Opening the dossier…
Opening the dossier…
Contractor dossier
375 projects on file, including joint ventures this contractor is part of.
Total projects
375
Total budget
₱12.4B
Average progress
98.7%
Completion rate
95.2%
Average risk score
38.3
Medium risk on average, out of 100
Flagged as unusual
7
1.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 256 | ₱8.1B | 34.7 | 3 | 99.5% |
| Region I | 80 | ₱2.1B | 44.7 | 2 | 98.5% |
| Region II | 36 | ₱2B | 49.8 | 1 | 95.8% |
| Region XII | 2 | ₱192M | 45.5 | 1 | 59.3% |
| Region VI | 1 | ₱32.4M | 46.3 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 140 | ₱7.3B | 46.2 | 3 | 98.8% |
| Roads | 117 | ₱2.4B | 30.9 | 0 | 98.9% |
| Buildings and Facilities | 111 | ₱2.3B | 34.5 | 1 | 98.9% |
| OTHER | 4 | ₱201.9M | 64.4 | 1 | 85.5% |
| GAA 2025 SSP | 2 | ₱193M | 95.4 | 2 | 95.6% |
| Bridges | 1 | ₱2.9M | 27.1 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CE0194CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ILOG BALIWAG RIVER, BARANGAY GABALDON, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | On-Going | ₱96.5M | 95% | High risk95 | Flagged0.006 |
| 25CE0193CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ILOG BALIWAG RIVER, BARANGAY CATALANACAN, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | On-Going | ₱96.5M | 96% | High risk95 | Flagged0.005 |
| 24CF0136SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD WITH DRAINAGE ALONG JAEN - SAN ANTONIO ROAD, JAEN, NUEVA EC | Region III | Nueva Ecija 2nd DEO | On-Going | ₱96M | 42% | High risk89 | Flagged0.059 |
| 25BJ0010OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF BAGUMBAYAN FLOOD CONTROL STRUCTURE ALONG BENAY RIVER, BARANGAY BAGUMBAYAN, | Region II | Nueva Vizcaya 2nd DEO | On-Going | ₱102.1M | 50% | High risk78 | Flagged0.005 |
| 17CE0157REHABILITATION OF FLOOD CONTROL ALONG BALIWAG RIVER, BRGY. MAPANGPANG, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱81.3M | 100% | High risk72 | —-0.052 |
| 17CE0153CONSTRUCTION/REHABILITATION OF AGUPALO ESTE SLOPE PROTECTION, BRGY. AGUPALO ESTE, LUPAO, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱58.6M | 100% | High risk72 | —-0.059 |
| 17CE0130CONSTRUCTION OF ONE (1) EVACUATION CENTER, BRGY. SAMPALOC, TALAVERA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱34.7M | 100% | High risk70 | —-0.067 |
| 21CF0144CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM - TIKAS) CONSTRUCTION OF ADMINISTRATION BUILDING AT SPECIAL FORCES REGIMENT (AIRBORNE), PHILIPPINE ARMY, F | Region III | Nueva Ecija 2nd DEO | Completed | ₱24.3M | 100% | High risk70 | —-0.071 |
| 21CF0185CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING IN BARANGAY BAGTING, GABALDON, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱4.9M | 100% | High risk70 | —-0.069 |
| 25CK0118REHABILITATION OF ROAD AT BARANGAY SAN ROQUE, LA PAZ, TARLAC | Region III | Tarlac 2nd DEO | On-Going | ₱49M | 100% | High risk70 | —-0.044 |
