Contractor dossier
370 projects on file, including joint ventures this contractor is part of.
Total projects
370
Total budget
₱10.8B
Average progress
93.3%
Completion rate
85.4%
Average risk score
46.7
Medium risk on average, out of 100
Flagged as unusual
2
0.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 277 | ₱6B | 44.5 | 1 | 92.7% |
| Region IV-A | 78 | ₱4.1B | 53.6 | 1 | 95.0% |
| Region III | 6 | ₱110.6M | 43.2 | 0 | 91.7% |
| Region V | 4 | ₱168.8M | 54.3 | 0 | 100.0% |
| Central Office | 3 | ₱352.1M | 74.9 | 0 | 100.0% |
| Region IV-B | 2 | ₱88.2M | 41.1 | 0 | 95.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 252 | ₱5.4B | 44.1 | 0 | 92.7% |
| Flood Control and Drainage | 92 | ₱4.7B | 50.8 | 1 | 97.1% |
| Buildings and Facilities | 17 | ₱298M | 47.1 | 0 | 84.8% |
| GAA 2025 OO-1 | 6 | ₱138.4M | 82.7 | 1 | 81.2% |
| OTHER | 2 | ₱94.2M | 70.9 | 0 | 100.0% |
| GAA 2025 OO-2 | 1 | ₱95.3M | 71.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DO0016ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - MANILA EAST RD - K0044 + 910 - K0045 + 000, K0054 + 132 - K0054 + 619, K0054 + 859 - K0056 + 000 | Region IV-A | Rizal 2nd DEO | On-Going | ₱48.2M | 97% | High risk91 | —-0.016 |
| 25OC0058ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS-NINOY AQUINO AVE - K0011 + 938 - K0010 + 526PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱40.8M | 95% | High risk86 | —-0.018 |
| 25OC0040ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE -PRIMARY ROADS - PARAÑAQUE-SUCAT RD - K0017 + 663 -K0016 + 000PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱21.6M | 95% | High risk86 | —-0.017 |
| 25OC0039ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS-PARAÑAQUE-SUCAT RD - K0016 + 234- K0016 + 349PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱6.6M | 0% | High risk85 | Flagged0.009 |
| 25OC0038ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS-PARANAQUE-SUCAT RD - K0015 + 372 - K0015 + 728PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | Completed | ₱20.2M | 100% | High risk78 | —-0.043 |
| 18C00052DREDGING OF GUAGUA-PASAC RIVER, SASMUAN, PAMPANGA | Central Office | Flood Control Management Cluster | Completed | ₱187.5M | 100% | High risk77 | —-0.034 |
| 21O00095CONSTRUCTION OF RIVERWALLS (INTERMITTENT SECTIONS) ALONG MALABON-TULLAHAN RIVER (UPSTREAM SIDE), BRGY. POTRERO, MALABON CITY | Central Office | Flood Control Management Cluster | Completed | ₱92.4M | 100% | High risk75 | —-0.069 |
| 20C00050REHABILITATION OF PAMPANGA RIVER (INLCUDING PULO) AT ARAYAT AND MACABEBE, PAMPANGA, PROVINCE OF PAMPANGA | Central Office | Flood Control Management Cluster | On-Going | ₱72.1M | 100% | High risk73 | —-0.022 |
| 24DF0154ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAMCONSTRUCTION OF BY-PASS AND DIVERSION ROADSREHABILITATION OF ROAD ALONG KAWIT-NOVELETA DIVERSION RD K0022+151-K0022 + 528, K0023+000-K0023+750 | Region IV-A | Cavite 1st DEO | On-Going | ₱95.5M | 0% | High risk73 | —-0.001 |
| 25DF0036ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMASSET PRESERVATION PROGRAMREHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADSKAWIT-NOVELETA DIV RD. - K0024 + 495 - K0025 + 438 | Region IV-A | Cavite 1st DEO | On-Going | ₱103.9M | 100% | High risk72 | —-0.044 |
| 25OH0025ORGANIZATIONAL OUTCOME 2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONST./MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS-CONST. OF SLOPE PROTECTION STRUCTURE/BANK IMPV'T. OF MARICABAN CREEK, STA. 0+936 TO STA.1+170 | National Capital Region | South Manila DEO | Completed | ₱95.3M | 100% | High risk72 | —-0.043 |
| 24DO0069ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURES | Region IV-A | Rizal 2nd DEO | Completed | ₱49M | 100% | High risk71 | —-0.041 |
| 24DJ0185OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, QUEZON-BATANGAS RD - K0106 + 284 - K0107 + 489 | Region IV-A | Quezon 2nd DEO | On-Going | ₱96.5M | 92% | High risk71 | —-0.034 |
