109 projects on file, including joint ventures this contractor is part of.
Total projects
109
Total budget
₱6B
Average progress
96.4%
Completion rate
88.1%
Average risk score
50.4
Medium risk on average, out of 100
Flagged as unusual
1
0.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region X | 108 | ₱5.8B | 50.1 | 0 | 96.8% |
| Central Office | 1 | ₱215M | 83.0 | 1 | 59.5% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 62 | ₱3.4B | 48.5 | 0 | 98.1% |
| Flood Control and Drainage | 21 | ₱1.3B | 49.9 | 0 | 98.2% |
| Bridges | 20 | ₱807M | 48.9 | 0 | 91.2% |
| OTHER | 3 | ₱338.3M | 76.3 | 1 | 86.5% |
| GAA 2025 SSP | 1 | ₱55.5M | 95.1 | 0 | 100.0% |
| GAA 2025 OO-2 | 1 | ₱85.8M | 90.6 | 0 | 82.7% |
| Buildings and Facilities | 1 | ₱49.2M | 46.3 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25K00338PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY( MALABANG-DOBLESTON-TUKURAN RD) - K1981 + 986 - K1983 + 853 | Region X | Region X | On-Going | ₱55.5M | 100% | High risk95 | —-0.004 |
| 25KF0047FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTIONOF DIKES ALONG BARANGAY PILI, SAPAD, (TRIBUTARY TO MARANDING RIVER), LANAO DEL NORTE | Region X | Lanao del Norte 2nd DEO | On-Going | ₱85.8M | 83% | High risk91 | —-0.015 |
| 21Z00018CONTRACT PACKAGE 4A - CONSTRUCTION OF ROROGAGUS BRIDGE, RECONSTRUCTION AND DEVELOPMENT PLAN FOR A GREATER MARAWI - STAGE 2 UNDER ADB LOAN NO. 3769 - PHI: EMERGENCY ASSISTANCE FOR RECONSTRUCTION AND RECOVERY OF MARAWI (EARRM) | Central Office | Roads Management Cluster II (Multilateral) | On-Going | ₱215M | 60% | High risk83 | Flagged0.013 |
| 23K00042REHAB./RECONST. OF ROADS SLIPS,SLOPE COLLAPSE, AND LANDSLIDE-SECONDARY ROADS, MASIU-GANASSI ROAD - (S01653MN) CHAINAGE 850 - CHAINAGE 1765 | Region X | Region X | Completed | ₱85.8M | 100% | High risk74 | —-0.030 |
| 23K00043REHAB./RECONST. OF ROADS SLIPS,SLOPE COLLAPSE, AND LANDSLIDE-SECONDARY ROADS, MASIU-GANASSI ROAD - (S01653MN) CHAINAGE 200 - CHAINAGE 606 | Region X | Region X | Completed | ₱37.6M | 100% | High risk71 | —-0.040 |
| 17K00147CONST./MAINT. OF FLOOD MITIGATION STRUCT. & DRAINAGE, CONST.OF REVETMENT/RIVER CONTROL ON STEEL SHT | Region X | Region X | Completed | ₱133.6M | 100% | High risk67 | —-0.036 |
| 24K00055CONST. OF FLOOD CONTROL STRUCTURE ALONG MARANDING RIVER, INCL. ROW, PACKAGE 5, LANAO DEL NORTE | Region X | Region X | On-Going | ₱157.7M | 100% | High risk65 | —-0.021 |
| 19K00048CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF BALO-I PLAINS FLOOD CONTROL PROJECT (PACKAGE 1), LANAO DEL NORTE | Region X | Region X | Completed | ₱125.3M | 100% | High risk61 | —-0.057 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 21Z00018CONTRACT PACKAGE 4A - CONSTRUCTION OF ROROGAGUS BRIDGE, RECONSTRUCTION AND DEVELOPMENT PLAN FOR A GREATER MARAWI - STAGE 2 UNDER ADB LOAN NO. 3769 - PHI: EMERGENCY ASSISTANCE FOR RECONSTRUCTION AND RECOVERY OF MARAWI (EARRM) | Central Office | Roads Management Cluster II (Multilateral) | On-Going | ₱215M | 60% | High risk83 | Flagged0.013 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 18KG0020FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SALVADOR FLOOD CONTROL PROJECT IN CABUYAO RIVER, STA. 0+000-STA. 0+305, SALVADOR, LANAO DEL NORTE. | Region X | Lanao del Norte 2nd DEO | Completed | ₱46.5M | 100% | Medium risk46 | —-0.081 |
