Opening the dossier…
Opening the dossier…
Contractor dossier
166 projects on file, including joint ventures this contractor is part of.
Total projects
166
Total budget
₱1.1B
Average progress
98.7%
Completion rate
97.0%
Average risk score
32.9
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 99 | ₱797M | 36.3 | 0 | 97.8% |
| Negros Island Region | 59 | ₱311.2M | 29.5 | 0 | 100.0% |
| Region X | 8 | ₱16.3M | 16.0 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 100 | ₱525.2M | 28.9 | 0 | 100.0% |
| Roads | 47 | ₱453.5M | 37.6 | 0 | 95.3% |
| Water Provision and Storage | 10 | ₱31.6M | 27.7 | 0 | 100.0% |
| OTHER | 7 | ₱89.6M | 62.5 | 0 | 100.0% |
| Flood Control and Drainage | 2 | ₱24.6M | 45.3 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 18HM0006CLUSTER I: 1. CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. CAITICAN, SIQUIJOR; 2. CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. CANG-ADIENG, SIQUIJOR; 3. CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. PULANGYUTA, SIQUIJOR; 4. CONSTRUCTION OF | Negros Island Region | Siquijor DEO | Completed | ₱6.6M | 100% | High risk70 | —-0.034 |
| 20HB0163LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS - CONCRETING OF ROADS AT SITIO CANTUGOP, NAPO TO BRGY. PUTLONGCAM, ALICIA, BOHOL ST. 0+000.00 - STA.3+202.90 WITH EXCEPTION - SECTION 1; STA. 2+065.00 - STA. 2+365 - SECT | Region VII | Bohol 3rd DEO | Completed | ₱49.5M | 100% | High risk68 | —-0.030 |
| 19HB0116CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES-JCT. (LIR) QUINOGITAN-SEVILLA-HANOPOL-TAGUSTUSAN (BALILIHAN) ROAD IN SUPPORT OF THE FURNITURE AND GARMENTS AND TOURISM INDUST | Region VII | Bohol 3rd DEO | Completed | ₱9.3M | 100% | High risk60 | —-0.030 |
| 21HB0026CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT TO ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTURE PROGRAM -TRIP), JCT. (TER) ITUM-DUAY-PAYAO ROAD, DUERO LEADING TO CAMP VERDE NATURE PARK IN DUERO, BOHOL, | Region VII | Bohol 3rd DEO | Completed | ₱4.9M | 100% | High risk60 | —-0.032 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 24HB0119CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN VALERIANO A. GANAS HIGH SCHOOL, BRGY. TAMBOAN, CARMEN, BOHOL | Region VII | Bohol 3rd DEO | Completed | ₱4.9M | 100% | Medium risk40 | —-0.048 |
| 77 | 22HJ0083CONCRETING OF BRGY. LINOTHANGAN (LEADING TO LOWER PULA) FMR, BRGY, LINOTHANGAN, CANLAON CITY, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱6M | 100% | Medium risk39 | —-0.042 |
| 78 | 22HJ0087CONCRETING OF BRGY. PULA (LEADING TO UPPER LINOTHANGAN) FMR, BRGY, PULA, CANLAON CITY, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱6M | 100% | Medium risk39 | —-0.042 |
| 79 | 19HB0210CONCRETING OF BRGY. ALOJA-BRGY. BEHIND THE CLOUDS FMR, BRGY. ALOJA AND BRGY. BEHIND THE CLOUDS, BATUAN, BOHOL STA.0+481.17-STA.0+629.24 - 1ST SECTION STA. 0+994.04-STA.1+351.97- 2ND SECTION | Region VII | Bohol 3rd DEO | Completed | ₱9.9M | 100% | Medium risk39 | —-0.041 |
| 80 | 23HB0175CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALEVIATING GAPS (SIPAG) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BRGY. BOTOC ORIENTAL, LOAY, BOHOL | Region VII | Bohol 3rd DEO | Completed | ₱4.8M | 100% | Medium risk39 | —-0.052 |
| 81 | 24HB0161CONSTRUCTION OF 1STY2CL, COGON ES, LILA, BOHOL | Region VII | Bohol 3rd DEO | Completed | ₱6.5M | 100% | Medium risk39 | —-0.052 |
| 82 | 24HB0160CONSTRUCTION OF 1 STY 2CL, CALVARIO ELEMENTARY SCHOOL, LILA, BOHOL | Region VII | Bohol 3rd DEO | Completed | ₱6.4M | 100% | Medium risk39 | —-0.052 |
| 83 | 24HB0162CONSTRUCTION OF 1STY 2CL, MACALINGAN P/S, LILA, BOHOL | Region VII | Bohol 3rd DEO | Completed | ₱6.5M | 100% | Medium risk39 | —-0.052 |
| 84 | 23HB0176CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALEVIATING GAPS (SIPAG) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BRGY. TOCDOG DAKU, LOAY, BOHOL | Region VII | Bohol 3rd DEO | Completed | ₱4.8M | 100% | Medium risk38 | —-0.052 |
