Opening the dossier…
Opening the dossier…
Contractor dossier
29 projects on file, including joint ventures this contractor is part of.
Total projects
29
Total budget
₱205.2M
Average progress
97.8%
Completion rate
89.7%
Average risk score
34.1
Medium risk on average, out of 100
Flagged as unusual
1
3.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 29 | ₱205.2M | 34.1 | 1 | 97.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 14 | ₱72.3M | 26.5 | 0 | 100.0% |
| Roads | 12 | ₱101.7M | 33.0 | 0 | 96.1% |
| GAA 2025 SSP | 1 | ₱4.9M | 93.4 | 1 | 93.8% |
| GAA 2025 OO-1 | 1 | ₱16.5M | 91.3 | 0 | 90.9% |
| Flood Control and Drainage | 1 | ₱9.9M | 37.7 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EI0109CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BALUGO NATIONAL HIGH SCHOOL, BARANGAY BALUGO, MANSALAY, ORIENTAL MINDORO, PHASE II | Region IV-B | Southern Mindoro DEO | On-Going | ₱4.9M | 94% | High risk93 | Flagged0.010 |
| 25EI0007ROAD WIDENING - SECONDARY ROADS - CALAPAN SOUTH ROAD - K0137+798.00 - K0138+131.00, ROXAS, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | On-Going | ₱16.5M | 91% | High risk91 | —-0.006 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EI0109CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BALUGO NATIONAL HIGH SCHOOL, BARANGAY BALUGO, MANSALAY, ORIENTAL MINDORO, PHASE II | Region IV-B | Southern Mindoro DEO | On-Going | ₱4.9M | 94% | High risk93 | Flagged0.010 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 21EI0177CONSTRUCTION OF MULTI - PURPOSE BUILDING AT BARANGAY ALCADESMA, BANSUD, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱3.8M | 100% | Low risk21 | —-0.086 |
| 27 | 24EI0091CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY SAN RAFAEL, ROXAS, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱2.9M | 100% | Low risk20 | —-0.086 |
| 28 | 21EI0086CONSTRUCTION OF ROAD AT BARANGAY MALITBOG, BONGABONG, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱1M | 100% | Low risk16 | —-0.087 |
| 29 | 18EI0155COMPLETION OF SCHOOL BUILDING (2 STY 4 CL) @ CARMUNDO NHS, BONGABONG, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱2.9M | 100% | Low risk14 | —-0.046 |