45 projects on file, including joint ventures this contractor is part of.
Total projects
45
Total budget
₱1.6B
Average progress
98.3%
Completion rate
93.3%
Average risk score
50.6
Medium risk on average, out of 100
Flagged as unusual
5
11.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Negros Island Region | 38 | ₱1.1B | 48.7 | 1 | 98.4% |
| Region VI | 7 | ₱495.8M | 61.2 | 4 | 97.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 23 | ₱665.2M | 47.7 | 0 | 97.4% |
| Flood Control and Drainage | 14 | ₱651M | 54.5 | 3 | 98.8% |
| Buildings and Facilities | 5 | ₱217.6M | 47.0 | 0 | 100.0% |
| Bridges | 2 | ₱84.7M | 49.2 | 1 | 100.0% |
| OTHER | 1 | ₱9.3M | 84.5 | 1 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 18GL0121REHABILITATION OF SPILLWAY IN BARANGAY MONTILLA TO BARANGAY MACAGAHAY, MOISES PADILLA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱9.3M | 100% | High risk84 | Flagged0.006 |
| 17HL0003ASSETS PRESERVATION OF NAT'L. RD.-REHAB/RECONST/UPGRADING. . .DGTE. SOUTH RD.,K0110+313-K0112+239,K0 | Negros Island Region | Negros Oriental 3rd DEO | Completed | ₱78.2M | 100% | High risk69 | —-0.051 |
| 16HL0158ASSETS PRESERV. OF NAT'L. RD-REHAB/RECONST./UPGRADING . . . BAYAWAN-KABANKALAN RD.,K0102+368-K0104+0 | Negros Island Region | Negros Oriental 3rd DEO | Completed | ₱48.9M | 100% | High risk67 | —-0.051 |
| 18G00094UPGRADING OF SHORE PROTECTION IN BRGY. ZONES 1, 1-A, AND 3 | Region VI | Region VI | Completed | ₱14.7M | 100% | High risk66 | Flagged0.003 |
| 17HK0161CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS AT ACCESS ROAD LEADING TO BANDERA HILLS, BRGY. BASAK, SAN JOSE, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 2nd DEO | Completed | ₱18.5M | 100% | High risk66 | —-0.053 |
| 23G00057CONSTRUCTION OF DIVERSION CHANNEL, BACOLOD CITY, NEGROS OCCIDENTAL | Region VI | Region VI | On-Going | ₱152.4M | 84% | High risk66 | Flagged0.001 |
| 24GA0014CONSTRUCTION OF REVETMENT WALL ALONG IBAJAY RIVER BRGY. POLO, IBAJAY, AKLAN | Region VI | Aklan DEO | Completed | ₱128.8M | 100% | High risk65 | —-0.053 |
| 17HJ0013CONSTRUCTION OF SAN JOSE FLOOD CONTROL ALONG DUMAGUETE NORTH ROAD, MANJUYOD, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱13.9M | 100% | High risk65 | —-0.044 |
| 17RG0002CONCRETING OF BRGY. ROAD, BARANGAY BANILAD-BAJUMPANDAN, DUMAGUETE CITY | Negros Island Region | Negros Oriental 2nd DEO | Completed | ₱6.5M | 100% | High risk65 | —-0.059 |
| 24GA0015CONSTRUCTION OF REVETMENT WALL ALONG IBAJAY RIVER BRGY. RIZAL, IBAJAY, AKLAN | Region VI | Aklan DEO | Completed | ₱95.3M | 100% | High risk65 | —-0.061 |
| 18G00096REHABILITATION OF DRAINAGE SYSTEM IN BGRY. ZONE 7, 5, 4 AND BRGY. PATIC | Region VI | Region VI | Completed | ₱13.3M | 100% | High risk64 | Flagged0.004 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 18GL0121REHABILITATION OF SPILLWAY IN BARANGAY MONTILLA TO BARANGAY MACAGAHAY, MOISES PADILLA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱9.3M | 100% | High risk84 | Flagged0.006 |
