Contractor dossier
12 projects on file, including joint ventures this contractor is part of.
Total projects
12
Total budget
₱369.3M
Average progress
100.0%
Completion rate
100.0%
Average risk score
50.5
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 12 | ₱369.3M | 50.5 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 9 | ₱197.7M | 49.8 | 0 | 100.0% |
| Flood Control and Drainage | 3 | ₱171.6M | 52.6 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 16HH0109CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, TALAMBAN - BACAYAN - PIT-OS ROAD, CEBU CITY | Region VII | Cebu City DEO | Completed | ₱40.1M | 100% | Medium risk57 | —-0.064 |
| 2 | 17HH0027PREVENTIVE MAINTENANCE BASED ON PAVEMENT MANAGEMENT SYSTEM / HIGHWAY DEVELOPMENT AND MANAGEMENT-4 (HDM-4), SECONDARY ROADS, CEBU SOUTH COASTAL RD, K0009+563 - K0009+730, K0010+100 - K0010+418, CEBU CITY | Region VII | Cebu City DEO | Completed | ₱26.4M | 100% | Medium risk56 | —-0.065 |
| 3 | 17HH0108ASSET PRESERVATION - REHABILITATION OF DAMAGED PAVED ROADS - TERTIARY ROADS, QUEZON BLVD. (CB) (S00119CB), CHAINAGE 0 - CHAINAGE 89, (S00120CB) CHAINAGE 0 - CHAINAGE 209, CEBU CITY | Region VII | Cebu City DEO | Completed | ₱23.4M | 100% | Medium risk56 | —-0.065 |
| 4 | 16HH0089REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED NAT'L. ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM / HIGHWAY DEV'T & MANAGEMENT(HDM-4)(INTERMITTENT SECTIONS) (SECONDARY ROAD), CEBU SOUTH ROAD SERVICE ROAD, CHAINAGE 000-0427 ( | Region VII | Cebu City DEO | Completed | ₱20.1M | 100% | Medium risk56 | —-0.065 |
| 5 | 16HH0088REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM / HIGHWAY DEVELOPMENT AND MANAGEMENT (HDM-4) (INTERMITTENT SECTIONS) (SECONDARY ROAD), S. OSMEÑABLVD., CHAINAGE 0000-0200 (S | Region VII | Cebu City DEO | Completed | ₱7.1M | 100% | Medium risk55 | —-0.064 |
| 6 | 19HH0066OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BUTUANON RIVER, BRGY. PIT-OS, CEBU CIT | Region VII | Cebu City DEO | Completed | ₱58.5M | 100% | Medium risk54 | —-0.074 |
| 7 | 19HH0058OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BUTUANON RIVER, BRGY. PULANGBATO, CEBU CI | Region VII | Cebu City DEO | Completed | ₱62.3M | 100% | Medium risk54 | —-0.076 |
| 8 | 19HH0065OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BUTUANON RIVER, BRGY. BACAYAN, CEBU C | Region VII | Cebu City DEO | Completed | ₱50.8M | 100% | Medium risk50 | —-0.077 |
| 9 | 22HH0024OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE -TERTIARY ROADS- CEBU-GUADALUPE RD - (S00065CB) CHAINAGE 000 - CHAINAGE 1616, (S00171CB) - CHAINAGE 000 - CHAINAGE 462, CEBU CITY | Region VII | Cebu City DEO | Completed | ₱38.4M | 100% | Medium risk47 | —-0.096 |
| 10 | 18HH0031CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, BACAYAN-PIT-OS-PULANGBATO ROAD, LEADING TO SIRAO FLOWER GARDEN, WATERFALLS, BRGY. PIT-OS & PULANGBATO, CEBU CITY | Region VII | Cebu City DEO | Completed | ₱31M | 100% | Medium risk47 | —-0.096 |
| 11 | 18HH0067ROAD CONCRETING AT BRGY. ADLAON, CEBU CITY | Region VII | Cebu City DEO | Completed | ₱9.1M | 100% | Medium risk46 | —-0.098 |
| 12 | 16HH0085OFF-CARRIAGEWAY IMPROVEMENT, B. RODRIGUEZ ST., CHAINAGE 000 - CHAINAGE 0470 (S00061CB), CEBU CITY | Region VII | Cebu City DEO | Completed | ₱2.1M | 100% | Low risk29 | —-0.065 |