| 77 | 23KM0013RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGE AT TOMINOBO BR. (B00884MN) ALONG MISAMIS ORIENTAL - MA CRISTINA BDRY RD | Region X | Iligan City DEO | Completed | ₱14.7M | 100% | Medium risk46 | —-0.064 |
| 78 | 18KF0088RETROFITTING/STRENGHTHENING OF PERMANENT BRIDGES TITUNOD BRIDGE 2 (B00956MN) ALONG LINAMON-ZAMBOANGA ROAD, KOLAMBUGAN, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | Completed | ₱16.8M | 100% | Medium risk46 | —-0.062 |
| 79 | 21K00114REHAB/RECONST/UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS,MARAWI-MASIU RD-K1590+722-K1592+433.2 | Region X | Region X | Completed | ₱41.9M | 100% | Medium risk46 | —-0.093 |
| 80 | 25KF0075SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD FROM BRGY. SITIO DAO-BRGY. MALINAS, KAPATAGAN, LANAO DEL NORTE | Region X | Lanao del Norte 2nd DEO | On-Going | ₱43.4M | 70% | Medium risk46 | —-0.050 |
| 81 | 18KG0040FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS,CONSTRUCTION OF REVETMENT/RIVER CONTROL ON SHEET PILE ALONG MALABANG-DOBLESTON-TUKURAN ROAD,KAROMATAN BRIDGE,BARANGAY POBLACION,SND,LANAO DEL NORTE | Region X | Lanao del Norte 2nd DEO | Completed | ₱27.9M | 100% | Medium risk46 | —-0.081 |
| 82 | 20KG0020NETWORK DEVELOPMENT:OFF-CARRIAGEWAY IMPROVEMENT-TERTIARY ROADS DOBLESTON-BUTADON ROAD-S00928MN,SND,LANAO DEL NORTE | Region X | Lanao del Norte 2nd DEO | Completed | ₱37M | 100% | Medium risk46 | —-0.092 |
| 83 | 19KG0036ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS: DOBLESTON-BUTADON ROAD - S00928MN, SND, LANAO DEL NORTE | Region X | Lanao del Norte 2nd DEO | Completed | ₱43.8M | 100% | Medium risk46 | —-0.092 |
| 84 | 21KG0057ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES - TERTIARY ROADS, LANAO DEL NORTE INTERIOR CIRCUMFERENTIAL ROAD, (LDNICR) - (S00970MN) CHAINAGE 26016-CHAINAGE 26366, TANGKAL, LANAO DEL NORTE | Region X | Lanao del Norte 2nd DEO | Completed | ₱34.3M | 100% | Medium risk46 | —-0.086 |
| 85 | 23KF0008NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS,LINAMON-ZAMBOANGA ROAD,K1617+012-K1618+210,KAPATAGAN,LANAO DEL NORTE | Region X | Lanao del Norte 2nd DEO | Completed | ₱39.9M | 100% | Medium risk45 | —-0.092 |
| 86 | 24K00137ASSET PRESERVATION- REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-PRIMARY ROADS, MARAWI-MALABANG ROAD-K1595+378-K1595+1242 | Region X | Region X | On-Going | ₱38M | 100% | Medium risk45 | —-0.054 |
| 87 | 19K00257REHABILITATION/IMPROVEMENT OF MARAWI-MALABANG COTABATO ROAD INCL. DRAINAGE ALONG LAKE LANAO CIRCUMFERENTIAL ROAD (MADALUM-MADAMBA SECTION) | Region X | Region X | Completed | ₱45.8M | 100% | Medium risk45 | —-0.093 |
