Opening the dossier…
Opening the dossier…
Contractor dossier
56 projects on file, including joint ventures this contractor is part of.
Total projects
56
Total budget
₱486.5M
Average progress
95.8%
Completion rate
92.9%
Average risk score
41.7
Medium risk on average, out of 100
Flagged as unusual
3
5.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 55 | ₱472M | 41.8 | 3 | 95.8% |
| Region III | 1 | ₱14.5M | 35.8 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 19 | ₱170.4M | 38.6 | 0 | 100.0% |
| Buildings and Facilities | 19 | ₱130.7M | 32.6 | 0 | 100.0% |
| Flood Control and Drainage | 12 | ₱147.2M | 46.4 | 0 | 99.3% |
| Bridges | 3 | ₱21.6M | 53.3 | 0 | 100.0% |
| OTHER | 2 | ₱11.7M | 86.4 | 2 | 37.4% |
| GAA 2025 SSP | 1 | ₱4.8M | 94.7 | 1 | 0.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25AJ0096CONCRETING OF ROAD, BRGY. ERFE, STA. BARBARA, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱4.8M | 0% | High risk95 | Flagged0.041 |
| 24A00580COMPLETION/EQUIPPING OF SUPER HEALTH CENTERS - MAPANDAN SUPER HEALTH CENTER, PANGASINAN | Region I | Region I | On-Going | ₱5.9M | 47% | High risk87 | Flagged0.059 |
| 24A00579COMPLETION/EQUIPPING OF SUPER HEALTH CENTERS - MANAOAG SUPER HEALTH CENTER, PANGASINAN | Region I | Region I | On-Going | ₱5.9M | 28% | High risk86 | Flagged0.065 |
| 17AJ0049CONSTRUCTION OF 3-STOREY DANIEL MARAMBA NATIONAL HIGH SCHOOL ALUMNI ASSOCIATION MPB-EDUCATION CENTER, STA. BARBARA, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱9.7M | 100% | High risk66 | —-0.056 |
| 17AI0022PREVENTIVE MAINTENANCE BASED ON PAVEMENT MGMT SYSTEM/HIGHWAY DEVT & MGMT-4 (HDM-4) (INTERMITTENT SEC | Region I | Pangasinan 3rd DEO | Completed | ₱14M | 100% | High risk66 | —-0.057 |
| 17AJ0052CONSTRUCTION OF DIKE WITH BANK PROTECTION WORKS, DALONGUE AND SONQUIL, STA. BARBARA, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱42M | 100% | High risk65 | —-0.044 |
| 17AJ0013CONSTRUCTION OF PROTECTION WORKS ALONG INGALERA RIVER, MALABAGO, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱14.1M | 100% | High risk65 | —-0.047 |
| 17AJ0030CONSTRUCTION OF PROTECTION WORKS ALONG INGALERA RIVER, LONGOS SECTION, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱14.7M | 100% | High risk65 | —-0.047 |
| 17AI0021CONSTN/REHAB/UPGRADING OF DRAINAGE ALONG PNVR, KO 175+000-KO175+669 | Region I | Pangasinan 3rd DEO | Completed | ₱6.4M | 100% | High risk65 | —-0.056 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24A00579COMPLETION/EQUIPPING OF SUPER HEALTH CENTERS - MANAOAG SUPER HEALTH CENTER, PANGASINAN | Region I | Region I | On-Going | ₱5.9M | 28% | High risk86 | Flagged0.065 |
| 24A00580COMPLETION/EQUIPPING OF SUPER HEALTH CENTERS - MAPANDAN SUPER HEALTH CENTER, PANGASINAN | Region I | Region I | On-Going | ₱5.9M | 47% | High risk87 | Flagged0.059 |
| 25AJ0096CONCRETING OF ROAD, BRGY. ERFE, STA. BARBARA, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱4.8M | 0% | High risk95 | Flagged0.041 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25AJ0096CONCRETING OF ROAD, BRGY. ERFE, STA. BARBARA, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱4.8M | 0% | High risk95 | Flagged0.041 |
| 2 | 24A00580COMPLETION/EQUIPPING OF SUPER HEALTH CENTERS - MAPANDAN SUPER HEALTH CENTER, PANGASINAN | Region I | Region I | On-Going | ₱5.9M | 47% | High risk87 | Flagged0.059 |
| 3 | 24A00579COMPLETION/EQUIPPING OF SUPER HEALTH CENTERS - MANAOAG SUPER HEALTH CENTER, PANGASINAN | Region I | Region I | On-Going | ₱5.9M | 28% | High risk86 | Flagged0.065 |
| 4 | 17AJ0049CONSTRUCTION OF 3-STOREY DANIEL MARAMBA NATIONAL HIGH SCHOOL ALUMNI ASSOCIATION MPB-EDUCATION CENTER, STA. BARBARA, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱9.7M | 100% | High risk66 | —-0.056 |
| 5 | 17AI0022PREVENTIVE MAINTENANCE BASED ON PAVEMENT MGMT SYSTEM/HIGHWAY DEVT & MGMT-4 (HDM-4) (INTERMITTENT SEC | Region I | Pangasinan 3rd DEO | Completed | ₱14M | 100% | High risk66 | —-0.057 |
