Contractor dossier
42 projects on file, including joint ventures this contractor is part of.
Total projects
42
Total budget
₱4.6B
Average progress
93.7%
Completion rate
88.1%
Average risk score
49.3
Medium risk on average, out of 100
Flagged as unusual
4
9.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region II | 31 | ₱3.3B | 47.4 | 2 | 96.8% |
| Region IV-A | 7 | ₱126.6M | 45.9 | 0 | 100.0% |
| National Capital Region | 3 | ₱290.2M | 66.5 | 1 | 45.2% |
| Central Office | 1 | ₱945.5M | 77.5 | 1 | 99.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 24 | ₱953.4M | 46.0 | 1 | 95.8% |
| Flood Control and Drainage | 6 | ₱1.2B | 55.2 | 1 | 100.0% |
| Bridges | 6 | ₱2.2B | 52.7 | 1 | 100.0% |
| Buildings and Facilities | 4 | ₱117.9M | 50.0 | 0 | 75.0% |
| OTHER | 1 | ₱96.5M | 68.7 | 1 | 35.6% |
| Water Provision and Storage | 1 | ₱22.1M | 48.8 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 19Z00008CONSTRUCTION OF BANK PROTECTION WORKS ALONG CAGAYAN RIVER AT IGUIG, CAGAYAN AND AGGUNETAN, LASAM, CAGAYAN | Central Office | Flood Control Management Cluster | On-Going | ₱945.5M | 100% | High risk78 | Flagged0.023 |
| 24O00160CONSTRUCTION OF MULTI-PURPOSE BUILDING,EAST AVENUE MEDICAL CENTER, EAST AVENUE, DILIMAN, QUEZON CITY | National Capital Region | National Capital Region | On-Going | ₱96.5M | 36% | High risk69 | Flagged0.015 |
| 19O00065PROPOSED MANILA BAY REHABILITATION PROGRAM (PURCHASE AND INSTALLATION OF 2,500 METERS TRASH BOOM, MA | National Capital Region | National Capital Region | Completed | ₱98.7M | 100% | High risk68 | —-0.013 |
| 18B00075DESIGN AND BUILD FOR THE CONSTRUCTION OF MISSING LINKS / NEW ROADS: MANILA NORTH ROAD (JCT. BANGAG - PARUDDUN SECT.) - JCT. CAGAYAN VALLEY ROAD (CAMALANIUGAN), CAGAYAN PROVINCE | Region II | Region II | On-Going | ₱2.1B | 100% | High risk66 | Flagged0.042 |
| 25O00068CONSTRUCTION OF MULTI-PURPOSE BUILDING, EAST AVENUE MEDICAL CENTER, EAST AVENUE, DILIMAN, QUEZON CITY | National Capital Region | National Capital Region | On-Going | ₱95.1M | 0% | High risk63 | —-0.021 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 18B00075DESIGN AND BUILD FOR THE CONSTRUCTION OF MISSING LINKS / NEW ROADS: MANILA NORTH ROAD (JCT. BANGAG - PARUDDUN SECT.) - JCT. CAGAYAN VALLEY ROAD (CAMALANIUGAN), CAGAYAN PROVINCE | Region II | Region II | On-Going | ₱2.1B | 100% | High risk66 | Flagged0.042 |
| 24BC0113CONCRETING OF LUCBAN-MAQUIRE FMR, BRGY, LUCBAN, ABULUG, CAGAYAN | Region II | Cagayan 2nd DEO | On-Going | ₱14.9M | 0% | Medium risk45 | Flagged0.037 |
| 19Z00008CONSTRUCTION OF BANK PROTECTION WORKS ALONG CAGAYAN RIVER AT IGUIG, CAGAYAN AND AGGUNETAN, LASAM, CAGAYAN | Central Office | Flood Control Management Cluster | On-Going | ₱945.5M | 100% | High risk78 | Flagged0.023 |
| 24O00160CONSTRUCTION OF MULTI-PURPOSE BUILDING,EAST AVENUE MEDICAL CENTER, EAST AVENUE, DILIMAN, QUEZON CITY | National Capital Region | National Capital Region | On-Going | ₱96.5M | 36% | High risk69 | Flagged0.015 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 19Z00008CONSTRUCTION OF BANK PROTECTION WORKS ALONG CAGAYAN RIVER AT IGUIG, CAGAYAN AND AGGUNETAN, LASAM, CAGAYAN | Central Office | Flood Control Management Cluster | On-Going | ₱945.5M | 100% | High risk78 | Flagged0.023 |
