25 projects on file, including joint ventures this contractor is part of.
Total projects
25
Total budget
₱188M
Average progress
97.5%
Completion rate
80.0%
Average risk score
32.6
Medium risk on average, out of 100
Flagged as unusual
1
4.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region X | 25 | ₱188M | 32.6 | 1 | 97.5% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 18 | ₱117.4M | 25.1 | 0 | 99.3% |
| Roads | 5 | ₱31.6M | 44.4 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱29.3M | 95.0 | 1 | 50.0% |
| Flood Control and Drainage | 1 | ₱9.8M | 44.6 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25KA0086CONSTRUCTION OF CLASSROOM BUILDING CONSTRUCTION AT BARANGAY 9 ELEMENTARY SCHOOL,BARANGAY 9, MALAYBALAY CITY, BUKIDNON BARANGAY 9, MALAYBALAY CITY, BUKIDNON | Region X | Bukidnon 1st DEO | On-Going | ₱29.3M | 50% | High risk95 | Flagged0.013 |
| 2 | 25KN0005CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CANITUAN, KALILANGAN, BUKIDNON | Region X | Bukidnon 4th DEO | On-Going | ₱12.9M | 88% | Medium risk45 | —-0.054 |
| 3 | 24K00370CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PAMOTOLON, KALILANGAN, BUKIDNON | Region X | Region X | On-Going | ₱12.8M | 100% | Medium risk45 | —-0.057 |
| 4 | 24KA0033CONSTRUCTION OF MANUPALI RIS DRAINAGE SYSTEM, LANTAPAN, BUKIDNON, LANTAPAN, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | Completed | ₱9.8M | 100% | Medium risk45 | —-0.077 |
| 5 | 23KA0048REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG KAPALONG-TALAINGOD-VALENCIA (BUKIDNON) RD K1571 + 202 - K1571 + 243, SAN FERNANDO, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱8M | 100% | Medium risk45 | —-0.092 |
| 6 | 22KA0001CONSTRUCTION OF ROAD, BARANGAY APO MACOTE, MALAYBALAY CITY, BUKIDNONBRGY. APO MACOTE, MALAYBALAY CITY, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | Completed | ₱4.9M | 100% | Medium risk44 | —-0.091 |
| 7 | 23KA0031REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG JCT. SH-IMPALAMBONG-OLD CASISANG RD K1507+(-1317) - K1507+(-1054), MALAYBALAY CITY, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | Completed | ₱8.7M | 100% | Medium risk44 | —-0.094 |
| 8 | 24KA0011CONSTRUCTION OF ROAD, BARANGAY VICTORY, LANTAPAN, BUKIDNON, BRGY. VICTORY, LANTAPAN, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | Completed | ₱5M | 100% | Medium risk44 | —-0.092 |
| 9 | 21KA0013CONCRETING OF ROAD, BARANGAY ZAMBOANGUITA, MALAYBALAY CITY, BUKIDNONBRGY. ZAMBOANGUITA, MALAYBALAY CITY, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | Completed | ₱4.9M | 100% | Medium risk44 | —-0.092 |
| 10 | 20KA0090CONSTRUCTION OF MULTI-PURPOSE BUILDING - CONSTRUCTION OF STAFF OFFICERS' QUARTERS (SOQ) INSIDE THE 403RD INFANTRY (PEACEMAKER) BRIGADE, 4ID, PA, CAMP OSITO D. BAHIAN, MALAYBALAY CITY, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱14.7M | 100% | Medium risk44 | —-0.093 |
| 11 | 24K00443CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LUMBO, VALENCIA CITY, BUKIDNON | Region X | Region X | On-Going | ₱4.9M | 100% | Medium risk43 | —-0.056 |
