Contractor dossier
10 projects on file, including joint ventures this contractor is part of.
Total projects
10
Total budget
₱694.3M
Average progress
82.0%
Completion rate
40.0%
Below 70%
Average risk score
68.4
High risk on average, out of 100
Flagged as unusual
4
40.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IX | 10 | ₱694.3M | 68.4 | 4 | 82.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 4 | ₱431.7M | 71.4 | 1 | 93.4% |
| Roads | 3 | ₱202.2M | 65.2 | 1 | 81.7% |
| OTHER | 2 | ₱21.8M | 72.1 | 1 | 100.0% |
| Bridges | 1 | ₱38.6M | 58.4 | 1 | 0.8% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24JK0002CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BARANGAY TALISAYAN (PACKAGE 2), ZAMBOANGA CITY | Region IX | Zamboanga City 1st DEO | Completed | ₱19.2M | 100% | High risk85 | Flagged0.023 |
| 24JA0011FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF FLOOD CONTROL STRUCTURE, TUMAGA RIVER (PASONANCA SECTION), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱131.2M | 93% | High risk75 | —-0.012 |
| 22J00091CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SAAZ RIVER, SAN RAMON BRIDGE 1 ALONG ZAMBOANGA CITY-LABUAN-LIMPAPA ROAD (PCA SECTION), ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱100.3M | 81% | High risk73 | Flagged0.002 |
| 20J00158CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION/EXTENSION OF FLOOD CONTROL AT SAAZ RIVER, SAN RAMON, ZAMBOANGA CITY | Region IX | Region IX | Completed | ₱111.1M | 100% | High risk73 | —-0.048 |
| 24J00098REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS -TERTIARY ROADS UMUS MATAHA - LUPA - PULA ROAD CHAINAGE 5000 - CHAINAGE 9000 | Region IX | Region IX | On-Going | ₱120.5M | 82% | High risk72 | —-0.012 |
| 21J00043CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SAAZ RIVER ALONG SAN RAMON BR. 2 ALONG ZAMBOANGA CITY-LABUAN-LIMPAPA SECONDARY ROAD, TALISAYAN, ZAMBOANGA CITY | Region IX | Region IX | Completed | ₱89.1M | 100% | High risk64 | —-0.056 |
| 22JA0010REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - ZAMBOANGA CITY-LABUAN-LIMPAPA RD - K1973+940 - K1974+030, K1973 218.74 - K1974+535 - K1974+580.30, K1974+740 - K1974+784.13 | Region IX | Zamboanga City 2nd DEO | Completed | ₱52.3M | 100% | High risk63 | —-0.075 |
| 24JA0141CONCRETING OF BRGY. PATALON FMR, BRGY. PATALON, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱29.4M | 64% | High risk60 | Flagged0.015 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24JK0002CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BARANGAY TALISAYAN (PACKAGE 2), ZAMBOANGA CITY | Region IX | Zamboanga City 1st DEO | Completed | ₱19.2M | 100% | High risk85 | Flagged0.023 |
| 24J00099REPLACEMENT OF PERMANENT WEAK BRIDGES - SUANG KAGANG BR. (B00003TW) ALONG BONGAO - PAHUT - SANGA-SANGA NATIONAL ROAD, BONGAO, TAWI-TAWI | Region IX | Region IX | On-Going | ₱38.6M | 1% | Medium risk58 | Flagged0.021 |
| 24JA0141CONCRETING OF BRGY. PATALON FMR, BRGY. PATALON, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱29.4M | 64% | High risk60 | Flagged0.015 |
| 22J00091CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SAAZ RIVER, SAN RAMON BRIDGE 1 ALONG ZAMBOANGA CITY-LABUAN-LIMPAPA ROAD (PCA SECTION), ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱100.3M | 81% | High risk73 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24JK0002CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BARANGAY TALISAYAN (PACKAGE 2), ZAMBOANGA CITY | Region IX | Zamboanga City 1st DEO | Completed | ₱19.2M | 100% | High risk85 | Flagged0.023 |
| 2 | 24JA0011FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF FLOOD CONTROL STRUCTURE, TUMAGA RIVER (PASONANCA SECTION), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱131.2M | 93% | High risk75 | —-0.012 |
| 3 | 22J00091CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SAAZ RIVER, SAN RAMON BRIDGE 1 ALONG ZAMBOANGA CITY-LABUAN-LIMPAPA ROAD (PCA SECTION), ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱100.3M | 81% | High risk73 | Flagged0.002 |
| 4 | 20J00158CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION/EXTENSION OF FLOOD CONTROL AT SAAZ RIVER, SAN RAMON, ZAMBOANGA CITY | Region IX | Region IX | Completed | ₱111.1M | 100% | High risk73 | —-0.048 |
| 5 | 24J00098REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS -TERTIARY ROADS UMUS MATAHA - LUPA - PULA ROAD CHAINAGE 5000 - CHAINAGE 9000 | Region IX | Region IX | On-Going | ₱120.5M | 82% | High risk72 | —-0.012 |
| 6 | 21J00043CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SAAZ RIVER ALONG SAN RAMON BR. 2 ALONG ZAMBOANGA CITY-LABUAN-LIMPAPA SECONDARY ROAD, TALISAYAN, ZAMBOANGA CITY | Region IX | Region IX | Completed | ₱89.1M | 100% | High risk64 | —-0.056 |
| 7 | 22JA0010REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - ZAMBOANGA CITY-LABUAN-LIMPAPA RD - K1973+940 - K1974+030, K1973 218.74 - K1974+535 - K1974+580.30, K1974+740 - K1974+784.13 | Region IX | Zamboanga City 2nd DEO | Completed | ₱52.3M | 100% | High risk63 | —-0.075 |
| 8 | 24JA0141CONCRETING OF BRGY. PATALON FMR, BRGY. PATALON, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱29.4M | 64% | High risk60 | Flagged0.015 |
| 9 | 25JK0033CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM - CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM | Region IX | Zamboanga City 1st DEO | On-Going | ₱2.5M | 100% | Medium risk59 | —-0.001 |
| 10 | 24J00099REPLACEMENT OF PERMANENT WEAK BRIDGES - SUANG KAGANG BR. (B00003TW) ALONG BONGAO - PAHUT - SANGA-SANGA NATIONAL ROAD, BONGAO, TAWI-TAWI | Region IX | Region IX | On-Going | ₱38.6M | 1% | Medium risk58 | Flagged0.021 |