| 2 | 24O00160CONSTRUCTION OF MULTI-PURPOSE BUILDING,EAST AVENUE MEDICAL CENTER, EAST AVENUE, DILIMAN, QUEZON CITY | National Capital Region | National Capital Region | On-Going | ₱96.5M | 36% | High risk69 | Flagged0.015 |
| 3 | 19O00065PROPOSED MANILA BAY REHABILITATION PROGRAM (PURCHASE AND INSTALLATION OF 2,500 METERS TRASH BOOM, MA | National Capital Region | National Capital Region | Completed | ₱98.7M | 100% | High risk68 | —-0.013 |
| 4 | 18B00075DESIGN AND BUILD FOR THE CONSTRUCTION OF MISSING LINKS / NEW ROADS: MANILA NORTH ROAD (JCT. BANGAG - PARUDDUN SECT.) - JCT. CAGAYAN VALLEY ROAD (CAMALANIUGAN), CAGAYAN PROVINCE | Region II | Region II | On-Going | ₱2.1B | 100% | High risk66 | Flagged0.042 |
| 5 | 25O00068CONSTRUCTION OF MULTI-PURPOSE BUILDING, EAST AVENUE MEDICAL CENTER, EAST AVENUE, DILIMAN, QUEZON CITY | National Capital Region | National Capital Region | On-Going | ₱95.1M | 0% | High risk63 | —-0.021 |
| 6 | 24BC0158ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- ASSET PRESERVATION- PREVENTIVE MAINTENANCE- TERTIARY ROADS- CAGAYAN- APAYAO- RD (TUAO- RIZAL SECTION) (S00655LZ) - K0544+500-K0550+000 | Region II | Cagayan 2nd DEO | Completed | ₱96.5M | 100% | Medium risk56 | —-0.013 |
| 7 | 24BC0157ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- ASSET PRESERVATION- PREVENTIVE MAINTENANCE- TERTIARY ROADS- CAGAYAN- APAYAO- RD (TUAO- RIZAL SECTION) (S006555LZ) - K0532+(-503)-K0537+000 | Region II | Cagayan 2nd DEO | Completed | ₱96.5M | 100% | Medium risk56 | —-0.012 |
| 8 | 20BC0159CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-CONCRETING OF ROAD, LASAM AND STO. NIÑO, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱96.5M | 100% | Medium risk55 | —-0.065 |
| 9 | 22BC0044CSSP-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - JCT. CENTRO LASAM-STO. NIÑO-PIAT ROAD LEADING TO BASILICA MINORE OF OUR LADY OF PIAT, STO. NIÑO, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱64.5M | 100% | Medium risk54 | —-0.031 |
| 10 | 19DO0036OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - MANILA EAST RD. - K0044+000 - K0044+880, K0048+300 - K0048+855, MORONG AND BARAS RIZAL | Region IV-A | Rizal 2nd DEO | Completed | ₱47.4M | 100% | Medium risk51 | —-0.105 |
| 11 | 24BC0054CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF MULTI-PURPOSE BUILDING, WESTERN CAGAYAN SCHOOL OF ARTS AND TRADES, LASAM, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱4.9M | 100% | Medium risk50 | —-0.083 |
| 12 | 21BC0106LOCAL INFRASTRUCTURE PROGRAM-LOCAL ROADS AND BRIDGES-CONSTRUCTION OF MAPURAO BRIDGE, BARANGAY MAPURAO, ALLACAPAN, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱19.8M | 100% | Medium risk50 | —-0.036 |
| 13 | 20B00021ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT: BRIDGE PROGRAM: REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES: MAGAPIT SUSPENSION BRIDGE (B01113LZ) ALONG JCT. LOGAC-MAGAPIT ROAD, MAGAPIT, LALLO, CAGAYAN | Region II | Region II | Completed | ₱34.2M | 100% | Medium risk49 | —-0.038 |