| 24DO0053ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - PREVENTIVE MAINTENANCE - TERTIARY ROADS - MARIKINA-INFANTA RD - K0040+205 - K0041+744 | Region IV-A | Rizal 2nd DEO | Completed | ₱45.2M | 100% | High risk70 | —-0.040 |
| 25OC0008ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-TERTIARY ROADS-EDSA/GUADALUPE CLOVERLEAF RD-(S04000LZ) CHAINAGE 000-CHAINAGE 028, CHAINAGE 196-CHAINAGE 203,MAKATI CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱1.1M | 100% | High risk70 | —-0.021 |
| 25CP0027FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF RIVERBANK PROTECTION ALONG MAASIM RIVER, BARANGAY SAPANG PUTIK, PHASE II, SAPANG PUTIK, SAN ILDEFONSO, BULACAN | Region III | Bulacan 3rd DEO | On-Going | ₱28.5M | 50% | High risk69 | —-0.018 |
| 17CH0021CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION/IMPROVEMEN | Region III | Pampanga 2nd DEO | Completed | ₱40.1M | 100% | High risk68 | —-0.061 |
| 25OC0123CONSTRUCTION OF REVETMENT ALONG PARAÑAQUE RIVER, DISTRICT 1,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱94.6M | 18% | High risk67 | —-0.025 |
| 17DQ0041MFO 2 - FOOD MANAGEMENT SERVICES, CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATON STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SLOPE PROTECTION ALONG METIZO RIVER, BARANGAY HABAY 2, BACOOR CITY, CAVITE | Region IV-A | Cavite 3rd DEO | Completed | ₱9.3M | 100% | High risk67 | —-0.059 |
| 24DF0272ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE & RELIABLE NATIONAL RD SYSTEMASSET PRESERVATION PROGREHAB/ RECONST/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADSKAWIT-NOVELETA-DIVERSION RD - K0022 + (-224) - K0022 + 143, K0022 + 151-K0022+450 | Region IV-A | Cavite 1st DEO | On-Going | ₱14.2M | 0% | High risk67 | —-0.009 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23DF0201CONSTRUCTION OF REVETMENT ALONG TAGUILID RIVER, BRGY. KAINGEN, KAWIT, CAVITE | Region IV-A | Cavite 1st DEO | On-Going | ₱28.7M | 100% | Medium risk52 | Flagged0.014 |
| 25OC0039ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS-PARAÑAQUE-SUCAT RD - K0016 + 234- K0016 + 349PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱6.6M | 0% | High risk85 | Flagged0.009 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 176 | 19OH0007ORGANIZATIONAL OUTCOME1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-RE | National Capital Region | South Manila DEO | Completed | ₱24.3M | 100% | Medium risk46 | —-0.098 |
| 177 | 20OF0301ASPHALT OVERLAY OF VARIOUS ROADS, BRGY SAN AGUSTIN, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱24M | 100% | Medium risk46 | —-0.098 |
| 178 | 20OF0304ASPHALT OVERLAY OF VARIOUS, BRGY. NAGKAISANG NAYON AND CAPRI NOVALICHES, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱23.8M | 100% | Medium risk46 | —-0.098 |
| 179 | 21OG0008REHABILITATION OF ROAD, BARANGAY WHITE PLAINS, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱28.1M | 100% | Medium risk46 | —-0.099 |
| 180 | 20OG0027PREVENTIVE MAINTENANCE OF ROAD : ASPHALT OVERLAY-E. RODRIGUEZ JR. AVE.-K0014+068-K0014+973, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱28.1M | 100% | Medium risk46 | —-0.099 |
| 181 | 18OH0009PREVENTIVE MAINTENANCE/ASPHALT OVERLAY ALONG EPIFANIO DELOS SANTOS AVENUE (EDSA),K0031+015-K0031+725 | National Capital Region | South Manila DEO | Completed | ₱19.3M | 100% | Medium risk46 | —-0.099 |
| 182 | 21OH0058CONVERGENCE AND SPECIAL SUPPORT PROGRAM/SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER RA 11329, REPAIR/MAINTENANCE (ASPHALT OVERLAY) ALONG OSMEÑA HIGHWAY FROM P. QUIRINO AVE TO CITY LIMIT, MANILA | National Capital Region | South Manila DEO | Completed | ₱19.3M | 100% | Medium risk46 | —-0.099 |
