375 projects on file, including joint ventures this contractor is part of.
Total projects
375
Total budget
₱12.4B
Average progress
98.7%
Completion rate
95.2%
Average risk score
38.3
Medium risk on average, out of 100
Flagged as unusual
7
1.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 256 | ₱8.1B | 34.7 | 3 | 99.5% |
| Region I | 80 | ₱2.1B | 44.7 | 2 | 98.5% |
| Region II | 36 | ₱2B | 49.8 | 1 | 95.8% |
| Region XII | 2 | ₱192M | 45.5 | 1 | 59.3% |
| Region VI | 1 | ₱32.4M | 46.3 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 140 | ₱7.3B | 46.2 | 3 | 98.8% |
| Roads | 117 | ₱2.4B | 30.9 | 0 | 98.9% |
| Buildings and Facilities | 111 | ₱2.3B | 34.5 | 1 | 98.9% |
| OTHER | 4 | ₱201.9M | 64.4 | 1 | 85.5% |
| GAA 2025 SSP | 2 | ₱193M | 95.4 | 2 | 95.6% |
| Bridges | 1 | ₱2.9M | 27.1 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CE0194CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ILOG BALIWAG RIVER, BARANGAY GABALDON, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | On-Going | ₱96.5M | 95% | High risk95 | Flagged0.006 |
| 25CE0193CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ILOG BALIWAG RIVER, BARANGAY CATALANACAN, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | On-Going | ₱96.5M | 96% | High risk95 | Flagged0.005 |
| 24CF0136SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD WITH DRAINAGE ALONG JAEN - SAN ANTONIO ROAD, JAEN, NUEVA EC | Region III | Nueva Ecija 2nd DEO | On-Going | ₱96M | 42% | High risk89 | Flagged0.059 |
| 25BJ0010OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF BAGUMBAYAN FLOOD CONTROL STRUCTURE ALONG BENAY RIVER, BARANGAY BAGUMBAYAN, | Region II | Nueva Vizcaya 2nd DEO | On-Going | ₱102.1M | 50% | High risk78 | Flagged0.005 |
| 17CE0157REHABILITATION OF FLOOD CONTROL ALONG BALIWAG RIVER, BRGY. MAPANGPANG, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱81.3M | 100% | High risk72 | —-0.052 |
| 17CE0153CONSTRUCTION/REHABILITATION OF AGUPALO ESTE SLOPE PROTECTION, BRGY. AGUPALO ESTE, LUPAO, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱58.6M | 100% | High risk72 | —-0.059 |
| 17CE0130CONSTRUCTION OF ONE (1) EVACUATION CENTER, BRGY. SAMPALOC, TALAVERA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱34.7M | 100% | High risk70 | —-0.067 |
| 21CF0144CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM - TIKAS) CONSTRUCTION OF ADMINISTRATION BUILDING AT SPECIAL FORCES REGIMENT (AIRBORNE), PHILIPPINE ARMY, F | Region III | Nueva Ecija 2nd DEO | Completed | ₱24.3M | 100% | High risk70 | —-0.071 |
| 21CF0185CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING IN BARANGAY BAGTING, GABALDON, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱4.9M | 100% | High risk70 | —-0.069 |
| 25CK0118REHABILITATION OF ROAD AT BARANGAY SAN ROQUE, LA PAZ, TARLAC | Region III | Tarlac 2nd DEO | On-Going | ₱49M | 100% | High risk70 | —-0.044 |
| 21CF0146CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM - TIKAS) CONSTRUCTION OF 2ND ADA BATTERY BASING FACILITIES, PHILIPPINE ARMY, FORT RAMON MAGSAYSAY, PALAYAN | Region III | Nueva Ecija 2nd DEO | Completed | ₱17.6M | 100% | High risk70 | —-0.072 |
| 21CF0149CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM - TIKAS) CONSTRUCTION OF MOBILE STRUCTURES FOR 2ND 155MM SELF- PROPELLED BATTERY FACILITY, FMNE, NUEVA ECI | Region III | Nueva Ecija 2nd DEO | Completed | ₱11.7M | 100% | High risk70 | —-0.073 |
| 20CF0057REHABILITATION OF PAMPANGA RIVER FLOOD CONTROL, BRGY. TABUATING, SAN LEONARDO, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱46.8M | 100% | High risk67 | —-0.062 |
| 16CE0163REPAIR/REHABILITATION OF TALAVERA RIVER, ALIAGA SECTION, SAN EUSTACIO, ALIAGA, NUEVA ECIJA, 1ST LD | Region III | Nueva Ecija 1st DEO | Completed | ₱4.8M | 100% | High risk67 | —-0.062 |