| 21CF0146CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM - TIKAS) CONSTRUCTION OF 2ND ADA BATTERY BASING FACILITIES, PHILIPPINE ARMY, FORT RAMON MAGSAYSAY, PALAYAN | Region III | Nueva Ecija 2nd DEO | Completed | ₱17.6M | 100% | High risk70 | —-0.072 |
| 21CF0149CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM - TIKAS) CONSTRUCTION OF MOBILE STRUCTURES FOR 2ND 155MM SELF- PROPELLED BATTERY FACILITY, FMNE, NUEVA ECI | Region III | Nueva Ecija 2nd DEO | Completed | ₱11.7M | 100% | High risk70 | —-0.073 |
| 20CF0057REHABILITATION OF PAMPANGA RIVER FLOOD CONTROL, BRGY. TABUATING, SAN LEONARDO, NUEVA ECIJA | Region III | Nueva Ecija 2nd DEO | Completed | ₱46.8M | 100% | High risk67 | —-0.062 |
| 16CE0163REPAIR/REHABILITATION OF TALAVERA RIVER, ALIAGA SECTION, SAN EUSTACIO, ALIAGA, NUEVA ECIJA, 1ST LD | Region III | Nueva Ecija 1st DEO | Completed | ₱4.8M | 100% | High risk67 | —-0.062 |
| 17CN0070CONCRETING/IMPROVEMENT OF ROAD, BRGY. TANAWAN, DINGALAN, AURORA | Region III | Aurora DEO | Completed | ₱9.9M | 100% | High risk66 | —-0.039 |
| 17CN0051CONCRETING OF BRGY. UMIRAY ROAD DINGALAN (INFRONT OF UMIRAY NATIONAL HIGH SCHOOL), DINGALAN, AURORA | Region III | Aurora DEO | Completed | ₱9.9M | 100% | High risk66 | —-0.042 |
| 17CN0065CONCRETING OF POBLACION ROAD DINGALAN (MAGSAYSAY ST.), DINGALAN, AURORA | Region III | Aurora DEO | Completed | ₱5M | 100% | High risk66 | —-0.068 |
| 16CE0225REHABILITATION/IMPROVEMENT OF BALIWAG RIVER CONTROL, MAPANGPANG, STA. 8+193.60-STA. 9+308.70, LUPAO, | Region III | Nueva Ecija 1st DEO | Completed | ₱16.2M | 100% | High risk66 | —-0.063 |
| 20CE0184CONCRETING OF TALUGTUG-UMINGAN ROAD, TALUGTUG, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱24.7M | 100% | High risk66 | —-0.067 |
| 24CE0360REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG TALAVERA RIVER, BARANGAY VILLA VINIEGAS, LLANERA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱95.5M | 100% | High risk65 | —-0.012 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24CF0136SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD WITH DRAINAGE ALONG JAEN - SAN ANTONIO ROAD, JAEN, NUEVA EC | Region III | Nueva Ecija 2nd DEO | On-Going | ₱96M | 42% | High risk89 | Flagged0.059 |
| 24M00226CONSTRUCTION OF SPECIAL CARE COMPLEX AT DR. JORGE P. ROYECA CITY HOSPITAL (PHASE 1), BARANGAY LAGAO, GENERAL SANTOS CITY, SOUTH COTABATO | Region XII | Region XII | On-Going | ₱95.5M | 19% | Medium risk46 | Flagged0.024 |
| 17AI0033CONSTN/MAINT OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS-AGNO RIVER BASIN & ALLIED RIVERS FLOO | Region I | Pangasinan 3rd DEO | Completed | ₱47.6M | 100% | High risk63 | Flagged0.012 |
| 25CE0194CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ILOG BALIWAG RIVER, BARANGAY GABALDON, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | On-Going | ₱96.5M | 95% | High risk95 | Flagged0.006 |
| 25CE0193CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ILOG BALIWAG RIVER, BARANGAY CATALANACAN, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | On-Going | ₱96.5M | 96% | High risk95 | Flagged0.005 |