| 183 | 23OE0157PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG TAYUMAN ST. (S02325LZ) - K0007 + 308.2 - K0007 + 1003.7, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱21.5M | 100% | Medium risk46 | —-0.099 |
| 184 | 23OE0156PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG CM RECTO AVE. (S02229LZ), STA. CRUZ, MANILA CITY - K0004 + (-1584.70) - K0004 + (-1199.00), K0004 + (099.40) - K0004 + 225.80 | National Capital Region | North Manila DEO | Completed | ₱26.5M | 100% | Medium risk46 | —-0.099 |
| 185 | 21OG0066REHABILITATION OF ROAD, BARANGAY E. RODRIGUEZ, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱28.2M | 100% | Medium risk46 | —-0.100 |
| 186 | 21OG0009REHABILITATION OF ROAD, BARANGAY ST. IGNATIUS, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱23.4M | 100% | Medium risk46 | —-0.100 |
| 187 | 25OE0097PREVENTIVE MAINTENANCE - SECONDARY ROADS - AH LACSON AVE - K0009 + (-999) - K0009 + (-546) | National Capital Region | North Manila DEO | Completed | ₱26.6M | 100% | Medium risk46 | —-0.100 |
| 188 | 23OE0160PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG BLUMENTRITT ST. C 400 - C 734, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱26.7M | 100% | Medium risk46 | —-0.100 |
| 189 | 25OE0091PREVENTIVE MAINTENANCE - TERTIARY ROADS - AURORA AVENUE - (S02355LZ) CHAINAGE 493 - CHAINAGE 666 | National Capital Region | North Manila DEO | Completed | ₱20.4M | 100% | Medium risk46 | —-0.100 |
| 190 | 22OE0052PREVENTIVE MAINTENANCE - TERTIARY ROADS - JUAN LUNA ST - K0003 + 637.70 - K0004 + 073.70, K0004 + 797.50 - K0005 + 021.10 | National Capital Region | North Manila DEO | Completed | ₱23.5M | 100% | Medium risk46 | —-0.098 |
| 191 | 23OH0020ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-EPIFANIO DELOS SANTOS AVENUE (EDSA)-K0031+000-K0031+356 | National Capital Region | South Manila DEO | Completed | ₱14.4M | 100% | Medium risk46 | —-0.100 |
| 192 | 20OH0069OO1:ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM-PREVENTIVE MAINT.-SECOND | National Capital Region | South Manila DEO | Completed | ₱18.4M | 100% | Medium risk46 | —-0.097 |
| 193 | 18OC0056ASSET PRESERVATION PROGRAM, REHABILITATION/RECONSTRUCTION OF PAVED ROAD ALONG QUIRINO AVENUE TO K0007+(-332) TO K0007+003,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | Completed | ₱17.1M | 100% | Medium risk46 | —-0.098 |
| 194 | 19OC0129PROPOSED IMPROVEMENT/SHEET PILING ALONG KAYBUBOY CREEK (PARAÑAQUE-LAS PIÑAS BOUNDARY EAST SECTION),PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | Completed | ₱46.5M | 100% | Medium risk46 | —-0.064 |
| 195 | 21OE0048PREVENTIVE MAINTENANCE - SECONDARY ROADS - R-10 K0005 + (-591.80) - K0005 + (-065.80) | National Capital Region | North Manila DEO | Completed | ₱24.3M | 100% | Medium risk46 | —-0.098 |
| 196 | 22OE0043PREVENTIVE MAINTENANCE - SECONDARY ROADS - C-2 ROAD - K0006+233.10 - K0006+850.20 | National Capital Region | North Manila DEO | Completed | ₱25.5M | 100% | Medium risk46 | —-0.099 |
| 197 | 21OI0117CONSTRUCTION OF DRAINAGE SYSTEM ALONG MONTILLANO STREET EXTENSION AND VICINITY, BRGY. ALABANG, MUNTINLUPA CITY | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱9.9M | 100% | Medium risk46 | —-0.083 |
| 198 | 19OI0160CONSTRUCTION OF FLOOD CONTROL STRUCTURE (INCLUDING PATHWAY), PASONG DIABLO CREEK, TRIBUTARY, BRGY. ALABANG, MUNTINLUPA CITY | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱8.9M | 100% | Medium risk46 | —-0.086 |
| 199 | 25OC0007ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - KALAYAAN AVE EXT - K0027 + 000 - K0027 + 396MAKATI CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱14.8M | 0% | Medium risk46 | —-0.036 |
| 200 | 22OH0068ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHAB./RECONST./UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-EPIFANIO DELOS SANTOS AVE. (EDSA),K0032+474-K0032+774,PASAY CITY | National Capital Region | South Manila DEO | Completed | ₱19.1M | 100% | Medium risk46 | —-0.089 |