH SCHOOL, BARANGAY TAY-AC, BANTAY, ILOCOS SUR | Region I | Ilocos Sur 1st DEO | Completed | ₱4M | 100% | Low risk29 | —-0.083 |
| 175 | 18AC0034CONSTRUCTION OF MULTI-PURPOSE BUILDING, SAN LUCAS, MAGSINGAL, ILOCOS SUR | Region I | Ilocos Sur 1st DEO | Completed | ₱2.4M | 100% | Low risk28 | —-0.078 |