Contractor dossier
14 projects on file, including joint ventures this contractor is part of.
Total projects
14
Total budget
₱445.2M
Average progress
55.8%
Completion rate
0.0%
Below 70%
Average risk score
51.3
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 14 | ₱445.2M | 51.3 | 0 | 55.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 10 | ₱230.6M | 49.6 | 0 | 50.0% |
| Flood Control and Drainage | 3 | ₱200M | 58.6 | 0 | 75.1% |
| Roads | 1 | ₱14.6M | 46.7 | 0 | 55.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DI0035REHABILITATION OF BANK STRUCTURE ALONG BINAN RIVER, PHASE 2, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱93.8M | 63% | High risk65 | —-0.031 |
| 24D00252CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG NEAR BINAN RIVER, BINAN CITY, LAGUNA | Region IV-A | Region IV-A | On-Going | ₱96.5M | 72% | High risk64 | —-0.032 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25DI0035REHABILITATION OF BANK STRUCTURE ALONG BINAN RIVER, PHASE 2, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱93.8M | 63% | High risk65 | —-0.031 |
| 2 | 24D00252CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG NEAR BINAN RIVER, BINAN CITY, LAGUNA | Region IV-A | Region IV-A | On-Going | ₱96.5M | 72% | High risk64 | —-0.032 |
| 3 | 24DI0163CONSTRUCTION OF MULTI-PURPOSE BUILDING (SCHOOL BUILDING), MALABAN ELEMENTARY SCHOOL (MAIN), BARANGAY MALABAN, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱48.3M | 0% | Medium risk56 | —-0.026 |
| 4 | 24DI0161CONSTRUCTION OF MULTI-PURPOSE BUILDING (BINAN SPED CENTER), BARANGAY STO. DOMINGO BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱29M | 42% | Medium risk53 | —-0.045 |
| 5 | 24DI0206CONSTRUCTION OF DIALYSIS AND CHEMOTHERAPY CENTER, BGY. CANLALAY, BINAN, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱29.1M | 36% | Medium risk53 | —-0.046 |
| 6 | 24DI0162CONSTRUCTION OF MULTI-PURPOSE BUILDING (PWD), REHABILITATION AND LIVELIHOOD CENTER, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱29.1M | 85% | Medium risk53 | —-0.059 |
| 7 | 25DI0133CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY SAN JOSE, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱19.4M | 0% | Medium risk51 | —-0.033 |
| 8 | 25DI0140CONSTRUCTION OF MULTI-PURPOSE BUILDING AND COVERED COURT SAN ISIDRO SUBDIVISION BARANGAY DELA PAZ, BINAN CITY | Region IV-A | Laguna 2nd DEO | On-Going | ₱19.4M | 2% | Medium risk51 | —-0.033 |
| 9 | 24DI0160CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY DELA PAZ, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱19.4M | 95% | Medium risk51 | —-0.063 |
| 10 | 24DI0154CONSTRUCTION OF MULTI-PURPOSE BUILDING (SPORTS CENTER), BARANGAY SAN FRANCISCO, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱19.4M | 100% | Medium risk51 | —-0.065 |
| 11 | 25DI0121CONSTRUCTION OF MULTI-PURPOSE BUILDING MERCEDES HOMES II BARANGAY STO. TOMAS, BINAN CITY | Region IV-A | Laguna 2nd DEO | On-Going | ₱14.6M | 39% | Medium risk50 | —-0.049 |
| 12 | 25DI0083REHABILITATION OF DRAINAGE, BARANGAY PLATERO, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱9.7M | 90% | Medium risk47 | —-0.052 |
| 13 | 25DI0076CONSTRUCTION OF ROAD, BARANGAY SAN ANTONIO, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱14.6M | 55% | Medium risk47 | —-0.064 |
| 14 | 24DI0146CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), SOUTHVILLE 5A (PHASE 3A), BARANGAY LANGKIWA, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱2.9M | 100% | Low risk26 | —-0.066 |