Contractor dossier
35 projects on file, including joint ventures this contractor is part of.
Total projects
35
Total budget
₱1.4B
Average progress
59.7%
Completion rate
37.1%
Below 70%
Average risk score
52.7
Medium risk on average, out of 100
Flagged as unusual
6
17.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 35 | ₱1.4B | 52.7 | 6 | 59.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 11 | ₱366.6M | 50.7 | 1 | 67.6% |
| Flood Control and Drainage | 10 | ₱357.9M | 49.3 | 1 | 62.8% |
| Buildings and Facilities | 6 | ₱165M | 50.4 | 0 | 38.0% |
| Bridges | 4 | ₱273.6M | 56.6 | 1 | 70.6% |
| OTHER | 2 | ₱169.2M | 62.6 | 2 | 3.9% |
| GAA 2025 SSP | 1 | ₱14.7M | 93.6 | 1 | 100.0% |
| Water Provision and Storage | 1 | ₱29.4M | 45.4 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HN0017SSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - COASTAL ROADS TO AUGMENT RESILLIENCY OF COASTAL COMMUNITIES - CONSTRUCTION OF CAUSEWAY, PHASE 2, BARANGAY MARIGONDON, LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱14.7M | 100% | High risk94 | Flagged0.007 |
| 24HN0141CSSP: SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD INCLUDING BRIDGE FROM SUDTUNGGAN TO BRGY. BABAG, LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱144.7M | 8% | High risk73 | Flagged0.045 |
| 25HD0146ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONST/MAINT OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONST OF FLOOD CONTROL ALONG MANANGA RIVER (RIGHT SIDE) AT SITIO KAWATAN, BRGY TABUN | Region VII | Cebu 1st DEO | On-Going | ₱144.7M | 6% | High risk67 | Flagged0.005 |
| 25HD0188CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONST OF MANGGILAMON BRIDGE, TALISAY CIT | Region VII | Cebu 1st DEO | On-Going | ₱141.9M | 16% | High risk66 | Flagged0.016 |
| 23HN0160CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CORDOVA-LAPU-LAPU CITY BRIDGE, LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | Completed | ₱98.8M | 100% | High risk64 | —-0.042 |
| 23HO0305CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, IMPROVEMENT OF BUGHO - BALA - BUGUIL ROAD | Region VII | Cebu 7th DEO | On-Going | ₱7.1M | 0% | High risk62 | Flagged0.052 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23HO0305CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, IMPROVEMENT OF BUGHO - BALA - BUGUIL ROAD | Region VII | Cebu 7th DEO | On-Going | ₱7.1M | 0% | High risk62 | Flagged0.052 |
| 24HN0141CSSP: SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD INCLUDING BRIDGE FROM SUDTUNGGAN TO BRGY. BABAG, LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱144.7M | 8% | High risk73 | Flagged0.045 |
| 25HD0188CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONST OF MANGGILAMON BRIDGE, TALISAY CIT | Region VII | Cebu 1st DEO | On-Going | ₱141.9M | 16% | High risk66 | Flagged0.016 |
| 24HN0065CSSP: SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BLDG./ FACILITIES - CONST. OF DIVERSION ROAD FROM SUDTUNGGAN, BRGY. BASAK TO BRGY. GABI (PHASE 2), LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱24.5M | 0% | Medium risk52 | Flagged0.012 |
| 25HN0017SSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - COASTAL ROADS TO AUGMENT RESILLIENCY OF COASTAL COMMUNITIES - CONSTRUCTION OF CAUSEWAY, PHASE 2, BARANGAY MARIGONDON, LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱14.7M | 100% | High risk94 | Flagged0.007 |
| 25HD0146ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONST/MAINT OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONST OF FLOOD CONTROL ALONG MANANGA RIVER (RIGHT SIDE) AT SITIO KAWATAN, BRGY TABUN | Region VII | Cebu 1st DEO | On-Going | ₱144.7M | 6% | High risk67 | Flagged0.005 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25HN0017SSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - COASTAL ROADS TO AUGMENT RESILLIENCY OF COASTAL COMMUNITIES - CONSTRUCTION OF CAUSEWAY, PHASE 2, BARANGAY MARIGONDON, LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱14.7M | 100% | High risk94 | Flagged0.007 |
| 2 | 24HN0141CSSP: SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD INCLUDING BRIDGE FROM SUDTUNGGAN TO BRGY. BABAG, LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱144.7M | 8% | High risk73 | Flagged0.045 |
| 3 | 25HD0146ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONST/MAINT OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONST OF FLOOD CONTROL ALONG MANANGA RIVER (RIGHT SIDE) AT SITIO KAWATAN, BRGY TABUN | Region VII | Cebu 1st DEO | On-Going | ₱144.7M | 6% | High risk67 | Flagged0.005 |
| 4 | 25HD0188CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONST OF MANGGILAMON BRIDGE, TALISAY CIT | Region VII | Cebu 1st DEO | On-Going | ₱141.9M | 16% | High risk66 | Flagged0.016 |
