Opening the dossier…
Opening the dossier…
Contractor dossier
118 projects on file, including joint ventures this contractor is part of.
Total projects
118
Total budget
₱707.3M
Average progress
98.3%
Completion rate
98.3%
Average risk score
31.6
Medium risk on average, out of 100
Flagged as unusual
3
2.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Negros Island Region | 91 | ₱524.7M | 29.1 | 1 | 100.0% |
| Region VI | 27 | ₱182.5M | 39.7 | 2 | 92.6% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 39 | ₱134.3M | 20.3 | 0 | 100.0% |
| Bridges | 37 | ₱227.4M | 36.8 | 2 | 94.6% |
| Roads | 32 | ₱305.8M | 38.9 | 0 | 100.0% |
| Water Provision and Storage | 9 | ₱30.1M | 27.1 | 0 | 100.0% |
| OTHER | 1 | ₱9.7M | 84.4 | 1 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23GL0124CONSTRUCTION OF ROAD AT BRGY. HIMAYA, HINIGARAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱9.7M | 100% | High risk84 | Flagged0.008 |
| 24GL0002CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY ROBLES, LA CASTELLANA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱4.9M | 100% | High risk66 | —-0.059 |
| 17RC0025PREVENTIVE MAINTENANCE BASED ONPAVEMENTMANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT AND MANAGEMENT-4 (HDM-4) OF BACOLOD SOUTH ROAD, K0046+(-910)-K0046+(-045), K0049+830-K0050+090, K0058+275-K0058+500, K0060+000-K0060+389, K0063+303-K0063+747, K0071+042-K0071+6 | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱29.7M | 100% | High risk66 | —-0.060 |
| 17RD0015CONSTRUCTION OF ROAD, CANLAMAY TO MAGBALLO LOCAL ROAD, BRGY. CANLAMAY, ILOG, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱8.9M | 100% | High risk64 | —-0.059 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 20G00139CONSTRUCTION OF TIMPAS BRIDGE | Region VI | Region VI | On-Going | ₱12.8M | 0% | Medium risk47 | Flagged0.041 |
| 20G00134CONSTRUCTION OF FORI - BURIAS BRIDGE | Region VI | Region VI | On-Going | ₱13.2M | 0% | Medium risk47 | Flagged0.040 |
| 23GL0124CONSTRUCTION OF ROAD AT BRGY. HIMAYA, HINIGARAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱9.7M | 100% | High risk84 | Flagged0.008 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 23GL0007OFF-CARRIAGEWAY IMPROVEMENT: PAVING OF SHOULDERS - VALLEHERMOSO-CANLAON CITY-LA CASTELLANA RD - K0074 + 376 - K0075 + 569 | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱20M | 100% | Medium risk45 | —-0.091 |
| 27 | 20GL0008RECONSTRUCTION OF CONCRETE PAVEMENT ALONG SECONDARY ROAD - ON SPECIFIC LOCATIONS ALONG JCT BAGONAWA - LA CASTELLANA - ISABELA RD (S00178NR) K0070+368.40-K0070+850, K0076+785- K0076+860, K0078+834- K0079+417 | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱19.6M | 100% | Medium risk45 | —-0.091 |
| 28 | 19GL0065RECONSTRUCTION TO CONCRETE PAVEMENT - ACCESS ROAD LEADING TO AGUISAN PORT | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱15.5M | 100% | Medium risk45 | —-0.091 |
| 29 | 21GL0049RECONSTRUCTION TO CONCRETE PAVEMENT AT SPECIFIC LOCATIONS ALONG BACOLOD SOUTH RD (S00134NR) K0071+847-K0072+015,K0073+077-K0073+413 | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱14.3M | 100% | Medium risk45 | —-0.091 |
| 30 | 24GL0033CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY MARINA, BINALBAGAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱4.9M | 100% | Medium risk45 | —-0.086 |
| 31 | 21GM0027CONSTRUCTION OF CONCRETE ROAD - JCT. BACOLOD SOUTH ROAD LEADING TO DAAN BANWA (BIRD WATCHING AREA), BRGY. DAAN BANUA, KABANKALAN CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱21.6M | 100% | Medium risk44 | —-0.075 |
| 32 | 18RC0001PREVENTIVE MAINTENANCE BASED ON PAVEMENT SYSTEM HIGHWAY DEVELOPMENT AND MANAGEMENT -4(HDM-4) OF BACOLOD SOUTH ROAD, K0046+112.4 - K0046+162, K0046+188.9-K0046+247.7,K0046+291-K0046+533.7, K0046+550.1-K0046+813.7,K0046+942.4-K0046+961,K0059+021.50 - K0059 | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱9.9M | 100% | Medium risk44 | —-0.090 |
| 33 | 21GL0051RECONSTRUCTION TO CONCRETE PAVEMENT - AT SPECIFIC LOCATIONS ALONG BACOLOD SOUTH RD (S00134NR) K0058+500 - K0058+738.8, K0059+080.7 - K0059+116.8, K0070+446 - K0070+600.2, K0070+640.9 - K0070+721.9, K0070+812.2 - K0071 + 042 | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱12.3M | 100% | Medium risk44 | —-0.090 |
