Contractor dossier
370 projects on file, including joint ventures this contractor is part of.
Total projects
370
Total budget
₱10.8B
Average progress
93.3%
Completion rate
85.4%
Average risk score
46.7
Medium risk on average, out of 100
Flagged as unusual
2
0.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 277 | ₱6B | 44.5 | 1 | 92.7% |
| Region IV-A | 78 | ₱4.1B | 53.6 | 1 | 95.0% |
| Region III | 6 | ₱110.6M | 43.2 | 0 | 91.7% |
| Region V | 4 | ₱168.8M | 54.3 | 0 | 100.0% |
| Central Office | 3 | ₱352.1M | 74.9 | 0 | 100.0% |
| Region IV-B | 2 | ₱88.2M | 41.1 | 0 | 95.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 252 | ₱5.4B | 44.1 | 0 | 92.7% |
| Flood Control and Drainage | 92 | ₱4.7B | 50.8 | 1 | 97.1% |
| Buildings and Facilities | 17 | ₱298M | 47.1 | 0 | 84.8% |
| GAA 2025 OO-1 | 6 | ₱138.4M | 82.7 | 1 | 81.2% |
| OTHER | 2 | ₱94.2M | 70.9 | 0 | 100.0% |
| GAA 2025 OO-2 | 1 | ₱95.3M | 71.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DO0016ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - MANILA EAST RD - K0044 + 910 - K0045 + 000, K0054 + 132 - K0054 + 619, K0054 + 859 - K0056 + 000 | Region IV-A | Rizal 2nd DEO | On-Going | ₱48.2M | 97% | High risk91 | —-0.016 |
| 25OC0058ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS-NINOY AQUINO AVE - K0011 + 938 - K0010 + 526PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱40.8M | 95% | High risk86 | —-0.018 |
| 25OC0040ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE -PRIMARY ROADS - PARAÑAQUE-SUCAT RD - K0017 + 663 -K0016 + 000PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱21.6M | 95% | High risk86 | —-0.017 |
| 25OC0039ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS-PARAÑAQUE-SUCAT RD - K0016 + 234- K0016 + 349PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱6.6M | 0% | High risk85 | Flagged0.009 |
| 25OC0038ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS-PARANAQUE-SUCAT RD - K0015 + 372 - K0015 + 728PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | Completed | ₱20.2M | 100% | High risk78 | —-0.043 |
| 18C00052DREDGING OF GUAGUA-PASAC RIVER, SASMUAN, PAMPANGA | Central Office | Flood Control Management Cluster | Completed | ₱187.5M | 100% | High risk77 | —-0.034 |
| 21O00095CONSTRUCTION OF RIVERWALLS (INTERMITTENT SECTIONS) ALONG MALABON-TULLAHAN RIVER (UPSTREAM SIDE), BRGY. POTRERO, MALABON CITY | Central Office | Flood Control Management Cluster | Completed | ₱92.4M | 100% | High risk75 | —-0.069 |
| 20C00050REHABILITATION OF PAMPANGA RIVER (INLCUDING PULO) AT ARAYAT AND MACABEBE, PAMPANGA, PROVINCE OF PAMPANGA | Central Office | Flood Control Management Cluster | On-Going | ₱72.1M | 100% | High risk73 | —-0.022 |
| 24DF0154ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAMCONSTRUCTION OF BY-PASS AND DIVERSION ROADSREHABILITATION OF ROAD ALONG KAWIT-NOVELETA DIVERSION RD K0022+151-K0022 + 528, K0023+000-K0023+750 | Region IV-A | Cavite 1st DEO | On-Going | ₱95.5M | 0% | High risk73 | —-0.001 |
| 25DF0036ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMASSET PRESERVATION PROGRAMREHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADSKAWIT-NOVELETA DIV RD. - K0024 + 495 - K0025 + 438 | Region IV-A | Cavite 1st DEO | On-Going | ₱103.9M | 100% | High risk72 | —-0.044 |
| 25OH0025ORGANIZATIONAL OUTCOME 2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONST./MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS-CONST. OF SLOPE PROTECTION STRUCTURE/BANK IMPV'T. OF MARICABAN CREEK, STA. 0+936 TO STA.1+170 | National Capital Region | South Manila DEO | Completed | ₱95.3M | 100% | High risk72 | —-0.043 |
| 24DO0069ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURES | Region IV-A | Rizal 2nd DEO | Completed | ₱49M | 100% | High risk71 | —-0.041 |
| 24DJ0185OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, QUEZON-BATANGAS RD - K0106 + 284 - K0107 + 489 | Region IV-A | Quezon 2nd DEO | On-Going | ₱96.5M | 92% | High risk71 | —-0.034 |
