Contractor dossier
869 projects on file, including joint ventures this contractor is part of.
Total projects
869
Total budget
₱44B
Average progress
96.1%
Completion rate
90.6%
Average risk score
44.8
Medium risk on average, out of 100
Flagged as unusual
22
2.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 228 | ₱11B | 49.4 | 3 | 96.0% |
| Region IV-B | 126 | ₱4.3B | 29.0 | 2 | 95.4% |
| Region III | 113 | ₱5.6B | 38.2 | 1 | 96.3% |
| Region XI | 99 | ₱4.5B | 43.3 | 2 | 99.9% |
| Region IV-A | 97 | ₱5.7B | 52.9 | 1 | 97.3% |
| Region I | 48 | ₱4.1B | 54.8 | 5 | 92.2% |
| Region VIII | 32 | ₱1.9B | 51.9 | 0 | 98.6% |
| Region II | 27 | ₱562.8M | 36.8 | 0 | 100.0% |
| Region VI | 26 | ₱1.6B | 53.9 | 3 | 87.8% |
| Region XII | 22 | ₱787.9M | 26.4 | 0 | 99.8% |
| Region IX | 18 | ₱2.1B | 70.8 | 3 | 90.4% |
| Region V | 15 | ₱605.6M | 53.0 | 1 | 85.1% |
| Region X | 7 | ₱414.9M | 35.8 | 0 | 100.0% |
| Region VII | 6 | ₱589.5M | 60.7 | 1 | 89.6% |
| Negros Island Region | 3 | ₱190.6M | 50.6 | 0 | 100.0% |
| Central Office | 2 | ₱147.6M | 68.3 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 314 | ₱20B | 50.2 | 4 | 96.7% |
| Buildings and Facilities | 314 | ₱8.8B | 35.3 | 3 | 98.8% |
| Roads | 200 | ₱12.1B | 48.1 | 2 | 96.3% |
| Bridges | 21 | ₱1.5B | 54.2 | 9 | 49.7% |
| OTHER | 15 | ₱1.2B | 65.8 | 3 | 94.6% |
| Bridges, Roads | 2 | ₱374.9M | 66.4 | 0 | 82.2% |
| Water Provision and Storage | 2 | ₱6.5M | 41.9 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱63.7M | 94.6 | 1 | 35.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OI0095RETROFITTING OF PLEASANT DRIVE BRIDGE, BRGY. BAYANAN, MUNTINLUPA CITY. | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱63.7M | 35% | High risk95 | Flagged0.024 |
| 24JA0146CONSTRUCTION/REHABILITATION OF ZAMBOANGA CONVENTION CENTER, PASONANCA, ZAMBOANGA CITY PHASE 1 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱117.6M | 30% | High risk84 | Flagged0.031 |
| 23GE0013CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SEBARIO RIVER, BARANGAY SEBARIO, SAN LORENZO, GUIMARAS | Region VI | Guimaras DEO | On-Going | ₱57.9M | 99% | High risk82 | Flagged0.016 |
| 24CC0546CONSTRUCTION OF FLOOD CONTROL STRUCTURE INCLUDING PUMPING STATION AND FLOOD GATE AT BARANGAY MEYTO, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.7M | 0% | High risk81 | Flagged0.008 |
| 24CM0078FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, REHABILITATION OF FLOOD MITIGATION STRUCTURE, STO. TOMAS RIVER (STA. FE SECTION), SAN MARCELINO, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱386M | 100% | High risk80 | —-0.019 |
| 24JK0003CONSTRUCTION OF FLOOD CONTROL PROJECT IN BARANGAY PASONANCA, PHASE 3, ZAMBOANGA CITY | Region IX | Zamboanga City 1st DEO | On-Going | ₱143.3M | 59% | High risk80 | Flagged0.050 |
| 24CC0550CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITH WATER PUNMPING STATION AT BARANGAY PANGINAY, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱96.5M | 74% | High risk79 | —-0.015 |
| 25DI0006CONSTRUCTION OF RIVER PROTECTION STRUCTURE NEAR SAN LORENZO ROAD, PHASE 1, SANTA ROSA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱94.3M | 69% | High risk79 | —-0.009 |
