Contractor dossier
5 projects on file, including joint ventures this contractor is part of.
Total projects
5
Total budget
₱28.8M
Average progress
89.8%
Completion rate
80.0%
Average risk score
41.0
Medium risk on average, out of 100
Flagged as unusual
1
20.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 5 | ₱28.8M | 41.0 | 1 | 89.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 4 | ₱22.6M | 28.0 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱6.2M | 92.7 | 1 | 49.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EG0040CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY APORAWAN, ABORLAN, PALAWAN | Region IV-B | Palawan 3rd DEO | On-Going | ₱6.2M | 49% | High risk93 | Flagged0.043 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EG0040CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY APORAWAN, ABORLAN, PALAWAN | Region IV-B | Palawan 3rd DEO | On-Going | ₱6.2M | 49% | High risk93 | Flagged0.043 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25EG0040CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY APORAWAN, ABORLAN, PALAWAN | Region IV-B | Palawan 3rd DEO | On-Going | ₱6.2M | 49% | High risk93 | Flagged0.043 |
| 2 | 22EE0068CONSTRUCTION OF EVACUATION CENTER BARANGAY POBLACION, ROXAS, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱9.9M | 100% | Medium risk37 | —-0.070 |
| 3 | 22EG0052CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY APURAWAN, MUNICIPALITY OF ABORLAN, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱4.9M | 100% | Medium risk33 | —-0.064 |
| 4 | 24EG0006CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SICSICAN, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱5.4M | 100% | Medium risk32 | —-0.067 |
| 5 | 23EE0117CONSTRUCTION OF 1-STY 1CL PEDRO BAQUIAO ELEMENTARY SCHOOL ROXAS, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱2.3M | 100% | Low risk10 | —-0.027 |