| 24DO0053ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - PREVENTIVE MAINTENANCE - TERTIARY ROADS - MARIKINA-INFANTA RD - K0040+205 - K0041+744 | Region IV-A | Rizal 2nd DEO | Completed | ₱45.2M | 100% | High risk70 | —-0.040 |
| 25OC0008ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-TERTIARY ROADS-EDSA/GUADALUPE CLOVERLEAF RD-(S04000LZ) CHAINAGE 000-CHAINAGE 028, CHAINAGE 196-CHAINAGE 203,MAKATI CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱1.1M | 100% | High risk70 | —-0.021 |
| 25CP0027FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF RIVERBANK PROTECTION ALONG MAASIM RIVER, BARANGAY SAPANG PUTIK, PHASE II, SAPANG PUTIK, SAN ILDEFONSO, BULACAN | Region III | Bulacan 3rd DEO | On-Going | ₱28.5M | 50% | High risk69 | —-0.018 |
| 17CH0021CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION/IMPROVEMEN | Region III | Pampanga 2nd DEO | Completed | ₱40.1M | 100% | High risk68 | —-0.061 |
| 25OC0123CONSTRUCTION OF REVETMENT ALONG PARAÑAQUE RIVER, DISTRICT 1,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱94.6M | 18% | High risk67 | —-0.025 |
| 17DQ0041MFO 2 - FOOD MANAGEMENT SERVICES, CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATON STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SLOPE PROTECTION ALONG METIZO RIVER, BARANGAY HABAY 2, BACOOR CITY, CAVITE | Region IV-A | Cavite 3rd DEO | Completed | ₱9.3M | 100% | High risk67 | —-0.059 |
| 24DF0272ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE & RELIABLE NATIONAL RD SYSTEMASSET PRESERVATION PROGREHAB/ RECONST/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADSKAWIT-NOVELETA-DIVERSION RD - K0022 + (-224) - K0022 + 143, K0022 + 151-K0022+450 | Region IV-A | Cavite 1st DEO | On-Going | ₱14.2M | 0% | High risk67 | —-0.009 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23DF0201CONSTRUCTION OF REVETMENT ALONG TAGUILID RIVER, BRGY. KAINGEN, KAWIT, CAVITE | Region IV-A | Cavite 1st DEO | On-Going | ₱28.7M | 100% | Medium risk52 | Flagged0.014 |
| 25OC0039ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS-PARAÑAQUE-SUCAT RD - K0016 + 234- K0016 + 349PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱6.6M | 0% | High risk85 | Flagged0.009 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 151 | 20OI0106CONSTRUCTION OF RETAINING WALL AT MAGDAONG CREEK, BRGY. TUNASAN, MUNTINLUPA CITY | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱29.4M | 100% | Medium risk46 | —-0.084 |
| 152 | 23DQ0035CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS - MANILA-CAVITE (NCR BDRY-JCT CAVITE CITY SECT) - K0019 + 390 - K0020 + 163 | Region IV-A | Cavite 3rd DEO | Completed | ₱17.5M | 100% | Medium risk46 | —-0.107 |
| 153 | 24DO0058ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - MANILA EAST RD - K0066+506 - K0066+714, K0067+152 - K0067+498 | Region IV-A | Rizal 2nd DEO | Completed | ₱14.7M | 100% | Medium risk46 | —-0.107 |
| 154 | 18DQ0016ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF REVETMENT ALONG IMUS RIVER | Region IV-A | Region IV-A | Completed | ₱39M | 100% | Medium risk46 | —-0.086 |
| 155 | 25OC0043ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - ROXAS BLVD-K0007 + 066 - K0007 + 293PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱26.9M | 0% | Medium risk46 | —-0.036 |
| 156 | 23OB0132ASSET PRESERVATION PROGRAM PREVENTIVE MAINTENANCE PRIMARY ROADS - C-5 ROAD - K0015 + (-1851) - K0015 + (-386) | National Capital Region | Metro Manila 1st DEO | Completed | ₱25.1M | 100% | Medium risk46 | —-0.098 |
| 157 | 25OC0010ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-PARAÑAQUE-SUCAT RD-K0013+(-266)-K0013+127,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱22.7M | 0% | Medium risk46 | —-0.035 |
| 158 | 25OC0115ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-PARAÑAQUE-SUCAT RD,-K0013+(-785)-K0013+(-702), K0013+(-639)-K0013+(-266),PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱25.7M | 0% | Medium risk46 | —-0.036 |