| 24C00158ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-TERTIARY ROADS-MEYCAUAYAN-CAMALIG-BAHAY PARI ROAD, PROVINCE OF BULACAN | Region III | Region III | On-Going | ₱174.2M | 67% | High risk77 | —-0.002 |
| 24HC0019ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS- FLOOD MANAGEMENT PROGRAM -CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF BIEN UNIDO SEAWALL AT BIEN UNIDO, BOHOL | Region VII | Bohol 2nd DEO | On-Going | ₱144.7M | 89% | High risk77 | Flagged0.030 |
| 25CC0462SIPAG - INTERJURISDICTIONAL ROADS AND/OR BRIDGES 9ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) PULILAN-BALIUAG BYPASS ROAD - BARANGAY SANTA PEREGRINA (PHASE 2), CHAINAGE 1300-CHAINAGE 3890, PULILAN, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 25% | High risk76 | —-0.012 |
| 25CC0457SIPAG - INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) - PULILAN-BALIUAG BYPASS ROAD - DULONG MALABON, CHAINAGE 0-CHAINAGE 1300, PULILAN, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 53% | High risk76 | —-0.020 |
| 22GA0030CONSTRUCTION OF REVETMENT WALL ALONG IBAJAY RIVER BRGY. LAGUINBANWA, IBAJAY, AKLAN | Region VI | Aklan DEO | Completed | ₱86.8M | 100% | High risk76 | —-0.018 |
| 25CD0178CONSTRUCTION OF BARANGAY ROADS, BRGY. CAYSIO, CAYPOMBO AND MAG-ASAWANG SAPA, SANTA MARIA, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱96M | 0% | High risk76 | —-0.007 |
| 23CC0284CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY PAGALA, BALIUAG, BULACAN (K005+681 TO K005+981), BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱72.4M | 100% | High risk76 | —-0.061 |
| 23JF0048CONSTRUCTION OF SHORELINE PROTECTION, BARANGAY PRESIDENT ROXAS, R.T. LIM, ZAMBOANGA SIBUGAY PACKAGE 1 | Region IX | Zamboanga Sibugay 2nd DEO | On-Going | ₱144.7M | 98% | High risk75 | —-0.011 |
| 25JK0028CONSTRUCTION OF FLOOD MITIGATION PROJECT (PHASE 2) IN BARANGAY PASONANCA, ZAMBOANGA CITY | Region IX | Zamboanga City 1st DEO | On-Going | ₱95M | 72% | High risk75 | —-0.017 |
| 24CD0259REHABILITATION OF PUMPING STATIONS WITHIN MARILAO AND MEYCAUAYAN, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱56.9M | 100% | High risk74 | —-0.058 |
| 23OE0216CONSTRUCTION OF PUMPING STATION AT ESTERO DE SAN MIGUEL, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱142.6M | 100% | High risk74 | —-0.005 |
| 18J00085CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-FLOOD CONTROL AND DRAINAGE - FLOOD CONTROL STRUCTURES/FACILITIES - CONSTRUCTION OF FLOOD CONTROL-DRAINAGE AT ISABELA CITY PROPER, ISABELA CITY, BASILAN | Region IX | Region IX | Completed | ₱130.3M | 100% | High risk73 | —-0.042 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24JK0003CONSTRUCTION OF FLOOD CONTROL PROJECT IN BARANGAY PASONANCA, PHASE 3, ZAMBOANGA CITY | Region IX | Zamboanga City 1st DEO | On-Going | ₱143.3M | 59% | High risk80 | Flagged0.050 |
| 24JA0146CONSTRUCTION/REHABILITATION OF ZAMBOANGA CONVENTION CENTER, PASONANCA, ZAMBOANGA CITY PHASE 1 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱117.6M | 30% | High risk84 | Flagged0.031 |
