Opening the dossier…
Opening the dossier…
Contractor dossier
26 projects on file, including joint ventures this contractor is part of.
Total projects
26
Total budget
₱897M
Average progress
99.7%
Completion rate
84.6%
Average risk score
47.8
Medium risk on average, out of 100
Flagged as unusual
1
3.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Cordillera Administrative Region | 10 | ₱259.8M | 47.4 | 1 | 100.0% |
| Region IX | 8 | ₱385.9M | 57.8 | 0 | 98.9% |
| Region VII | 3 | ₱163.3M | 47.5 | 0 | 100.0% |
| National Capital Region | 3 | ₱84.2M | 46.9 | 0 | 100.0% |
| Region X | 2 | ₱3.8M | 12.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Water Provision and Storage | 15 | ₱552.3M | 44.5 | 0 | 100.0% |
| Flood Control and Drainage | 8 | ₱261.8M | 54.8 | 0 | 98.9% |
| OTHER | 1 | ₱34.3M | 77.8 | 1 | 100.0% |
| Roads | 1 | ₱46.8M | 49.1 | 0 | 100.0% |
| Buildings and Facilities | 1 | ₱1.9M | 11.4 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24PK0080CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) CONSTRUCTION / REHABILITATION OF WATER SUPPY / SEPTAGE AND SEWERAGE / RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM CONSTRUCTION OF WATER SUPPLY SYSTEMS - CONSTRUCTION OF WATER SUPPLY SYSTEM (LEVEL III), BALBAL | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱34.3M | 100% | High risk78 | Flagged0.003 |
| 17JA0030CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT PASONANCA-STA. MARIA-TUMAGA SECTION (INCLUDING RIGHT OF WAY), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱36M | 100% | High risk65 | —-0.038 |
| 17JA0021CONSTRUCTION OF FLOOD CONTROL AT MAASIN CREEK, (INCLUDING RIGHT OF WAY ACQUISITION), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱23.6M | 100% | High risk65 | —-0.036 |
| 22J00090CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT AYALA RIVER, BRGY. AYALA, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱56.2M | 91% | High risk62 | —-0.007 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24PK0080CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) CONSTRUCTION / REHABILITATION OF WATER SUPPY / SEPTAGE AND SEWERAGE / RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM CONSTRUCTION OF WATER SUPPLY SYSTEMS - CONSTRUCTION OF WATER SUPPLY SYSTEM (LEVEL III), BALBAL | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱34.3M | 100% | High risk78 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24PK0080CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) CONSTRUCTION / REHABILITATION OF WATER SUPPY / SEPTAGE AND SEWERAGE / RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM CONSTRUCTION OF WATER SUPPLY SYSTEMS - CONSTRUCTION OF WATER SUPPLY SYSTEM (LEVEL III), BALBAL | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱34.3M | 100% | High risk78 | Flagged0.003 |
| 2 | 17JA0030CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT PASONANCA-STA. MARIA-TUMAGA SECTION (INCLUDING RIGHT OF WAY), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱36M | 100% | High risk65 | —-0.038 |
| 3 | 17JA0021CONSTRUCTION OF FLOOD CONTROL AT MAASIN CREEK, (INCLUDING RIGHT OF WAY ACQUISITION), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱23.6M | 100% | High risk65 | —-0.036 |
| 4 | 22J00090CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT AYALA RIVER, BRGY. AYALA, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱56.2M | 91% | High risk62 | —-0.007 |
| 5 | 21JA0047CONSTRUCTION OF SHORELINE PROTECTION, SAN RAMON SECTION, TALISAYAN, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱42M | 100% | Medium risk55 | —-0.063 |
| 6 | 20JA0022CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SHORELINE PROTECTION AT TALISAYAN SECTION, TALISAYAN, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱34.3M | 100% | Medium risk55 | —-0.064 |
