Contractor dossier
11 projects on file, including joint ventures this contractor is part of.
Total projects
11
Total budget
₱401.4M
Average progress
90.2%
Completion rate
63.6%
Below 70%
Average risk score
47.4
Medium risk on average, out of 100
Flagged as unusual
2
18.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 4 | ₱21.1M | 37.1 | 0 | 100.0% |
| National Capital Region | 3 | ₱17.7M | 46.0 | 0 | 100.0% |
| Region XI | 2 | ₱182.7M | 62.1 | 1 | 81.8% |
| Region VIII | 1 | ₱141.3M | 65.7 | 1 | 41.5% |
| Negros Island Region | 1 | ₱38.7M | 45.3 | 0 | 87.5% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 4 | ₱83.6M | 36.6 | 0 | 92.9% |
| OTHER | 3 | ₱160.3M | 67.7 | 1 | 93.2% |
| Bridges | 2 | ₱149.4M | 56.3 | 1 | 70.8% |
| Roads | 2 | ₱8.1M | 29.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24L00247CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (EARTHDIKE) ALONG MANGALCAL CREEK BOTH SIDES, CARMEN, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱144.1M | 80% | High risk80 | Flagged0.033 |
| 25I00117BRIDGE - WIDENING OF PERMANENT BRIDGES - DAGUITAN PARALLEL BR. ALONG MAHARLIKA HIGHWAY | Region VIII | Region VIII | On-Going | ₱141.3M | 42% | High risk66 | Flagged0.003 |
| 18CC0194ROAD CONCRETING BARANGAY TANAWAN, BUSTOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱8.1M | 100% | High risk62 | —-0.042 |
| 18CC0196ROAD CONCRETING OF BARANGAY BAGBAGUIN, PANDI, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱8.1M | 100% | High risk62 | —-0.042 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24L00247CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (EARTHDIKE) ALONG MANGALCAL CREEK BOTH SIDES, CARMEN, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱144.1M | 80% | High risk80 | Flagged0.033 |
| 25I00117BRIDGE - WIDENING OF PERMANENT BRIDGES - DAGUITAN PARALLEL BR. ALONG MAHARLIKA HIGHWAY | Region VIII | Region VIII | On-Going | ₱141.3M | 42% | High risk66 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24L00247CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (EARTHDIKE) ALONG MANGALCAL CREEK BOTH SIDES, CARMEN, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱144.1M | 80% | High risk80 | Flagged0.033 |
| 2 | 25I00117BRIDGE - WIDENING OF PERMANENT BRIDGES - DAGUITAN PARALLEL BR. ALONG MAHARLIKA HIGHWAY | Region VIII | Region VIII | On-Going | ₱141.3M | 42% | High risk66 | Flagged0.003 |
| 3 | 18CC0194ROAD CONCRETING BARANGAY TANAWAN, BUSTOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱8.1M | 100% | High risk62 | —-0.042 |
| 4 | 18CC0196ROAD CONCRETING OF BARANGAY BAGBAGUIN, PANDI, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱8.1M | 100% | High risk62 | —-0.042 |
| 5 | 18OD0184REHABILITATION OF ROADS WITH BRIDGE REPLACEMENT BRGY. 171, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱8.1M | 100% | Medium risk47 | —-0.061 |
| 6 | 18OE0029ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGSINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: DRAINAGE IMPROVEMENT ALONG TECSON ST., MANILA CITY STA. 0+000.00 TO STA. 0 | National Capital Region | North Manila DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.089 |
| 7 | 17OE0184LIP: CONCRETING WITH DRAINAGE IMPROVEMENT OF TAYUMAN ST., MANILA CITY 2ND LD MANILA CITY 2ND LEGISLATIVE DISTRICT | National Capital Region | North Manila DEO | Completed | ₱4.7M | 100% | Medium risk46 | —-0.067 |
| 8 | 25HJ0004ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DOMOLOG RIVER, BINDOY, NEGR | Negros Island Region | Negros Oriental 1st DEO | On-Going | ₱38.7M | 87% | Medium risk45 | —-0.037 |
| 9 | 24LF0121CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG LINGAYAO RIVER, MANAY, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | On-Going | ₱38.6M | 84% | Medium risk44 | —-0.017 |
| 10 | 18CC0243ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - BIGAA-PLARIDEL VIA BULACAN AND MALOLOS ROAD K0051+000 TO K0051+750 PLARIDEL, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱3.4M | 100% | Low risk14 | —-0.102 |
| 11 | 18CC0227CONSTRUCTION OF RIP RAP IN LOOK 1ST, CITY OF MALOLOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱1.5M | 100% | Low risk11 | —-0.090 |