| 12 | 23KA0121CONSTRUCTION OF MULTI-PURPOSE BUILDING,BRGY. BATANGAN, VALENCIA CITY, BUKIDNON BRGY. BATANGAN, VALENCIA CITY, BUKIDNON 4TH LD | Region X | Bukidnon 1st DEO | Completed | ₱9.9M | 100% | Medium risk43 | —-0.095 |
| 13 | 21KA0063CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. MT.NEBO, VALENCIA CITY, BUKIDNONBRGY. MT. NEBO, VALENCIA CITY, BUKIDNON 4TH LD | Region X | Bukidnon 1st DEO | Completed | ₱9.6M | 100% | Medium risk42 | —-0.095 |
| 14 | 22KA0005CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LALIGAN, VALENCIA CITY, BUKIDNON LALIGAN CENTRAL SCHOOL (SCHOOL ID: 126873), BRGY. LALIGAN, VALENCIA CITY, BUKIDNON 4TH LD | Region X | Bukidnon 1st DEO | Completed | ₱4.9M | 100% | Medium risk42 | —-0.094 |
| 15 | 18KA0099CONSTRUCTION OF 2-STOREY, 6-CLASSROOM SCHOOL BUILDING AT BAGONTAAS CES, VALENCIA CITY, BUKIDNONVALENCIA CITY, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱12.7M | 100% | Medium risk38 | —-0.046 |
| 16 | 18KA0094CONSTRUCTION OF 2-STOREY, 4-CLASSROOM SCHOOL BUILDING AT SAN MARTIN ES, MALAYBALAY CITY, BUKIDNONMALAYBALAY CITY, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱10.5M | 100% | Medium risk37 | —-0.047 |
| 17 | 24K00372CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SINAYAWAN, VALENCIA CITY, BUKIDNON | Region X | Region X | On-Going | ₱2.9M | 100% | Low risk15 | —-0.055 |
| 18 | 21KA0111CONSTRUCTION OF MULTI-PURPOSE FACILITY (COVERED COURT), SITIO PUNUON, BRGY. LAMBAGAN, CABANGLASAN, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱3M | 100% | Low risk12 | —-0.094 |
| 19 | 20KA0085CONSTRUCTION OF MULTI-PURPOSE BUILDING - CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. SINAYAWAN, VALENCIA CITY, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱2.4M | 100% | Low risk11 | —-0.094 |
| 20 | 20KA0084CONSTRUCTION OF MULTI-PURPOSE BUILDING - CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), PUROK 18, POBLACION, VALENCIA CITY, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱2.4M | 100% | Low risk11 | —-0.095 |
| 21 | 22KA0047CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT CABANGLASAN NATIONAL HIGH SCHOOL, BARANGAY POBLACION, CABANGLASAN, BUKIDNON, CABANGLASAN, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | Completed | ₱2M | 100% | Low risk10 | —-0.093 |
| 22 | 17KA0103CONSTRUCTION OF 1-STOREY, 3 CLASSROOM SCHOOL BUILDING '@ BUCO-SINAIT ES, VALENCIA CITY, BUKIDNONVALENCIA CITY, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱4.1M | 100% | Low risk4 | —-0.024 |
| 23 | 17KA0111CONSTRUCTION OF 1-STOREY, 2 CLASSROOM SCHOOL BUILDING '@CAMBANGON ES, VALENCIA CITY, BUKIDNONVALENCIA CITY, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱2.6M | 100% | Low risk3 | —-0.025 |
| 24 | 17KA0130CONSTRUCTION OF 1-STOREY, 2-CLASSROOM SCHOOL BUILDING (2ND UNIT)@ CAMBANGON ES, VALENCIA CITY BUKIDNONVALENCIA CITY, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱2.6M | 100% | Low risk3 | —-0.025 |
| 25 | 17KA0100CONSTRUCTION OF 1-STOREY, 2 CLASSROOM SCHOOL BUILDING '@ MT. NEBO ES, VALENCIA CITY, BUKIDNONVALENCIA CITY, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱2.5M | 100% | Low risk3 | —-0.024 |