| 17CN0070CONCRETING/IMPROVEMENT OF ROAD, BRGY. TANAWAN, DINGALAN, AURORA | Region III | Aurora DEO | Completed | ₱9.9M | 100% | High risk66 | —-0.039 |
| 17CN0051CONCRETING OF BRGY. UMIRAY ROAD DINGALAN (INFRONT OF UMIRAY NATIONAL HIGH SCHOOL), DINGALAN, AURORA | Region III | Aurora DEO | Completed | ₱9.9M | 100% | High risk66 | —-0.042 |
| 17CN0065CONCRETING OF POBLACION ROAD DINGALAN (MAGSAYSAY ST.), DINGALAN, AURORA | Region III | Aurora DEO | Completed | ₱5M | 100% | High risk66 | —-0.068 |
| 16CE0225REHABILITATION/IMPROVEMENT OF BALIWAG RIVER CONTROL, MAPANGPANG, STA. 8+193.60-STA. 9+308.70, LUPAO, | Region III | Nueva Ecija 1st DEO | Completed | ₱16.2M | 100% | High risk66 | —-0.063 |
| 20CE0184CONCRETING OF TALUGTUG-UMINGAN ROAD, TALUGTUG, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱24.7M | 100% | High risk66 | —-0.067 |
| 24CE0360REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG TALAVERA RIVER, BARANGAY VILLA VINIEGAS, LLANERA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱95.5M | 100% | High risk65 | —-0.012 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24CF0136SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD WITH DRAINAGE ALONG JAEN - SAN ANTONIO ROAD, JAEN, NUEVA EC | Region III | Nueva Ecija 2nd DEO | On-Going | ₱96M | 42% | High risk89 | Flagged0.059 |
| 24M00226CONSTRUCTION OF SPECIAL CARE COMPLEX AT DR. JORGE P. ROYECA CITY HOSPITAL (PHASE 1), BARANGAY LAGAO, GENERAL SANTOS CITY, SOUTH COTABATO | Region XII | Region XII | On-Going | ₱95.5M | 19% | Medium risk46 | Flagged0.024 |
| 17AI0033CONSTN/MAINT OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS-AGNO RIVER BASIN & ALLIED RIVERS FLOO | Region I | Pangasinan 3rd DEO | Completed | ₱47.6M | 100% | High risk63 | Flagged0.012 |
| 25CE0194CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ILOG BALIWAG RIVER, BARANGAY GABALDON, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | On-Going | ₱96.5M | 95% | High risk95 | Flagged0.006 |
| 25CE0193CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ILOG BALIWAG RIVER, BARANGAY CATALANACAN, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | On-Going | ₱96.5M | 96% | High risk95 | Flagged0.005 |
| 25BJ0010OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF BAGUMBAYAN FLOOD CONTROL STRUCTURE ALONG BENAY RIVER, BARANGAY BAGUMBAYAN, | Region II | Nueva Vizcaya 2nd DEO | On-Going | ₱102.1M | 50% | High risk78 | Flagged0.005 |
| 17AI0038REPAIR/REHAB OF RIVER BANK RIVER CTRL PROJ, BRGY. AGNO C, TAYUG, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱7.2M | 100% | Medium risk56 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 24CE0027REHABILITATION OF DIKE ALONG TALAVERA RIVER, BARANGAY SAN EUSTACIO TO LA PURISIMA, ALIAGA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱95.5M | 100% | Medium risk56 | —-0.079 |
| 52 | 25CE0040CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TALAVERA RIVER, BARANGAY SIBUT, SAN JOSE CITY, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱95.5M | 100% | Medium risk56 | —-0.077 |
| 53 | 24CE0018REHABILITATION OF DIKE ALONG TALAVERA RIVER, BARANGAY SAN ANDRES II, QUEZON, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱95.5M | 100% | Medium risk56 | —-0.078 |
| 54 | 24CE0017REHABILITATION OF DIKE ALONG TALAVERA RIVER, BARANGAY SAN ALEJANDRO, QUEZON, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱95.5M | 100% | Medium risk56 | —-0.078 |
| 55 | 24CE0015REHABILITATION OF DIKE ALONG TALAVERA RIVER, BARANGAY DOLORES, SANTO DOMINGO, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱95.5M | 100% | Medium risk56 | —-0.078 |
| 56 | 24CE0026REHABILITATION OF DIKE ALONG TALAVERA RIVER, BARANGAYS SAN CARLOS TO BIBICLAT, ALIAGA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱95.5M | 100% | Medium risk56 | —-0.078 |