| 14 | 21BC0114CSSP-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-JCT. CENTRO LASAM-STO. NIÑO-PIAT ROAD LEADING TO BASILICA MINORE OF OUR LADY OF PIAT, STO. NIÑO, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱16.6M | 100% | Medium risk49 | —-0.046 |
| 15 | 19BD0055WATER MANAGEMENT FACILITIES -WATER SUPPLY -CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, CONSTRUCTION / REHABILITATION / IMPROVEMENT OF LEVEL III WATER SUPPLY SYSTEM, IGUIG, CAGAYAN | Region II | Cagayan 3rd DEO | Completed | ₱22.1M | 100% | Medium risk49 | —-0.043 |
| 16 | 21BC0090CSSP-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-MATUCAY-SILAGAN ROAD LEADING TO SILAGAN FALLS AND CAVES, BRGY. SILANGAN, ALLACAPAN, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱14.7M | 100% | Medium risk49 | —-0.042 |
| 17 | 23BC0063OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF CHICO RIVER CONTROL STRUCTURE ALONG CHICO RIVER, ST | Region II | Cagayan 2nd DEO | Completed | ₱48.2M | 100% | Medium risk47 | —-0.065 |
| 18 | 20DO0069LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM-FLOOD CONTROL AND DRAINAGE-FLOOD CONTROL STRUCTURES/FACILITIES- RIPRAPPING/SLOPE PROTECTION OD SITIO SAN ROQUE ROAD, BRGY. PINUGAY BARAS, RIZAL | Region IV-A | Rizal 2nd DEO | Completed | ₱9.7M | 100% | Medium risk47 | —-0.090 |
| 19 | 20BC0014CONSTRUCTION OF MISSING LINKS/NEW ROADS, CAGAYAN-APAYAO-CONNER ROAD, RIZAL, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱48.5M | 100% | Medium risk46 | —-0.073 |
| 20 | 22BB0024OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS- CONST. /REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONST. OF FLOOD MITIGATION STUCTURE-CONSTRUCTION OF SEAWALL CENTRO NORTE, BUGUEY, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱47.5M | 100% | Medium risk46 | —-0.062 |
| 21 | 21DO0003ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - PILILLA JCT. JALAJALA RD - K0065+000 - K0065+882 PILILLA RIZAL | Region IV-A | Rizal 2nd DEO | Completed | ₱14.7M | 100% | Medium risk46 | —-0.108 |
| 22 | 22BC0008OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-PRIMARY ROADS-MANILA NORTH RD - K0590+(-604)-K0590+(-544), K0590+400-K0590+450, STA. PRAXEDES, | Region II | Cagayan 2nd DEO | Completed | ₱71.1M | 100% | Medium risk46 | —-0.068 |
| 23 | 22BC0025OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF DUGO FLOOD CONTROL ALONG ABULUG RIVER (STA. 10+310-STA. 10+600 L/S), ABULUG, C | Region II | Cagayan 2nd DEO | Completed | ₱49M | 100% | Medium risk46 | —-0.061 |
| 24 | 19DO0009LOCAL PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS - LOCAL INFRASTRUCTURE PROGRAM - CONCRETING OF ROADS (BAYANI FERRERA ROAD, BRGY. SAN JUAN AND SAN JOSE) BARAS, RIZAL | Region IV-A | Rizal 2nd DEO | Completed | ₱7.1M | 100% | Medium risk46 | —-0.105 |
| 25 | 20BC0128ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) TERTIARY ROADS-JCT. LOGAC-LASAM-GAGABUTAN ROAD (S00656LZ)-CHAINAGE 15419-CHAINAGE 15809, CHAINAGE 15872-CHA | Region II | Cagayan 2nd DEO | Completed | ₱38.2M | 100% | Medium risk45 | —-0.079 |