| 6 | 17AJ0052CONSTRUCTION OF DIKE WITH BANK PROTECTION WORKS, DALONGUE AND SONQUIL, STA. BARBARA, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱42M | 100% | High risk65 | —-0.044 |
| 7 | 17AJ0013CONSTRUCTION OF PROTECTION WORKS ALONG INGALERA RIVER, MALABAGO, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱14.1M | 100% | High risk65 | —-0.047 |
| 8 | 17AJ0030CONSTRUCTION OF PROTECTION WORKS ALONG INGALERA RIVER, LONGOS SECTION, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱14.7M | 100% | High risk65 | —-0.047 |
| 9 | 17AI0021CONSTN/REHAB/UPGRADING OF DRAINAGE ALONG PNVR, KO 175+000-KO175+669 | Region I | Pangasinan 3rd DEO | Completed | ₱6.4M | 100% | High risk65 | —-0.056 |
| 10 | 17AI0060CONSTN & MAINT OF BRIDGES ALONG NATL RD, REPLACEMENT OF PERMANENT WEAK BRIDGES AT PRIMICIAS BRIDGE I | Region I | Pangasinan 3rd DEO | Completed | ₱5.6M | 100% | Medium risk54 | —-0.027 |
| 11 | 17AI0020CONSTN & MAINT OF BRIDGES ALONG NATL RD, REPLACEMENT OF PERMANENT WEAK BRIDGES AT PRIMICIAS BRIDGE I | Region I | Pangasinan 3rd DEO | Completed | ₱7.1M | 100% | Medium risk54 | —-0.028 |
| 12 | 17AH0038REHAB./MAJOR REPAIR OF PERMANENT BR AT BALOCTOT BR (B00579LZ) ALONG CARMEN JCTN-BAYAMBANG-MANAT RD. | Region I | Pangasinan 2nd DEO | Completed | ₱8.9M | 100% | Medium risk53 | —-0.029 |
| 13 | 20AI0011CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. MANAOL, POZORRUBIO, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱5.2M | 100% | Medium risk51 | —-0.089 |
| 14 | 22AJ0074CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BRGY. BALINGUEO, STA. BARBARA, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱4.9M | 100% | Medium risk50 | —-0.087 |
| 15 | 19AI0164CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MITURA RIVER, BRGY. TOBOY AND SOBOL, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱18.8M | 100% | Medium risk47 | —-0.075 |
| 16 | 21AJ0059CONSTRUCTION OF SLOPE PROTECTION ALONG SAN JUAN RIVER, BARANGAY TURAC, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱4.8M | 100% | Medium risk47 | —-0.072 |
| 17 | 18AI0007OFF-CARRIAGEWAY IMPVT OF TERTIARY RD ALONG BINALONAN-ASINGAN-STA. MARIA RD INCL ROW KO 194+623-KO 19 | Region I | Pangasinan 3rd DEO | Completed | ₱24.3M | 100% | Medium risk46 | —-0.089 |
| 18 | 23AJ0068CONSTRUCTION OF DRAINAGE AT BARANGAY CABILOCAAN, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱4.8M | 100% | Medium risk46 | —-0.074 |
| 19 | 20AI0030CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS MANILA NORTH ROAD, KO 178+268 - KO 179+057; KO 180+275 - KO 180+363 | Region I | Pangasinan 3rd DEO | Completed | ₱15.3M | 100% | Medium risk46 | —-0.089 |
| 20 | 25AJ0011CONSTRUCTION OF DRAINAGE STRUCTURE, BARANGAY GUILIG, MALASIQUI, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱6.7M | 91% | Medium risk45 | —-0.038 |
| 21 | 18AJ0062CONSTRUCTION OF PROTECTION WORKS ALONG SINUCALAN RIVER, BARANGAY DALONGUE, STA. BARBARA, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱18.5M | 100% | Medium risk45 | —-0.072 |
| 22 | 18AI0023ASSET PRESERVATION-PREVENTIVE MAINT CARMEN JCT-MANAT RD KO 176+000-KO 176+500 | Region I | Pangasinan 3rd DEO | Completed | ₱6.2M | 100% | Medium risk45 | —-0.092 |
| 23 | 20AJ0090CONSTRUCTION OF PROTECTION WORKS ALONG SINUCALAN RIVER AT BRGY. TEBAG, STA. BARBARA, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱9.5M | 100% | Medium risk45 | —-0.074 |
| 24 | 24AJ0105CONSTRUCTION OF 1-STOREY 3-CLASSROOM SCHOOL BUILDING IN SAN VICENTE ELEMENTARY SCHOOL, BRGY. SAN VICENTE, BAYAMBANG, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱6M | 100% | Medium risk45 | —-0.046 |
| 25 | 21AJ0012CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG AGNO RIVER, BARANGAY SAN GABRIEL 2ND, BAYAMBANG, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱9.6M | 100% | Medium risk44 | —-0.073 |