| 18G00096REHABILITATION OF DRAINAGE SYSTEM IN BGRY. ZONE 7, 5, 4 AND BRGY. PATIC | Region VI | Region VI | Completed | ₱13.3M | 100% | High risk64 | Flagged0.004 |
| 18G00094UPGRADING OF SHORE PROTECTION IN BRGY. ZONES 1, 1-A, AND 3 | Region VI | Region VI | Completed | ₱14.7M | 100% | High risk66 | Flagged0.003 |
| 23G00057CONSTRUCTION OF DIVERSION CHANNEL, BACOLOD CITY, NEGROS OCCIDENTAL | Region VI | Region VI | On-Going | ₱152.4M | 84% | High risk66 | Flagged0.001 |
| 20G00093REHABILITATION AND IMPROVEMENT OF FLOOD CONTROL STRUCTURE OF SIBUCAO RIVER, BRGY. BAGONAWA, SAN ENRIQUE, NEGROS OCCIDENTAL | Region VI | Region VI | Completed | ₱55.1M | 100% | Medium risk53 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 18GL0121REHABILITATION OF SPILLWAY IN BARANGAY MONTILLA TO BARANGAY MACAGAHAY, MOISES PADILLA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱9.3M | 100% | High risk84 | Flagged0.006 |
| 2 | 17HL0003ASSETS PRESERVATION OF NAT'L. RD.-REHAB/RECONST/UPGRADING. . .DGTE. SOUTH RD.,K0110+313-K0112+239,K0 | Negros Island Region | Negros Oriental 3rd DEO | Completed | ₱78.2M | 100% | High risk69 | —-0.051 |
| 3 | 16HL0158ASSETS PRESERV. OF NAT'L. RD-REHAB/RECONST./UPGRADING . . . BAYAWAN-KABANKALAN RD.,K0102+368-K0104+0 | Negros Island Region | Negros Oriental 3rd DEO | Completed | ₱48.9M | 100% | High risk67 | —-0.051 |
| 4 | 18G00094UPGRADING OF SHORE PROTECTION IN BRGY. ZONES 1, 1-A, AND 3 | Region VI | Region VI | Completed | ₱14.7M | 100% | High risk66 | Flagged0.003 |
| 5 | 17HK0161CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS AT ACCESS ROAD LEADING TO BANDERA HILLS, BRGY. BASAK, SAN JOSE, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 2nd DEO | Completed | ₱18.5M | 100% | High risk66 | —-0.053 |
| 6 | 23G00057CONSTRUCTION OF DIVERSION CHANNEL, BACOLOD CITY, NEGROS OCCIDENTAL | Region VI | Region VI | On-Going | ₱152.4M | 84% | High risk66 | Flagged0.001 |
| 7 | 24GA0014CONSTRUCTION OF REVETMENT WALL ALONG IBAJAY RIVER BRGY. POLO, IBAJAY, AKLAN | Region VI | Aklan DEO | Completed | ₱128.8M | 100% | High risk65 | —-0.053 |
| 8 | 17HJ0013CONSTRUCTION OF SAN JOSE FLOOD CONTROL ALONG DUMAGUETE NORTH ROAD, MANJUYOD, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱13.9M | 100% | High risk65 | —-0.044 |
| 9 | 17RG0002CONCRETING OF BRGY. ROAD, BARANGAY BANILAD-BAJUMPANDAN, DUMAGUETE CITY | Negros Island Region | Negros Oriental 2nd DEO | Completed | ₱6.5M | 100% | High risk65 | —-0.059 |
| 10 | 24GA0015CONSTRUCTION OF REVETMENT WALL ALONG IBAJAY RIVER BRGY. RIZAL, IBAJAY, AKLAN | Region VI | Aklan DEO | Completed | ₱95.3M | 100% | High risk65 | —-0.061 |
| 11 | 18G00096REHABILITATION OF DRAINAGE SYSTEM IN BGRY. ZONE 7, 5, 4 AND BRGY. PATIC | Region VI | Region VI | Completed | ₱13.3M | 100% | High risk64 | Flagged0.004 |
| 12 | 21HJ0062REHABILITATION/IMPROVEMENT OF CABCABAN-NALUNDAN ROAD, MUNICIPALITY OF BINDOY, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱91.7M | 100% | Medium risk54 | —-0.081 |