| 25BJ0010OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF BAGUMBAYAN FLOOD CONTROL STRUCTURE ALONG BENAY RIVER, BARANGAY BAGUMBAYAN, | Region II | Nueva Vizcaya 2nd DEO | On-Going | ₱102.1M | 50% | High risk78 | Flagged0.005 |
| 17AI0038REPAIR/REHAB OF RIVER BANK RIVER CTRL PROJ, BRGY. AGNO C, TAYUG, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱7.2M | 100% | Medium risk56 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 126 | 22BJ0043BASIC INFRASTRUCTURE PROGRAM-FLOOD MITIGATION STRUCTURE PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES CONSTRUCTION OF CUTAR FLOOD CONTROL STRUCTURE ALONG STA. FE RIVER, CUTAR, ARITAO, NUEVA VIZCAYA | Region II | Nueva Vizcaya 2nd DEO | Completed | ₱48.3M | 100% | Medium risk46 | —-0.068 |
| 127 | 23BJ0001CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT LAMO SECTION, DUPAX DEL NORTE, NUEVA VIZCAYA | Region II | Nueva Vizcaya 2nd DEO | Completed | ₱48.2M | 100% | Medium risk46 | —-0.069 |
| 128 | 18GA0038CONST. OF FLOOD CONTROL STRUCTURE, ALONG AKLAN RIVER, BRGY. TIGAYON, KALIBO, AKLAN | Region VI | Aklan DEO | Completed | ₱32.4M | 100% | Medium risk46 | —-0.063 |
| 129 | 24M00226CONSTRUCTION OF SPECIAL CARE COMPLEX AT DR. JORGE P. ROYECA CITY HOSPITAL (PHASE 1), BARANGAY LAGAO, GENERAL SANTOS CITY, SOUTH COTABATO | Region XII | Region XII | On-Going | ₱95.5M | 19% | Medium risk46 | Flagged0.024 |
| 130 | 19AI0346CONSTRUCTION OF THREE (3) STOREY SIX (6) CLASSROOM SCHOOL BUILDING, SAN ANTONIO NATIONAL HIGH SCHOOL, STO. TOMAS, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱17.1M | 100% | Medium risk46 | —-0.044 |
| 131 | 19AI0350CONSTRUCTION OF THREE (3) STOREY SIX (6) CLASSROOM SCHOOL BUILDING, SAN JOSE ELEMENTARY SCHOOL, STO. TOMAS, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱20M | 100% | Medium risk46 | —-0.042 |
| 132 | 19AI0145ASPHALT OVERLAY ALONG CARMEN JUNCTION-MANAT ROAD, KO 172+000 - KO 173+000; KO 174+000 - KO 174+300; | Region I | Pangasinan 3rd DEO | Completed | ₱21.3M | 100% | Medium risk46 | —-0.089 |
| 133 | 20AI0029CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGNO RIVER, BRGY. LAOAC (LEFT BANK), ALCALA, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱37.2M | 100% | Medium risk46 | —-0.073 |
| 134 | 20AI0071CONCRETING OF ROADS AT SAN NICOLAS, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱11.3M | 100% | Medium risk46 | —-0.092 |
| 135 | 19AI0026ASPHALT OVERLAY ALONG PANGASINAN-NUEVA ECIJA ROAD, KO 178+373 - KO 180+000, KO 182+000 - KO 182+960 | Region I | Pangasinan 3rd DEO | Completed | ₱23.2M | 100% | Medium risk46 | —-0.089 |
| 136 | 19AI0347CONSTRUCTION OF THREE (3) STOREY SIX (6) CLASSROOM SCHOOL BUILDING, MACAYO INTEGRATED SCHOOL, ALCALA, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱16.9M | 100% | Medium risk46 | —-0.045 |
| 137 | 20AI0024CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGALACAN AND ALLIED RIVERS, BRGY. BATAKIL-BOBONAN, POZORRUBIO, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱37.2M | 100% | Medium risk45 | —-0.070 |