| 24HC0019ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS- FLOOD MANAGEMENT PROGRAM -CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF BIEN UNIDO SEAWALL AT BIEN UNIDO, BOHOL | Region VII | Bohol 2nd DEO | On-Going | ₱144.7M | 89% | High risk77 | Flagged0.030 |
| 25OI0095RETROFITTING OF PLEASANT DRIVE BRIDGE, BRGY. BAYANAN, MUNTINLUPA CITY. | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱63.7M | 35% | High risk95 | Flagged0.024 |
| 23J00212CONSTRUCTION OF NEW PROVINCIAL GOVERNMENT CAPITOL BUILDING, KARUNGDUNG, BONGAO, TAWI-TAWI | Region IX | Region IX | On-Going | ₱240.8M | 80% | High risk72 | Flagged0.023 |
| 23GE0013CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SEBARIO RIVER, BARANGAY SEBARIO, SAN LORENZO, GUIMARAS | Region VI | Guimaras DEO | On-Going | ₱57.9M | 99% | High risk82 | Flagged0.016 |
| 25D00172CONSTRUCTION OF BY-PASS AND DIVERSION ROADS LIPA CITY-PADRE GARCIA DIVERSION ROAD, PACKAGE S, BATANGAS | Region IV-A | Region IV-A | On-Going | ₱187.2M | 11% | High risk66 | Flagged0.014 |
| 24EF0065WIDENING OF PERMANENT BRIDGES BATANG-BATANG BR. (B00035PW) ALONG PUERTO PRINCESA SOUTH RD., NARRA, PALAWAN | Region IV-B | Palawan 2nd DEO | On-Going | ₱117M | 58% | High risk60 | Flagged0.014 |
| 24G00041CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG ILOG-BUNGOL RIVER (SO. LAPAK), ILOG, NEGROS OCCIDENTAL | Region VI | Region VI | On-Going | ₱193M | 40% | High risk66 | Flagged0.013 |
| 23A00451REPAIR/ REHABILITATION OF CALUNGBUYAN BR. ALONG SANTA-RANCHO ROAD, SANTA, ILOCOS SUR | Region I | Region I | On-Going | ₱178.5M | 90% | High risk63 | Flagged0.012 |
| 25A00159CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BAUANG - SAN FERNANDO - SAN JUAN BYPASS ROAD, (SAN FERNANDO- SAN JUAN SECTION), PACKAGE 2, LA UNION | Region I | Region I | On-Going | ₱88.7M | 10% | Medium risk52 | Flagged0.012 |
| 25A00518SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), CONSTRUCTION OF SWIP, BARANGAY CAMANDINGAN, CITY OF BATAC, ILOCOS NORTE | Region I | Region I | On-Going | ₱112.3M | 0% | High risk66 | Flagged0.009 |
| 24A00621CONSTRUCTION/REPAIR/REHABILITATION OF DORMITORY - MARIANO MARCOS STATE UNIVERSITY | Region I | Region I | On-Going | ₱48.8M | 90% | Medium risk50 | Flagged0.009 |
| 24CC0546CONSTRUCTION OF FLOOD CONTROL STRUCTURE INCLUDING PUMPING STATION AND FLOOD GATE AT BARANGAY MEYTO, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.7M | 0% | High risk81 | Flagged0.008 |
| 22E00133SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-MULTI-PURPOSE BUILDING/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF CRUISE PORT AND FACILITIES-PACKAGE F, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱95.5M | 52% | Medium risk52 | Flagged0.007 |
| 23OI0103CONSTRUCTION OF BYPASS / ALTERNATE DIVERSION ROAD, ALABANG ZAPOTE ROAD, LAS PINAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱46.7M | 0% | Medium risk50 | Flagged0.006 |
| 24F00007ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF FLYOVERS/INTERCHANGES/UNDERPASSES/LONG SPAN BRIDGES-DARAGA ALBAY DIVERSION ROAD (TABON-TABON FLYOVER), ALBAY, BRGY. TABON-TABON, DARAGA, AL | Region V | Region V | On-Going | ₱139.4M | 3% | High risk72 | Flagged0.005 |