| 13 | 20G00093REHABILITATION AND IMPROVEMENT OF FLOOD CONTROL STRUCTURE OF SIBUCAO RIVER, BRGY. BAGONAWA, SAN ENRIQUE, NEGROS OCCIDENTAL | Region VI | Region VI | Completed | ₱55.1M | 100% | Medium risk53 | Flagged0.001 |
| 14 | 17RB0118CONSTRUCTION OF THREE (3) UNITS - THREE (3) STOREY FIFTEEN (15) CLASSROOM SCHOOL BUILDING AT VICTORIAS NATIONAL HIGH SCHOOL, VICTORIAS CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 1st DEO | Completed | ₱85.7M | 100% | Medium risk51 | —-0.008 |
| 15 | 23HJ0020OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-TERTIARY ROADS-MABINAY-AYUNGON RD - K0114+765-K0116+932, K0117+000-K0120+231, K0128+151-K0128+308, AYUNGON | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱55.2M | 100% | Medium risk51 | —-0.087 |
| 16 | 20G00108CONSTRUCTION OF PERMANENT EVACUATION CENTER/ MULTI-PURPOSE COVERED COURT (STANDARD) | Region VI | Region VI | Completed | ₱36.2M | 100% | Medium risk49 | —-0.063 |
| 17 | 17RB0119CONSTRUCTION OF THREE (3) UNITS - TWO (2) STOREY TWELVE (12) CLASSROOM SCHOOL BUILDING AT VICTORIAS NATIONAL HIGH SCHOOL, VICTORIAS CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 1st DEO | Completed | ₱53.7M | 100% | Medium risk49 | —-0.017 |
| 18 | 24GL0082REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG BINALBAGAN RIVER AT BRGY. 1 AND BRGY. 3, MUN. OF MOISES PADILLA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱50.2M | 100% | Medium risk48 | —-0.065 |
| 19 | 24GL0089REHABILITATION AND IMPROVEMENT OF SPILLWAY AND SLOPE PROTECTION AT BRG. MACAGAHAY AND BRGY. MONTILLA, MUN. OF MOISES PADILLA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱47M | 100% | Medium risk48 | —-0.066 |
| 20 | 18GL0122REHABILITATION OF SLOPE PROTECTION IN BINALBAGAN RIVER BRGY. 3, POBLACION, MOISES PADILLA, NEG. OCC | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱9.3M | 100% | Medium risk47 | —-0.024 |
| 21 | 18GL0120REHABILITATION OF DRAINAGE OUTLET AT BRGY. 1, POBLACION, MOISES PADILLA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.022 |
| 22 | 20GM0064IMPROVEMENT OF BRIDGE, SIT-AN CREEK, BRGY. EAST, CANDONI, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱29.6M | 100% | Medium risk46 | —-0.007 |
| 23 | 18HJ0062CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES: BRGY. MANTAHAW-MOLOGPOLOG-NALUNDAN-ATOTES-BULOD ROAD-JCT. DUMAGUETE NORTH ROAD IN SUPPORT OF BROOM REED MAKER, COCONUT, AN | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱46.4M | 100% | Medium risk45 | —-0.087 |
| 24 | 18HK0006ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGMENT PROGRAM | Negros Island Region | Negros Oriental 2nd DEO | Completed | ₱32.9M | 100% | Medium risk45 | —-0.061 |
| 25 | 18HK0005ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION OF TANJAY | Negros Island Region | Negros Oriental 2nd DEO | Completed | ₱29.4M | 100% | Medium risk45 | —-0.066 |