| 5 | 23HN0160CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CORDOVA-LAPU-LAPU CITY BRIDGE, LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | Completed | ₱98.8M | 100% | High risk64 | —-0.042 |
| 6 | 23HO0305CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, IMPROVEMENT OF BUGHO - BALA - BUGUIL ROAD | Region VII | Cebu 7th DEO | On-Going | ₱7.1M | 0% | High risk62 | Flagged0.052 |
| 7 | 23HE0127ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHAB/RECONST OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE- SECONDARY ROADS - CEBU-TOLEDO WHARF RD (JCT NAGA-ULING), K0016+1139-K0016+1219, CAMP 4 | Region VII | Cebu 1st DEO | Completed | ₱96.5M | 100% | Medium risk60 | —-0.084 |
| 8 | 24HE0061ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CEBU-TOLEDO WHARF ROAD LINAO-CANTABACO SECTION, MINGLANILLA, CEBU | Region VII | Cebu 1st DEO | Completed | ₱96.5M | 100% | Medium risk60 | —-0.085 |
| 9 | 25HO0168CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF RONDA MULTI-PURPOSE BUILDING (PHASE I), RONDA, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱48M | 0% | Medium risk54 | —-0.024 |
| 10 | 24HN0065CSSP: SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BLDG./ FACILITIES - CONST. OF DIVERSION ROAD FROM SUDTUNGGAN, BRGY. BASAK TO BRGY. GABI (PHASE 2), LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱24.5M | 0% | Medium risk52 | Flagged0.012 |
| 11 | 25HE0086CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD LEADING TO BUGAS | Region VII | Cebu 2nd DEO | On-Going | ₱48M | 3% | Medium risk51 | —-0.032 |
| 12 | 23H00063LOCAL PROGRAM, NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES, CONSTRUCTION OF MULTI-PURPOSE OFFICE BUILDING, DPWH REGIONAL OFFICE VII, SOUTH ROAD PROPERTIES, CEBU CITY | Region VII | Region VII | On-Going | ₱28.9M | 40% | Medium risk51 | —-0.023 |
| 13 | 24HG0108LOCAL PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES - NATIONAL BUILDING PROGRAM - CONSTRUCTION OF DPWH CEBU 4TH DEO MOTORPOOL BUILDING, DALAGUETE, CEBU | Region VII | Cebu 2nd DEO | On-Going | ₱29.4M | 44% | Medium risk50 | —-0.033 |
| 14 | 24HO0058CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), EVACUATION CENTERS/QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES, CONSTRUCTION OF EVACUATION CENTER, PUROK IHO, SAN ROQUE, BARANGAY POBLACION, ALEGRIA, CEBU | Region VII | Cebu 7th DEO | Completed | ₱29.7M | 100% | Medium risk50 | —-0.089 |
| 15 | 24H00099LOCAL PROGRAM, NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES, CONSTRUCTION OF MULTI-PURPOSE OFFICE BUILDING, PHASE 2, DPWH REGIONAL OFFICE VII, SOUTH ROAD PROPERTIES, CEBU CITY | Region VII | Region VII | On-Going | ₱24.1M | 44% | Medium risk50 | —-0.031 |
| 16 | 24HD0105SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF FLOOD CONTROL AND DRAINAGE SYSTEM ALONG TAYTAYAN CREEK, TAYTAYAN, CITY OF BOGO, CEBU | Region VII | Cebu 4th DEO | Completed | ₱49M | 100% | Medium risk49 | —-0.078 |
| 17 | 24HO0054ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES, BANKO BANKO BRIDGE (B00461CB) ALONG SANTANDER-BARILI-TOLEDO ROAD | Region VII | Cebu 7th DEO | On-Going | ₱19.3M | 68% | Medium risk48 | —-0.006 |
| 18 | 25HO0058ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, REHABILITATION/ MAJOR REPAIR OF PERMANENT BRIDGES, TUBOD BR. (B00502CB) ALONG SIBONGA-DUMANJUG RD | Region VII | Cebu 7th DEO | On-Going | ₱13.6M | 98% | Medium risk48 | —-0.028 |
| 19 | 24HO0038ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF DRAINAGE SYSTEM ALONG BRGY. BALABAGON, MOALBOAL, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱28.5M | 34% | Medium risk48 | —-0.012 |
| 20 | 25HO0097ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF DRAINAGE SYSTEM, PHASE 3, BARANGAY TUNGA, MOALBOAL, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱14.5M | 9% | Medium risk48 | —-0.013 |
| 21 | 25HO0096ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF DUMANJUG CIS DRAINAGE SYSTEM, DUMANJUG, CEBU (PHASE 2) | Region VII | Cebu 7th DEO | On-Going | ₱14.5M | 85% | Medium risk48 | —-0.036 |
| 22 | 25HO0095ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF DRAINAGE SYSTEM ALONG BRGY. BALABAGON, MOALBOAL, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱24M | 44% | Medium risk48 | —-0.027 |
| 23 | 24HO0028ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF DUMANJUG CIS DRAINAGE SYSTEM, DUMANJUG, CEBU | Region VII | Cebu 7th DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.075 |
| 24 | 25HE0083CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD LEADING TO BUTONG U | Region VII | Cebu 2nd DEO | On-Going | ₱38.4M | 10% | Medium risk47 | —-0.033 |
| 25 | 24HO0124CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF DRAINAGE SYSTEM, PHASE 2, BARANGAY TUNGA, MOALBOAL | Region VII | Cebu 7th DEO | On-Going | ₱29M | 96% | Medium risk47 | —-0.054 |