| 25GD0060WIDENING OF BRIDGE - ANHAWON BR. (B00244PN) ALONG ILOILO EAST COAST-CAPIZ RD (PHASE II) | Region VI | Capiz 1st DEO | On-Going | ₱37M | 7% | Medium risk48 | Flagged0.003 |
| 21L00012CONSTRUCTION OF ROAD, POBLACION, MARAGUSAN - PALOC ROAD, PACKAGE 3, DAVAO DE ORO | Region XI | Region XI | On-Going | ₱125.4M | 91% | High risk63 | Flagged0.002 |
| 25A00226CONSTRUCTION OF MISSING LINKS/NEW ROADS - SANTOL (LA UNION) - KIBUNGAN (BENGUET) ROAD (SUGPON SECTION), LA UNION | Region I | Region I | On-Going | ₱56.1M | 25% | Medium risk53 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 21AA0080CONSTRUCTION OF ILOCOS NORTE PROVINCIAL CAPITOL MULTI-PURPOSE EXPANSION BUILDING, LAOAG CITY, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱99M | 100% | High risk73 | —-0.058 |
| 27 | 17CD0171IMPROVEMENT/REHABILITATION OF MINUYAN SPORTS COMPLEX, SAPANG PALAY, CITY OF SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱17.8M | 100% | High risk72 | —-0.073 |
| 28 | 24F00007ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF FLYOVERS/INTERCHANGES/UNDERPASSES/LONG SPAN BRIDGES-DARAGA ALBAY DIVERSION ROAD (TABON-TABON FLYOVER), ALBAY, BRGY. TABON-TABON, DARAGA, AL | Region V | Region V | On-Going | ₱139.4M | 3% | High risk72 | Flagged0.005 |
| 29 | 20A00225CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LAOAG-SAN NICOLAS BYPASS ROAD (LAOAG CITY SECTION), ILOCOS NORTE | Region I | Region I | Completed | ₱190M | 100% | High risk72 | —-0.050 |
| 30 | 23J00212CONSTRUCTION OF NEW PROVINCIAL GOVERNMENT CAPITOL BUILDING, KARUNGDUNG, BONGAO, TAWI-TAWI | Region IX | Region IX | On-Going | ₱240.8M | 80% | High risk72 | Flagged0.023 |
| 31 | 22J00024CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DAPITAN RIVER, TUTUA-POLO SECTION (DOWNSTREAM) ALONG DIPOLOG-OROQUIETA ROAD (SO1316MN) , DAPITAN CIT | Region IX | Region IX | On-Going | ₱95.3M | 95% | High risk71 | —-0.005 |
| 32 | 20DI0154CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SINALHAN, STA. ROSA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱30.4M | 100% | High risk71 | —-0.073 |
| 33 | 22O00081CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ILANG-ILANG CREEK LEADING TO TULLAHAN RIVER AT BRGY. COMMONWEALTH, QUEZON CITY | Central Office | Flood Control Management Cluster | Completed | ₱53.5M | 100% | High risk71 | —-0.078 |
| 34 | 20J00022CONSTRUCTION OF MISSING LINKS/NEW ROADS SINDANGAN - BAYOG - LAKEWOOD ROAD TALINGA- DAGOHOY - TINAPLAN - TITIK, ZAMBOANGA DEL NORTE | Region IX | Region IX | Completed | ₱163.3M | 100% | High risk71 | —-0.058 |
| 35 | 23A00342REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS, MANILA NORTH RD - K0578+640 - K0578+900 L/S | Region I | Region I | Completed | ₱337.7M | 100% | High risk70 | —-0.037 |
| 36 | 21J00030CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION/EXTENSION OF FLOOD CONTROL STRUCTURE (REVETMENT) ALONG DAPITAN RIVER, TUTUA-POLO SECTION ALONG DIPOLOG-OROQUIETA ROAD, DAPITAN CITY, ZAMBOANGA DEL NORTE PACKAGE I | Region IX | Region IX | On-Going | ₱108.8M | 100% | High risk70 | —-0.006 |