| 88 | 19K00324IMPROVEMENT/WIDENING OF MARAWI-MALABANG ROAD INCLUDING DRAINAGE ALONG LAKE LANAO CIRCUMFERENTIAL ROAD (BALINDONG-TUGAYA-BACOLOD-KALAWI SECTION) | Region X | Region X | Completed | ₱37.3M | 100% | Medium risk45 | —-0.093 |
| 89 | 18KG0002NETWORK DEVELOPMNET - PAVING OF UNPAVED ROADS ALONG TERTIARY ROADS: (LDNICR) MAGSAYSAY-TUBOD ROAD - S0094MN, K1583+742-K1584+845, MAGSAYSAY, LANAO DEL NORTE. | Region X | Lanao del Norte 2nd DEO | Completed | ₱35.8M | 100% | Medium risk45 | —-0.094 |
| 90 | 23KF0026SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF MARANDING RIVER IRRIGATION SYSTEM, MAIN CANAL SERVICE ROAD,LALA, LDN | Region X | Lanao del Norte 2nd DEO | Completed | ₱26.4M | 100% | Medium risk45 | —-0.093 |
| 91 | 18KF0020CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO TRADE, INDUSTRIES AND ECON. ZONES, MAGOONG-BOSQUE ROAD TO MIRAIC IN SUPPORT OF AGRIBUSINESS, PROCESSED FRUITS AND NUTS, LINAMON, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | Completed | ₱14.6M | 100% | Medium risk45 | —-0.094 |
| 92 | 24KG0020CONSTRUCTION OF ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES ACCESS ROAD LEADING TO KALILANGAN COLD SPRING, BRGY. PINPIN TO BRGY. KALILANGAN, TUBOD, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | Completed | ₱24.5M | 100% | Medium risk45 | —-0.093 |
| 93 | 18KF0021CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATION, ACCESS ROADS LEADING TO DAPIT ALIM, TUBOD, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | Completed | ₱19.1M | 100% | Medium risk45 | —-0.094 |
| 94 | 24KM0022CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG LDNICR, ILIGAN CITY | Region X | Iligan City DEO | Completed | ₱29.4M | 100% | Medium risk45 | —-0.081 |
| 95 | 19KF0054CONSTRUCTION OF FLOOD CONTROL ALONG RIVER BANK OF ILIGAN CITY AT ZONE 4, SITIO ISLA VERDE TO ZONE 5, MALINDAWAG, BRGY. ABUNO, ILIGAN CITY | Region X | Lanao del Norte 1st DEO | Completed | ₱41.6M | 100% | Medium risk45 | —-0.082 |
| 96 | 22KF0011CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG ILIGAN RIVER, BARANGAY TUBOD, ILIGAN CITY, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | Completed | ₱37.2M | 100% | Medium risk45 | —-0.082 |
| 97 | 22K00033REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS, MARAWI-MALABANG ROAD - (S01652MN) CHAINAGE 20981 - CHAINAGE 21731 | Region X | Region X | Completed | ₱18.7M | 100% | Medium risk44 | —-0.094 |
| 98 | 19KF0071REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG STA. FELOMINA-BONBONON-DIGKILAAN-ROGONGON ROAD, K1521+1015-K1522+350, ILIGAN CITY | Region X | Lanao del Norte 1st DEO | Completed | ₱18.8M | 100% | Medium risk44 | —-0.088 |
| 99 | 18KF0049CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ILIGAN RIVER (UPSTREAM) INCLUDING ROW AT BRGY. MAHAYAHAY, ILIGAN CITY | Region X | Lanao del Norte 1st DEO | Completed | ₱26.2M | 100% | Medium risk44 | —-0.082 |
| 100 | 21K00111REHAB/RECONST/UPGRDNG OF DAMAGED PAVED ROADS-PRIMARY ROADS, MARAWI-MALABANG RD-K1604+446-K1604+990.9 | Region X | Region X | Completed | ₱14M | 100% | Medium risk44 | —-0.094 |