| 85 | 20HJ0076CONSTRUCTION OF 1 UNIT ONE-STOREY THREE CLASSROOM SCHOOL BUILDING AT MALANGSA ES, VALLEHERMOSO, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱5.1M | 100% | Medium risk38 | —-0.045 |
| 86 | 19KI0178CONSTRUCTION OF 1-STOREY 3-CL (WITH TOILET ATTACHED) SCHOOL BUILDING AT MANGIDKID ES (127500), PLARIDEL, MISAMIS OCCIDENTAL. | Region X | Misamis Occidental 1st DEO | Completed | ₱6.7M | 100% | Medium risk38 | —-0.051 |
| 87 | 20HB0157LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS CONCRETING OF ROADS AT BRGY. IPIL, JAGNA, BOHOL STA. 0+000.00 - STA. 0+314.00 | Region VII | Bohol 3rd DEO | Completed | ₱4.7M | 100% | Medium risk37 | —-0.095 |
| 88 | 20HJ0125CONSTRUCTION OF 2 UNITS ONE-STOREY THREE CLASSROOM SCHOOL BUILDING W/ TOILET ATTACHED AT EACH CLASSROOM AT LAOS ES, GUIHULNGAN, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱14.5M | 100% | Medium risk37 | —-0.046 |
| 89 | 18HJ0092CONSTRUCTION OF ONE UNIT FOUR STOREY WORKSHOP BUILDING AT PACUAN NATIONAL HIGH SCHOOL (7.0M X 23M PLUS CORRIDOR 2.50M), LA LIBERTAD, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱21.3M | 100% | Medium risk37 | —-0.041 |
| 90 | 21HJ0109CONSTRUCTION/COMPLETION OF 1 UNIT 2 STOREY 4 CLASSROOM SCHOOL BUILDING AT GUIHULNGAN NATIONAL AGRICULTURAL SCHOOL, CITY OF GUIHULNGAN, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱8.4M | 100% | Medium risk36 | —-0.047 |
| 91 | 19HB0211CONCRETING OF BRGY. ODIONG FMR, BRGY. ODIONG, JAGNA, BOHOL STA.0+040.00-STA.0+317.00 | Region VII | Bohol 3rd DEO | Completed | ₱4.7M | 100% | Medium risk34 | —-0.041 |
| 92 | 19HM0033LOCALLY FUNDED PROJECTS, BUILDINGS AND OTHER STRUCTURES-MULTIPURPOSE/FACILITIES-LOCAL INFRASTRUCTURE PROGRAM, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, LAZI, SIQUIJOR, 1) YTAYA, LAZI, SIQUIJOR, 2) LOWER CABANGCALAN, LAZI, SIQUIJOR, 3) CATAMBOAN | Negros Island Region | Siquijor DEO | Completed | ₱3.9M | 100% | Medium risk33 | —-0.085 |
| 93 | 18HM0010CLUSTER VI: 1. CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. CANGBAGSA, LARENA, SIQUIJOR; 2. CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. CABULIHAN, LARENA, SIQUIJOR | Negros Island Region | Siquijor DEO | Completed | ₱2.8M | 100% | Medium risk33 | —-0.085 |
| 94 | 17HM0040CONSTRUCTION OF 1-UNIT 2-STOREY 6-CLASSROOM SCHOOL BUILDING AT LAZI CENTRAL ELEMENTARY SCHOOL, LAZI, SIQUIJOR | Negros Island Region | Siquijor DEO | Completed | ₱12.1M | 100% | Medium risk32 | —-0.023 |
| 95 | 16HM0044CONSTRUCTION OF 1-UNIT 2-STOREY 4-CLASSROOM SCHOOL BUILDING AT CABULIHAN INTEGRATED SCHOOL, LARENA, SIQUIJOR | Negros Island Region | Siquijor DEO | Completed | ₱6.5M | 100% | Medium risk32 | —-0.023 |
| 96 | 17HM0055CONSTRUCTION OF 1-UNIT 2-STOREY 4-CLASSROOM SCHOOL BUILDING AT SAN ANTONIO ELEMENTARY SCHOOL, SIQUIJOR (CAPITAL), SIQUIJOR | Negros Island Region | Siquijor DEO | Completed | ₱9.3M | 100% | Medium risk32 | —-0.023 |
| 97 | 17HM0028CONSTRUCTION OF 1-UNIT 2-STOREY 4-CLASSROOM SCHOOL BUILDING AT PONONG LEMENTARY SCHOOL, SIQUIJOR (CAPITAL), SIQUIJOR | Negros Island Region | Siquijor DEO | Completed | ₱9.4M | 100% | Medium risk32 | —-0.023 |
| 98 | 17HM0030CONSTRUCTION OF 1-UNIT 2-STOREY 4-CLASSOOM SCHOOL BUILDING AT CABULIHAN INTEGRATED SCHOOL, LARENA, SIQUIJOR | Negros Island Region | Siquijor DEO | Completed | ₱9.2M | 100% | Medium risk32 | —-0.023 |
| 99 | 18HM0041CONSTRUCTION OF WATER SUPPLY SYSTEM (LEVEL II), BRGY. BONGA, MARIA, SIQUIJOR | Negros Island Region | Siquijor DEO | Completed | ₱2.4M | 100% | Medium risk32 | —-0.047 |
| 100 | 19HM0042LOCALLY FUNDED PROJECTS, WATER MANAGEMENT FACILITIES-WATER SUPPLY-LOCAL INFRASTRUCTURE PROGRAM, CONSTRUCTION OFLEVEL II WATER SYSTEM, LAZI, SIQUIJOR, 1) CAMPALANAS, LAZI, SIQUIJOR, 2) GABAYAN AND TALAYONG, LAZI, SIQUIJOR, 3) POO, LAZI, SIQUIJOR | Negros Island Region | Siquijor DEO | Completed | ₱4M | 100% | Medium risk31 | —-0.049 |