| 37 | 20A00181LOCAL INFRASTUCTURE PROGRAM - CONSTRUCTION OF MISSING LINK/NEW ROADS, PIDDIG-CARASI (ILOCOS NORTE) - CALANASAN(APAYAO) CONNECTING CABUGAO-CONNER (APAYAO)-TUAO(CAGAYAN) ROAD | Region I | Region I | Completed | ₱99M | 100% | High risk70 | —-0.069 |
| 38 | 22A00306CONSTRUCTION OF MISSING LINKS/NEW ROADS - PIDDIG-CARASI-CALANASAN ROAD, ILOCOS NORTE (PACKAGE 3) | Region I | Region I | Completed | ₱96.5M | 100% | High risk70 | —-0.070 |
| 39 | 17CD0170CONSTRUCTION OF BY-PASSES /DIVERSION ROADS, INCLUDING ROW, WESTERN BULACAN CONNECTOR, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱33.9M | 100% | High risk69 | —-0.068 |
| 40 | 23OE0213CONSTRUCTION OF RETARDING BASIN AT ESTERO DE KABULUSAN, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱96.5M | 100% | High risk69 | —-0.018 |
| 41 | 18DI0038NETWORK DEVELOPMENT PROGRAM- OFF- CARRIAGEWAY IMPROVEMENT- PRIMARY ROADS-MANILA SOUTH RD. - K0044+125 - K0045+652, CABUYAO CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱43M | 100% | High risk69 | —-0.036 |
| 42 | 18CC0217MALOLOS CITY CIRCUMFERENTIAL ROAD MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱61.4M | 100% | High risk69 | —-0.037 |
| 43 | 21J00059REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - RIZAL - DAKAK - DAPITAN COASTAL LOOP ROAD | Region IX | Region IX | On-Going | ₱102.9M | 100% | High risk68 | —-0.016 |
| 44 | 24D00062CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ALAMINOS - SAN PABLO CITY BYPASS ROAD, PACKAGE I, LAGUNA | Region IV-A | Region IV-A | On-Going | ₱224.6M | 66% | High risk68 | —-0.009 |
| 45 | 17DN0128CONSTRUCTION OF RETAINING WALL ALONG M.L. QUEZON EXTENSION, BRGY. SAN ROQUE, ANTIPOLO CITY | Region IV-A | Rizal 1st DEO | Completed | ₱17.3M | 100% | High risk68 | —-0.056 |
| 46 | 17B00049PROPOSED CONST'N OF REG'L EVACUATION CENTER, DISTRICT IV, BAYOMBONG, NUEVA VISCAYA | Region II | Region II | Completed | ₱30.9M | 100% | High risk68 | —-0.054 |
| 47 | 24E00054FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/MAIMNTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OPF ROAD DIKE/ESPLANADE ALONG SITIO KATANLAWAN, PALUAN, OCC. MINDORO | Region IV-B | Region IV-B | Completed | ₱241.2M | 100% | High risk67 | —-0.036 |
| 48 | 17DK0233CONSTRUCTION OF FLOOD CONTROL STRUCTURES WITHIN LALAVIÑAN (REAL -2) RIVER, REAL, QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱9.3M | 100% | High risk67 | —-0.058 |
| 49 | 25OH0007ORGANIZATIONAL OUTCOME 2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS/FLOOD MANAGEMENT PROGRAM/CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONST. OF BOOSTER PUMPING STATION ALONG ESTERO DE PANDACAN ALONG ADONIS STREET BRGY. 864, | National Capital Region | South Manila DEO | On-Going | ₱138.9M | 100% | High risk67 | —-0.043 |
| 50 | 24E00034FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS- CONST. OF ROAD DIKE/ESPLANADE ALONG PANGALAAN RIVER (LEFT SIDE), NAUJAN, OR. MINDORO | Region IV-B | Region IV-B | Completed | ₱289.5M | 100% | High risk67 | —-0.036 |