56 projects on file, including joint ventures this contractor is part of.
Total projects
56
Total budget
₱544.2M
Average progress
97.4%
Completion rate
92.9%
Average risk score
42.7
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 56 | ₱544.2M | 42.7 | 0 | 97.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 37 | ₱338.4M | 40.7 | 0 | 100.0% |
| Buildings and Facilities | 8 | ₱74.6M | 38.9 | 0 | 93.6% |
| Water Provision and Storage | 4 | ₱70.5M | 45.5 | 0 | 75.8% |
| OTHER | 3 | ₱37.6M | 61.4 | 0 | 100.0% |
| Flood Control and Drainage | 3 | ₱19.2M | 45.1 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱4M | 70.8 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HA0097REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - TAGBILARAN CITY-CORELLA-SIKATUNA-LOBOC RD - K0012+379.5-K0012+420, K0017+637-K0017+754 | Region VII | Bohol 1st DEO | On-Going | ₱4M | 100% | High risk71 | —-0.003 |
| 19HB0110CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TRADES, INDUSTRIES, AND ECONOMIC ZONES, HINAWANAN (LOAY)-CONCEPTION-JCT. (SIKATUNA-LOBOC) ROAD IN SUPPORT OF THE FURNITURE AND GARMENTS INDUSTRY, LOAY, BO | Region VII | Bohol 3rd DEO | Completed | ₱9.5M | 100% | High risk62 | —-0.029 |
| 19HB0108CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, POBLACION ONDOL, TAYTAY, CAMBANCE ROAD LEADING TO CRUZ DAKO, BRGY. POBLACION ONDOL, LOBOC, BOHOL (MOUNTANEOUS AREA). SECTION 1: | Region VII | Bohol 3rd DEO | Completed | ₱18.3M | 100% | High risk62 | —-0.029 |
| 23HB0115CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS WATER SUPPLY SYSTEM CONSTRUCTION OF SOLAR WATER SYSTEM, MUNICIPALITY OF GARCIA HERNANDEZ, BOHOL | Region VII | Bohol 3rd DEO | Completed | ₱9.8M | 100% | High risk61 | —-0.030 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25HA0097REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - TAGBILARAN CITY-CORELLA-SIKATUNA-LOBOC RD - K0012+379.5-K0012+420, K0017+637-K0017+754 | Region VII | Bohol 1st DEO | On-Going | ₱4M | 100% | High risk71 | —-0.003 |
| 2 | 19HB0110CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TRADES, INDUSTRIES, AND ECONOMIC ZONES, HINAWANAN (LOAY)-CONCEPTION-JCT. (SIKATUNA-LOBOC) ROAD IN SUPPORT OF THE FURNITURE AND GARMENTS INDUSTRY, LOAY, BO | Region VII | Bohol 3rd DEO | Completed | ₱9.5M | 100% | High risk62 | —-0.029 |
| 3 | 19HB0108CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, POBLACION ONDOL, TAYTAY, CAMBANCE ROAD LEADING TO CRUZ DAKO, BRGY. POBLACION ONDOL, LOBOC, BOHOL (MOUNTANEOUS AREA). SECTION 1: | Region VII | Bohol 3rd DEO | Completed | ₱18.3M | 100% | High risk62 | —-0.029 |
| 4 | 23HB0115CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS WATER SUPPLY SYSTEM CONSTRUCTION OF SOLAR WATER SYSTEM, MUNICIPALITY OF GARCIA HERNANDEZ, BOHOL | Region VII | Bohol 3rd DEO | Completed | ₱9.8M | 100% | High risk61 | —-0.030 |
| 5 | 17HA0013MFO 1-NATIONAL ROAD NETWORK SERVICE-ASSET PRESERVATION OF NATIONAL ROADS-INCLUDING DRAINAGE BASED (T | Region VII | Bohol 1st DEO | Completed | ₱28.9M | 100% | Medium risk57 | —-0.063 |
| 6 | 17HA0052CONSTRUCTION OF MULTI-PURPOSE BUILDING, (COOPERATIVE TRAINING/EVACUATION CENTER), TEACHER'S VILLAGE, SAN ISIDRO, TAGBILARAN CITY, BOHOL, PROJECT ID: P00144502VS. | Region VII | Bohol 1st DEO | Completed | ₱9.5M | 100% | Medium risk56 | —-0.065 |
| 7 | 16HA0024CLUSTER C (CONSTRUCTION OF MULTI-PURPOSE BUILDING AND COMPLETION OF PUBLIC MARKET) CONSTRUCTION OF M | Region VII | Bohol 1st DEO | Completed | ₱11.5M | 100% | Medium risk55 | —-0.065 |
| 8 | 17HA0025MFO 1-NATIONAL ROAD NETWORK SERVICE-ASSET PRESERVATION OF NATIONAL ROADS-RAHABILITATION/CONSTRUCTION | Region VII | Bohol 1st DEO | Completed | ₱11.8M | 100% | Medium risk55 | —-0.063 |
| 9 | 21HA0166REHABILITATION OF MULTI-PURPOSE BUILDING (OLD CORTES MUNICIPAL PUBLIC MARKET), CORTES, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱19.8M | 100% | Medium risk48 | —-0.085 |