| 34 | 22GM0041CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, ABACA TO TAMBAD, BARANGAY ABACA, CAUAYAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱14.9M | 100% | Medium risk44 | —-0.090 |
| 35 | 19GF0010ROAD WIDENING- ILOILO-ANTIQUE ROAD (K0023+690 - K0023+786, K0023+814 - K0023+910, K0030+514 - K0030+531, K0030+547 - K0030+597, K0031+651 - K0031+747, K0031+770.80 - K0031+846.80), TIGBAUAN & GUIMBAL, ILOILO | Region VI | Iloilo 1st DEO | Completed | ₱12.5M | 100% | Medium risk44 | —-0.088 |
| 36 | 20GF0069CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - GUIMBAL - TUBUNGAN RD. (K0031+041 - K0031+519, K0033+254 - K0033+666, K0033+666 - K0034+079), GUIMBAL, ILOILO | Region VI | Iloilo 1st DEO | Completed | ₱11.4M | 100% | Medium risk44 | —-0.088 |
| 37 | 21GF0070CONSTRUCTION / IMPROVEMENT OF OTON MUNICIPAL LOCAL ROADS, OTON, ILOILO | Region VI | Iloilo 1st DEO | Completed | ₱5.9M | 100% | Medium risk44 | —-0.088 |
| 38 | 21GM0072CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD FROM NATIONAL ROAD TO PUROK CAMPILISAN, BRGY. ORINGAO, KABANKALAN CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱5.9M | 100% | Medium risk44 | —-0.091 |
| 39 | 21GM0028CONSTRUCTION OF CONCRETE ROAD - NRJ LEADING TO BALICAOCAO HIGHLAND RESORT, KABANKALAN CITY, NEGROS OCCIDENTAL, BRGY. ORONG, KABANKALAN CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱7M | 100% | Medium risk44 | —-0.092 |
| 40 | 24GM0020REHABILITATION OF PAVED ROAD - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG BACOLOD SOUTH RD - K0088+235 - K0088+304, KABANKALAN CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱5.9M | 100% | Medium risk44 | —-0.090 |
| 41 | 23GM0046CONSTRUCTION OF CONCRETE ROAD - CONCRETING OF ROAD, CROSSING MANAOLAN, BRGY IV, SIPALAY CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱9.7M | 100% | Medium risk44 | —-0.089 |
| 42 | 21GM0060CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF LOCAL ROAD, BARANGAY DELICIOSO, ILOG TO BARANGAY SALONG, KABANKALAN ROAD, NEGROS OCCIDENTAL, ILOG & KABANKALAN CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱5M | 100% | Medium risk44 | —-0.090 |
| 43 | 19GM0069CONSTRUCTION OF LOCAL ROAD - SITIO SAN RAMON, BRGY. MANALAD, ILOG, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱9.5M | 100% | Medium risk44 | —-0.091 |
| 44 | 23GM0062CONSTRUCTION OF MULTI-PURPOSE BUILDING - CONSTRUCTION OF MULTI-PURPOSE BUILDING (TABU PUBLIC MARKET), TABU, ILOG, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱9.9M | 100% | Medium risk44 | —-0.086 |
| 45 | 19GF0073CONSTRUCTION OF ONE-STOREY FOUR CLASSROOM SCHOOL BUILDING, BALBINO SERON ELEMENTARY SCHOOL, SAN JOAQUIN, ILOILO | Region VI | Iloilo 1st DEO | Completed | ₱9.7M | 100% | Medium risk43 | —-0.042 |
| 46 | 25GM0029CONSTRUCTION OF MULTI-PURPOSE BUILDING - CONSTRUCTION OF MULTI-PURPOSE BUILDING, AGRIPINO ALVAREZ ELEMENTARY SCHOOL, BARANGAY MAMBAROTO, SIPALAY CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱5M | 100% | Medium risk43 | —-0.085 |
| 47 | 17RC0049CONSTRUCTION RAIN WATER COLLECTION SYSTEM (RWCS), A. CAMALOBALO ELEMENTARY SCHOOL, B. ALEJANDRO SANTERO ELEMENTARY SCHOOL, C. CANDUMARAO ELEMENTARY SCHOOL, D. CARABALAN ELEMENTARY SCHOOL, E. SAN AGUSTIN ELEMENTARY SCHOOL, F. MAHALANG ELEMENTARY SCHOOL, G. | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱3.2M | 100% | Medium risk41 | —-0.030 |
| 48 | 18GL0087CONCRETING OF BRGY. CABADIANGAN FMRPHASE II, BRGY. CABADIANGAN, HIMAMAYLAN CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱5M | 100% | Medium risk39 | —-0.040 |
| 49 | 22GL0110CONSTRUCTION OF FARM-TO-MILL ROAD, BRGY. GUINPANAAN TO SO. KABAYABASAN, BRGY. MONTILLA, MOISES PADILLA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱5.2M | 100% | Medium risk39 | —-0.038 |
| 50 | 17RD0080CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS - RAINWATER C | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱3.2M | 100% | Medium risk39 | —-0.030 |