| 7 | 18JF0076CONSTRUCTION OF WATER SUPPLY PROJECT, SIAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱71.3M | 100% | Medium risk54 | —-0.031 |
| 8 | 18JF0077CONSTRUCTION OF WATER SUPPLY PROJECT, ROSELLER LIM, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱69.4M | 100% | Medium risk54 | —-0.024 |
| 9 | 22PL0061CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM-WATER SUPPLY - CONSTRUCTION OF LEVEL III WATER SUPPLY SYSTEM, TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱69.2M | 100% | Medium risk53 | —-0.039 |
| 10 | 18JF0075CONSTRUCTION OF WATER SUPPLY PROJECT, KABASALAN, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱53.2M | 100% | Medium risk52 | —-0.027 |
| 11 | 20HA0083CONSTRUCTION OF WATER SUPPLY SYSTEM IN BALILIHAN, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱81.9M | 100% | Medium risk51 | —-0.027 |
| 12 | 23PL0092CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, MUNICIPALITY PINUKPUK, PROVINCE OF KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱19.6M | 100% | Medium risk51 | —-0.008 |
| 13 | 25PL0111CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - RAINWATER COLLECTOR SYSTEM | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱2.6M | 100% | Medium risk50 | —-0.005 |
| 14 | 18OF0040ROAD IMPROVEMENT OF D. TUAZON ST., Q.C. | National Capital Region | Quezon City 1st DEO | Completed | ₱46.8M | 100% | Medium risk49 | —-0.094 |
| 15 | 22PL0062CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM-WATER SUPPLY - CONSTRUCTION OF LEVEL III WATER SUPPLY SYSTEM, RIZAL, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱42.1M | 100% | Medium risk49 | —-0.045 |
| 16 | 23PK0092CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION / REHABILITATION OF WATER SUPPLY / SEPTAGE AND SEWERAGE / RAIN WATER COLLECTOR / WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SUPPLY PROJECT, MUNICIPALITY BALBALAN, PROVINCE OF KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱19.6M | 100% | Medium risk49 | —-0.047 |
| 17 | 24PL0072CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM - CONSTRUCTION OF WATER SUPPLY SYSTEM (LEVEL III), RIZAL, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱44.1M | 100% | Medium risk48 | —-0.044 |
| 18 | 22HB0086CONVERGENCE AND SPECIAL SUPPORT PROGRAM 1CONSTRUCTION/REHABILITATION OF WATER SUPPLY SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM 1 WATER SUPPLY SYSTEM 1 REHABILITATION OF WATER SUPPLY SYSTEM - LEVEL III, SIERRA BULLONES, BOHOL | Region VII | Bohol 3rd DEO | Completed | ₱49M | 100% | Medium risk47 | —-0.044 |
| 19 | 23PL0107CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM-WATER SUPPLY SYSTEM - CONSTRUCTION OF LEVEL III WATER SUPPLY SYSTEM IN TANUDAN, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱24.5M | 100% | Medium risk46 | —-0.047 |
| 20 | 18OF0096REHABILITATION/ IMPROVEMENT OF CULIAT CREEK, Q.C. | National Capital Region | Quezon City 1st DEO | Completed | ₱18.4M | 100% | Medium risk46 | —-0.083 |
| 21 | 20OF0150REHABILITATION OF DRAINAGE, CULIAT CREEK, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱19M | 100% | Medium risk46 | —-0.087 |
| 22 | 22HB0091CONVERGENCE AND SPECIAL SUPPORT PROGRAM -SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE / FACILITIES - CONSTRUCTION OF DRAINAGE SYSTEM, BARANGAY POBLACION, BILAR, BOHOL SECTION | Region VII | Bohol 3rd DEO | Completed | ₱32.3M | 100% | Medium risk44 | —-0.075 |
| 23 | 21PL0088REHABILITATION OF BASAO/ELEB, DAYA WATERWORKS, TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱2M | 100% | Low risk25 | —-0.045 |
| 24 | 21PL0090REHABILITATION OF PUROK 6 BULANAO/LANGNGA-DURODOL/PANTAR WATERWORKS, TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱2M | 100% | Low risk25 | —-0.046 |
| 25 | 18KB0038CONSTRUCTION OF WATER SYSTEM, PUROK 6, 7 AND 9, BRGY PAY-AS, KADINGILAN, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱1.9M | 100% | Low risk13 | —-0.057 |