| 10 | 19HA0043CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINANGE SYSTEMS - CONSTRUCTION OF BOX CULVERT AT POBLACION, CATIGBIAN ALONG JCT. (TNR) CBCMR K0035+887, CATIGBIAN, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱4.8M | 100% | Medium risk47 | —-0.076 |
| 11 | 23HA0091CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BRGY. POBLACION, CORELLA, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱11.3M | 49% | Medium risk47 | —-0.025 |
| 12 | 18HA0018CONSTRUCTION (COMPLETION) OF DPWH BUILDING BOHOL 1ST DISTRICT ENGINEERING OFFICE BUILDING INCLUDING SITE DEVELOPMENT, DAO, TAGBILARAN CITY, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱6.8M | 100% | Medium risk46 | —-0.094 |
| 13 | 24HA0095CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM - CONSTRUCTION OF WATER SUPPLY SYSTEM (LEVEL III), SIKATUNA, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱24.4M | 100% | Medium risk46 | —-0.058 |
| 14 | 22HA0094CONSTRUCTION OF JCT. SIKATUNA-BALILIHAN ROAD-BADIANG-CAMBUAC NORTE LEADING TO CAWASAN FALLS AND LAHUG CAVE, SIKATUNA, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱34.3M | 100% | Medium risk46 | —-0.093 |
| 15 | 25HA0026REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - TAGBILARAN CITY-CORELLA-SIKATUNA-LOBOC RD - K0009 + 000 - K0009 + 486 | Region VII | Bohol 1st DEO | On-Going | ₱15.3M | 100% | Medium risk46 | —-0.063 |
| 16 | 23HA0073CONCRETING OF ROAD, FERMIN TORRALBA STREET EXTENSION, BRGY. COGON, TAGBILARAN, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱14.9M | 100% | Medium risk46 | —-0.096 |
| 17 | 19HA0042CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF BOX CULVERT AT CANDUMAYAO, CATIGBIAN ALONG JCT. (TNR) CBCMR K0036+212 AND AT K0036+700, CATIGBIAN, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱9.7M | 100% | Medium risk46 | —-0.077 |
| 18 | 21HA0019CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - M. CAPAYAS STREET CONNECTING RAMON ENERIO ST. TO CPG EAST AVENUE IN SUPPORT TO THE GIFTS AND HOUSEWARES AND AGRIBUSINESS INDUSTRIES, TAGBILARAN CITY, BOHOL, PACKAG | Region VII | Bohol 1st DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.092 |
| 19 | 22HB0103CONVERGENCE AND SPECIAL SUPPORT PROGRAM -CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM - WATER SUPPLY SYSTEM - CONSTRUCTION OF LEVEL III WATER SUPPLY SYSTEM, LOAY, BOHOL | Region VII | Bohol 3rd DEO | Completed | ₱26.6M | 100% | Medium risk46 | —-0.049 |
| 20 | 24HB0032CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - HINAWANAN (LOAY)-CONCEPTION - JCT. ( | Region VII | Bohol 3rd DEO | Completed | ₱14.6M | 100% | Medium risk46 | —-0.095 |
| 21 | 18HA0014REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS TERTIARY ROADS-TAGBILARAN CITY-CORELLA-SIKATUNA-LOBOC ROAD K0015+280-K0016+130, SIKATUNA, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱20.7M | 100% | Medium risk46 | —-0.095 |
| 22 | 21HA0001CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - UBUJAN - MANGA COASTAL ROAD IN SUPPORT TO AGRIBUSINESS INDUSTRY, TAGBILARAN CITY, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱4.8M | 100% | Medium risk46 | —-0.092 |
| 23 | 20HA0006OFF-CARRIAGEWAY IMPROVEMENT - TAGBILARAN NORTH ROAD (TAGBILARAN - JETAFE SECT.) - K0034+000 - K0034+601 | Region VII | Bohol 1st DEO | Completed | ₱13.7M | 100% | Medium risk46 | —-0.097 |
| 24 | 19HA0004CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - JCT. DPR LOURDES-LIBAONG ROAD LEADING TO AMARELA, LIBAONG BEACH AND PANGLAO WHITE BEACH, PANGLAO, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱9.4M | 100% | Medium risk46 | —-0.095 |
| 25 | 19HA0047CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATION - LOURDES-LIBAONG ROAD LEADING TO VARIOUS RESORTS AND TOURISM ESTABLISHMENT, PANGLAO, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱9.5M | 100% | Medium risk46 | —-0.095 |