| 57 | 23CE0134IMPROVEMENT OF RIVER CHANNEL ALONG TALAVERA RIVER (BRGY. CABUBULAONAN), TALAVERA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱99M | 100% | Medium risk56 | —-0.077 |
| 58 | 23CK0064REHABILITATION OF EXISTING DIKE ALONG RIO CHICO RIVER (MACALONG SECTION, RIGHT BANK), PACKAGE 1, LA PAZ, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱96.5M | 100% | Medium risk56 | —-0.080 |
| 59 | 23CE0042CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG LABONG RIVER, BRGY. POBLACION SUR, LICAB, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱96.5M | 100% | Medium risk55 | —-0.077 |
| 60 | 23CE0031CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LABONG RIVER, BARANGAY VILLAROSA, (PHASE 6), LICAB, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱96.5M | 100% | Medium risk55 | —-0.078 |
| 61 | 23CE0082REHABILITATION OF DIKE ALONG TALAVERA RIVER, BRGY. POBLACION SUR, TALAVERA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱99M | 100% | Medium risk55 | —-0.076 |
| 62 | 22CE0121CONSTRUCTION OF SLOPE PROTECTION ALONG TALAVERA RIVER, BRGY. SAN JOSE, LICAB, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱96.5M | 100% | Medium risk55 | —-0.079 |
| 63 | 23CE0053REHABILITATION OF DIKE ALONG TALAVERA RIVER, BRGY. SAN JOSE TO BRGY. STA. MARIA, LICAB, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱96.5M | 100% | Medium risk55 | —-0.080 |
| 64 | 23CE0052REHABILITATION OF DIKE ALONG TALAVERA RIVER, BRGY. SAN AGUSTIN, STO. DOMINGO, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱96.5M | 100% | Medium risk55 | —-0.078 |
| 65 | 23CE0041REHABILITATION OF DIKE ALONG TALAVERA RIVER, BRGY. CONCEPCION, STO. DOMINGO, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱96.5M | 100% | Medium risk55 | —-0.078 |
| 66 | 24BJ0016NETWORK DEVELOPMENT-ROAD WIDENING-SECONDARY ROADS, NUEVA VIZCAYA-BENGUET ROAD-K0239+671-K0242+000, ARITAO, NUEVA VIZCAYA | Region II | Nueva Vizcaya 2nd DEO | Completed | ₱92.2M | 100% | Medium risk55 | —-0.070 |
| 67 | 23CE0038REHABILITATION OF DIKE ALONG TALAVERA RIVER, BRGY. PANTOC TO BRGY. BIBICLAT, ALIAGA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱96.5M | 100% | Medium risk55 | —-0.079 |
| 68 | 23CE0037REHABILITATION OF DIKE ALONG TALAVERA RIVER, BRGY. LAPURISIMA TO BRGY. PANTOC, ALIAGA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱96.5M | 100% | Medium risk55 | —-0.079 |
| 69 | 21AI0144CONSTRUCTION OF MULTI-PURPOSE BUILDING, CARMAY EAST, ROSALES PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱38.4M | 100% | Medium risk54 | —-0.081 |
| 70 | 21AI0149CONSTRUCTION OF SOCIAL WELFARE, MULTI-PURPOSE BUILDING, ROSALES, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱29.7M | 100% | Medium risk54 | —-0.078 |
| 71 | 20AI0083CONSTRUCTION OF MULTI-PURPOSE BUILDING, ZONE 1, ROSALES, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱4.8M | 100% | Medium risk54 | —-0.089 |
| 72 | 19A00135STRUCTURAL IMPROVEMENT OF PUBLIC BUILDINGS AND CONSTRUCTION OF EVACUATION CENTERS - REGION I, CONSTRUCTION OF EVACUATION CENTERS - REGION I, BRGY. LAUREN, UMINGAN, PANGASINAN | Region I | Region I | Completed | ₱34.2M | 100% | Medium risk53 | —-0.070 |
| 73 | 23AH0147CLUSTER NO. VIII - BASIC INFRASTRUCTURE PROGRAM - 1. CONSTRUCTION OF MULTI-PURPOSE BUILDING, MANGATAREM, PANGASINAN; 2. CONSTRUCTION OF MULTI-PURPOSE BUILDING (GYM), MANGATAREM, PANGASINAN; 3. CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), TORRE | Region I | Pangasinan 2nd DEO | Completed | ₱28.2M | 100% | Medium risk53 | —-0.079 |
| 74 | 20AI0153CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. BANTOG, ASINGAN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱14.4M | 100% | Medium risk53 | —-0.082 |
| 75 | 22A00091CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, URDANETA BYPASS ROAD, PANGASINAN | Region I | Region I | Completed | ₱67.1M | 100% | Medium risk53 | —-0.083 |