| 138 | 20CE0211CONSTRUCTION OF 2STY6CL, HOMESTEAD I ES, TALAVERA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱21M | 100% | Medium risk45 | —-0.024 |
| 139 | 19AI0338CONSTRUCTION OF TWO (2) STOREY SIX (6) CLASSROOM SCHOOL BUILDING, VACANTE ELEMENTARY SCHOOL BINALONAN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱14.2M | 100% | Medium risk45 | —-0.046 |
| 140 | 20CE0212CONSTRUCTION OF 2STY8CL, MINABUYOK ES, TALAVERA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱23M | 100% | Medium risk45 | —-0.024 |
| 141 | 19CI0122NETWORK DEVELOPMENT-WIDENING-SECONDARY ROADS,ARAYAT-MAGALANG-MABALACAT ROAD,K0110+866-KO112+552-KO112+750,MABALACAT CITY | Region III | Pampanga 3rd DEO | Completed | ₱92.1M | 100% | Medium risk45 | —-0.090 |
| 142 | 23MH0020CONSTRUCTION OF RIVER BANK PROTECTION AT BARANGAY SANTA CLARA, KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱96.5M | 100% | Medium risk45 | —-0.062 |
| 143 | 18AI0350CONSTRUCTION OF TWO STOREY SIX CLASSROOM SCHOOL BUILDING SUGCONG E/S, POZORRUBIO, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱14.4M | 100% | Medium risk45 | —-0.046 |
| 144 | 23BJ0019ASSET PRESERVATION -REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGE PAVED ROADS -TERTIARY ROADS, ARITAO-QUIRINO ROAD - K0237+(-983) - K0237+112, ARITAO, NUEVA VIZCAYA | Region II | Nueva Vizcaya 2nd DEO | Completed | ₱35.8M | 100% | Medium risk44 | —-0.082 |
| 145 | 24BJ0036NETWORK DEVELOPMENT-ROAD WIDENING-SECONDARY ROADS, NUEVA VIZCAYA-BENGUET ROAD-K0242+000-K0243+000 ARITAO, NUEVA VIZCAYA | Region II | Nueva Vizcaya 2nd DEO | Completed | ₱38.5M | 100% | Medium risk44 | —-0.083 |
| 146 | 24BJ0032ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT-ROAD WIDENING-SECONDARY ROADS NUEVA VIZCAYA-BENGUET ROAD-K0245+000-K0246+000 BAAN, ARITAO, NUEVA VIZCAYA | Region II | Nueva Vizcaya 2nd DEO | Completed | ₱38.6M | 100% | Medium risk44 | —-0.083 |
| 147 | 23BJ0026ASSET PRESERVATION PROGRAM- REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGE PAVED ROADS-TERTIARY ROADS ARITAO-QUIRINO ROAD K0242+000-K0243+000 ARITAO, NUEVA VIZCAYA | Region II | Nueva Vizcaya 2nd DEO | Completed | ₱33.5M | 100% | Medium risk44 | —-0.082 |
| 148 | 23BJ0035ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE ALONG TERTIARY ROADS, ARITAO-QUIRINO K024+619-K0256+329, K0260+602-K0262+690 KASIBU, NUEVA VIZCAYA | Region II | Nueva Vizcaya 2nd DEO | Completed | ₱37.8M | 100% | Medium risk44 | —-0.084 |
| 149 | 22BJ0044BASIC INFRASTRUCTURE PROGRAM (BIP): FLOOD CONTROL MITIGATION STRUCTURES PROTECTING BASIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURES ALONG SANTA FE RIVER, BONE SOUTH SECTION ARITAO, NUEVA VIZCAYA | Region II | Nueva Vizcaya 2nd DEO | Completed | ₱34.1M | 100% | Medium risk44 | —-0.069 |
| 150 | 23BJ0011ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE ALONG PRIMARY ROADS, DAANG MAHARLIKA (LZ)-K0233+336-K0235+020, K0236+190-K0237+260, ARITAO, NUEVA VIZCAYA | Region II | Nueva Vizcaya 2nd DEO | Completed | ₱46.3M | 100% | Medium risk44 | —-0.078 |