| 159 | 25OC0116ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-PARAÑAQUE-SUCAT RD,-K0013+266-K0013+623,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱20.5M | 0% | Medium risk46 | —-0.036 |
| 160 | 25OC0037ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS-PARANAQUE-SUCAT RD - K0015 + 023 - K0015 + 486PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱25.1M | 96% | Medium risk46 | —-0.067 |
| 161 | 22OI0008PREVENTIVE MAINTENANCE - SECONDARY ROADS PARANAQUE-SUCAT ROAD-K0020+(-526)-K0020+(-233), MUNTINLUPA CITY | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱21.7M | 100% | Medium risk46 | —-0.095 |
| 162 | 21OH0044ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-SECONDARY ROADS-ANDREW AVENUE-K0008+(-058)-K0008+(-009),K0008+(-453)-K0008+(-058),K0008+(-550)-K0008+(-453),K0008+(-750)-K0008+(-550), | National Capital Region | South Manila DEO | Completed | ₱26.5M | 100% | Medium risk46 | —-0.095 |
| 163 | 23OC0098CONSTRUCTION OF ROAD, VICTOR MEDINA ST., DISTRICT I,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | Completed | ₱19.6M | 100% | Medium risk46 | —-0.098 |
| 164 | 21OH0037ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION-PREVENTIVE MAINTENANCE-TERTIARY ROADS-SOUTH SUPER H-WAY WEST SERVICE RD-K0012+351-K0013+287, PASAY CITY | National Capital Region | South Manila DEO | Completed | ₱22.9M | 100% | Medium risk46 | —-0.098 |
| 165 | 25OC0011ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE -PRIMARY ROADS - PARAÑAQUE-SUCAT RD - K0013 + 724 -K0014 + 056PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱19M | 0% | Medium risk46 | —-0.035 |
| 166 | 25OC0012ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-PARAÑAQUE-SUCAT RD-K0014+116-K0014+420,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱17.9M | 97% | Medium risk46 | —-0.067 |
| 167 | 21OH0067CONVERGENCE AND SPECIAL SUPPORT PROGRAM/SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER RA 11329, REPAIR/MAINTENANCE (ASPHALT OVERLAY) ALONG NAIA ROAD FROM TAMBO BRIDGE TO MIAA, PASAY CITY | National Capital Region | South Manila DEO | Completed | ₱19.2M | 100% | Medium risk46 | —-0.098 |
| 168 | 19OC0051IMPROVEMENT/SHEET PILING OF VILLANUEVA CREEK PHASE I (LOPEZ-SALVADOR BRIDGE),PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | Completed | ₱46.5M | 100% | Medium risk46 | —-0.067 |
| 169 | 24DF0014ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMASSET PRESERVATION PROGRAMPREVENTIVE MAINTENANCE - PRIMARY ROADSMANILA-CAVITE RD - K0027 + (-504) - K0027 + (-386), K0033 + 322 - K0033 + 622 | Region IV-A | Cavite 1st DEO | Completed | ₱19.7M | 100% | Medium risk46 | —-0.104 |
| 170 | 25OE0089PREVENTIVE MAINTENANCE - TERTIARY ROADS - ARLEGUI ST - K0003 + (-218) - K0003 + 364 | National Capital Region | North Manila DEO | On-Going | ₱22.8M | 85% | Medium risk46 | —-0.063 |
| 171 | 25OE0098PREVENTIVE MAINTENANCE - TERTIARY ROADS - QUEZON BLVD (LZ) - (S02553LZ) CHAINAGE 000 - CHAINAGE 294 | National Capital Region | North Manila DEO | On-Going | ₱23.1M | 87% | Medium risk46 | —-0.065 |
| 172 | 20OG0026PREVENTIVE MAINTENANCE OF ROAD : ASPHALT OVERLAY - KAMIAS RD -K0010+(-720)-K0010 +153, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱22.3M | 100% | Medium risk46 | —-0.096 |
| 173 | 20OF0300ASPHALT OVERLAY OF VARIOUS ROAD, BRGY. NORTH FAIRVIEW, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱23.7M | 100% | Medium risk46 | —-0.097 |
| 174 | 20OF0303ASPHALT OVERLAY OF VARIOUS ROADS, BRGY. STA. LUCIA, NOVALICHES, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱23.8M | 100% | Medium risk46 | —-0.098 |
| 175 | 19OH0004ORGANIZATIONAL OUTCOME 1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATON PROGRAM-PRE | National Capital Region | South Manila DEO | Completed | ₱20.6M | 100% | Medium risk46 | —-0.098 |