Contractor dossier
30 projects on file, including joint ventures this contractor is part of.
Total projects
30
Total budget
₱129.3M
Average progress
99.5%
Completion rate
93.3%
Average risk score
21.0
Low risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region X | 30 | ₱129.3M | 21.0 | 0 | 99.5% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 15 | ₱51.8M | 13.7 | 0 | 100.0% |
| Roads | 13 | ₱73M | 30.1 | 0 | 98.9% |
| Water Provision and Storage | 1 | ₱2.6M | 16.1 | 0 | 100.0% |
| Flood Control and Drainage | 1 | ₱1.9M | 14.8 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 17KF0032CONCRETING OF ROAD AT BULOD, TUBOD, LANAO DEL NORTE, SECTION A KO+000+500, SECTION B- KO+000-KO+240.00 | Region X | Lanao del Norte 1st DEO | Completed | ₱9.4M | 100% | Medium risk46 | —-0.067 |
| 2 | 17KF0033CONCRETING OF ROAD AT MALINGAO, TUBOD, LANAO DEL NORTE, SECTION A KO 0+000-KO 0+641.00, SECTION B KO 0+000-KO 0+193.10 | Region X | Lanao del Norte 1st DEO | Completed | ₱9.4M | 100% | Medium risk45 | —-0.067 |
| 3 | 25KM0030IMPROVEMENT OF ROAD FROM BRGY. BURU-UN TO BRGY. DITUCALAN, ILIGAN CITY, LANAO DEL NORTE | Region X | Iligan City DEO | On-Going | ₱4.8M | 85% | Medium risk44 | —-0.056 |
| 4 | 23KM0017IMPROVEMENT OF ROAD, BARANGAY MARIA CRISTINA, ILIGAN CITY, LANAO DEL NORTE | Region X | Iligan City DEO | Completed | ₱5M | 100% | Medium risk43 | —-0.094 |
| 5 | 19KB0104CONSTRUCTION OF MULTI-PURPOSE BUILDING (TRIBAL HALL & TRAINING CENTER), SINUDA, KITAOTAO, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱5M | 100% | Medium risk42 | —-0.091 |
| 6 | 18K00329CONCRETING OF BRGY. POBLACION BAYABAO FMR, BRGY. POBLACION BAYABAO, BUTIG, LANAO DEL SUR | Region X | Region X | Completed | ₱9.1M | 100% | Medium risk41 | —-0.042 |
| 7 | 18KF0117CONCRETING OF BRGY. ESPERANZA-BRGY. BABALAYA FARM-TO-MARKET ROAD, BRGY. ESPERANZA, BACOLOD, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | Completed | ₱10.4M | 100% | Medium risk39 | —-0.043 |
| 8 | 23KM0078CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. STO. ROSARIO, CITY OF ILIGAN | Region X | Iligan City DEO | Completed | ₱4.8M | 100% | Medium risk38 | —-0.051 |
| 9 | 17KF0150CONSTRUCTION OF BRGY. BARA-ASON TO BRGY. TINGINTINGIN FMR, BRGY. BARA-ASON AND BRGY. TINGINTINGIN, KAUSWAGAN, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | Completed | ₱10.4M | 100% | Medium risk38 | —-0.015 |
| 10 | 17KF0157CONSTRUCTION OF 2-STOREY WORKSHOP BUILDING (7X18) AT DALIPUGA NATIONAL HIGH SCHOOL-HINDANG NATIONAL HIGH SCHOOL ANNEX, ILIGAN CITY | Region X | Lanao del Norte 1st DEO | Completed | ₱8.5M | 100% | Low risk19 | —-0.029 |
| 11 | 23KM0076CONSTRUCTION/REHABILITATION OF PEDESTRIAN OVERPASS, BRGY. STO. ROSARIO, CITY OF ILIGAN | Region X | Iligan City DEO | Completed | ₱2.9M | 100% | Low risk18 | —-0.044 |
| 12 | 24KM0003REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS ALONG ILIGAN CITY DIVERSION RD - (S01383MN) CHAINAGE 619 - CHAINAGE 674, CHAINAGE 914 - CHAINAGE 972 | Region X | Iligan City DEO | Completed | ₱3.1M | 100% | Low risk16 | —-0.094 |
| 13 | 25KM0045CONSTRUCTION OF RAINWATER COLLECTORS SYSTEM (RCWS), ILIGAN CITYA. DIGKILAAN NATIONAL HIGH SCHOOLB. BONBONON ELEMENTARY SCHOOLC. KIWALAN ELEMENTARY SCHOOLD. HINAPLANON NATIONAL HIGH SCHOOLE. STA. FILOMENA CENTRAL SCHOOL | Region X | Iligan City DEO | On-Going | ₱2.6M | 100% | Low risk16 | —-0.034 |
| 14 | 22KI0066CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING BRGY. SOLINOG, CALAMBA, MISAMIS OCCIDENTAL | Region X | Misamis Occidental 1st DEO | Completed | ₱3M | 100% | Low risk16 | —-0.096 |
| 15 | 19KF0005CONCRETING OF ROAD, ZONE PLUTO 1, BRGY. SUAREZ, ILIGAN CITY, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | Completed | ₱2.2M | 100% | Low risk16 | —-0.090 |
| 16 | 18KF0010CONSTRUCTION OF ROAD, BRGY. SUAREZ, ILIGAN CITY | Region X | Lanao del Norte 1st DEO | Completed | ₱2.1M | 100% | Low risk16 | —-0.090 |
| 17 | 19KF0010CONCRETING OF ROAD, PUROK SAN MIGUEL, BRGY. TUBOD, ILIGAN CITY, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | Completed | ₱2.4M | 100% | Low risk16 | —-0.091 |
| 18 | 24KM0004PAVING OF UNPAVED ROADS ALONG LANAO DEL NORTE INTERIOR CIRCUM. RD. K1533+398-K1533+443 | Region X | Iligan City DEO | Completed | ₱1.9M | 100% | Low risk16 | —-0.092 |
| 19 | 18KF0017REHABILITATION/IMPROVEMENT OF DRAINAGE AT IGLESIA NI CRISTO, BRGY. TIBANGA, ILIGAN CITY | Region X | Lanao del Norte 1st DEO | Completed | ₱1.9M | 100% | Low risk15 | —-0.078 |
| 20 | 21KF0069CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY MUNTAY, KOLAMBUGAN, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | Completed | ₱3.5M | 100% | Low risk11 | —-0.096 |
| 21 | 21KF0070CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY AUSTIN HEIGHTS, KOLAMBUGAN, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | Completed | ₱3.5M | 100% | Low risk11 | —-0.096 |
| 22 | 23KM0019CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BUHANGINAN HILL, PALA-O, ILIGAN CITY, LANAO DEL NORTE | Region X | Iligan City DEO | Completed | ₱3M | 100% | Low risk11 | —-0.096 |
| 23 | 19K00448CONSTRUCTION OF ONE-STOREY 3 CLASSROOM SCHOOL BUILDING, MAUYAG-MEMORIAL ELEMENTARY SCHOOL, MALABANG, LANAO DEL SUR | Region X | Region X | Completed | ₱4.4M | 100% | Low risk11 | —-0.047 |
| 24 | 19KF0068IMPROVEMENT OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, ILIGAN CITY | Region X | Lanao del Norte 1st DEO | Completed | ₱1.9M | 100% | Low risk10 | —-0.097 |
| 25 | 19K00367CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. DOLANGAN, BUTIG, LANAO DEL SUR | Region X | Region X | Completed | ₱1.4M | 100% | Low risk9 | —-0.095 |