Opening the dossier…
Opening the dossier…
Contractor dossier
125 projects on file, including joint ventures this contractor is part of.
Total projects
125
Total budget
₱6.7B
Average progress
95.1%
Completion rate
85.6%
Average risk score
47.9
Medium risk on average, out of 100
Flagged as unusual
7
5.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XI | 49 | ₱2.6B | 49.5 | 5 | 94.8% |
| Region I | 24 | ₱985.8M | 50.5 | 0 | 93.7% |
| Region XII | 16 | ₱1.1B | 35.3 | 0 | 100.0% |
| Cordillera Administrative Region | 9 | ₱714.1M | 54.4 | 1 | 96.7% |
| Region III | 9 | ₱158.1M | 35.0 | 0 | 100.0% |
| Region X | 5 | ₱433.7M | 54.4 | 0 | 100.0% |
| National Capital Region | 4 | ₱177.4M | 47.8 | 0 | 73.8% |
| Region VIII | 3 | ₱198M | 54.7 | 0 | 100.0% |
| Region IV-B | 2 | ₱210.2M | 57.5 | 0 | 86.0% |
| Region IV-A | 2 | ₱57.2M | 47.0 | 0 | 100.0% |
| Region XIII | 1 | ₱39M | 95.2 | 1 | 57.5% |
| Region II | 1 | ₱44.1M | 44.1 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 53 | ₱3.1B | 46.1 | 0 | 98.6% |
| Flood Control and Drainage | 38 | ₱2.4B | 51.7 | 1 | 99.3% |
| Buildings and Facilities | 19 | ₱501.4M | 35.5 | 2 | 93.3% |
| Bridges | 9 | ₱353.6M | 46.8 | 0 | 83.3% |
| OTHER | 4 | ₱198.3M | 73.0 | 2 | 71.0% |
| GAA 2025 SSP | 1 | ₱39M | 95.2 | 1 | 57.5% |
| GAA 2025 OO-1 | 1 | ₱76M | 93.8 | 1 | 29.9% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25NH0061CONSTRUCTION OF BRIDGE LINKING BURGOS AND TAG-ANUNGAN BOTH OF CORTES, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | On-Going | ₱39M | 58% | High risk95 | Flagged0.028 |
| 25L00093PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - MAHARLIKA HIGHWAY (DAVAO CITY - JCT. DIGOS SECT) - (S00039MN) K1517+804 - K1518+060, K1518+231 - K1518+405, (S01455MN) CHAINAGE 2488 - CHAINAGE 3712, DAVAO CITY | Region XI | Region XI | On-Going | ₱76M | 30% | High risk94 | Flagged0.022 |
| 22LB0308CONSTRUCTION OF ROAD WITH DRAINAGE AT BARANGAY TALOMO PROPER, DAVAO CITY | Region XI | Davao City DEO | On-Going | ₱57.9M | 74% | High risk76 | Flagged0.034 |
| 25L00106CONSTRUCTION (COMPLETION) OF BUILDING INSTITUTE FOR INFECTIOUS DISEASE, SOUTHERN PHILIPPINES MEDICAL CENTER, DAVAO CITY, PHASE II | Region XI | Region XI | On-Going | ₱42M | 11% | High risk72 | Flagged0.031 |
| 21MB0028ROAD WIDENING INCLUDING DRAINAGE ALONG MABUHAY ROAD, STA. 3+666 TO STA. 4+991, GENERAL SANTOS CITY | Region XII | South Cotabato 1st DEO | Completed | ₱65.5M | 100% | High risk72 | —-0.024 |
| 18LB0022CONST./IMP. OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS JCT. DAVAO COTABATO OLD ROAD BA | Region XI | Davao City DEO | Completed | ₱32.8M | 100% | High risk72 | —-0.026 |
| 19P00045REHABILITATION OF THE FLOOD MITIGATION STRUCTURE ALONG BUED RIVER BASIN, CAMP 1 SECTION, TABAAN SUR, TUBA, BENGUET | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱144.8M | 100% | High risk67 | Flagged0.009 |
| 17AJ0032CONSTRUCTION OF CONCRETE REVETMENT ALONG MARUSAY RIVER AT LASIP SECTION, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱23.9M | 100% | High risk65 | —-0.046 |
| 17AJ0054CONSTRUCTION OF PROTECTION WORKS ALONG AGNO RIVER, GUELEW SECTION, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱9.8M | 100% | High risk65 | —-0.048 |
| 17AI0040OFF-CARRIAGEWAY IMPVT INCL DRAINAGE ALONG PANGASINAN-NUEVA ECIJA RD, STA 186+009-STA. 186+492 | Region I | Pangasinan 3rd DEO | Completed | ₱9.5M | 100% | High risk65 | —-0.059 |
| 22L00092CONSTRUCTION OF JUNCTION SALINGCOMOT - BATAWAN ROAD, BAGANGA, DAVAO ORIENTAL | Region XI | Region XI | Completed | ₱164M | 100% | High risk64 | —-0.049 |
| 18PE0107REHABILITATION AND CONSTRUCTION OF DUNGON BRIDGE FLOOD CONTROL, CAMP 1, TUBA, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | Completed | ₱92.6M | 100% | High risk64 | —-0.003 |
| 18PE0106REHABILITATION AND CONSTRUCTION OF BUED RIVER BASIN FLOOD MITIGATION STRUCTURE, CAMP 1 SECTION, TUBA, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | Completed | ₱92.5M | 100% | High risk62 | —-0.002 |
| 21L00042ROAD WIDENING ALONG FATIMA - MALABOG ROAD (S00059MN), K1507+010-K1508+498, DAVAO CITY | Region XI | Region XI | On-Going | ₱100.5M | 74% | High risk62 | —-0.011 |
| 22A00078CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PARONGKING RIVER, BRGY. AMBONAO AND BRGY. SAN MIGUEL, CALASIAO, PANGASINAN (PHASE I) | Region I | Region I | Completed | ₱129.6M | 100% | High risk62 | —-0.049 |
| 22A00079CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PARONGKING RIVER, BRGY. AMBONAO AND BRGY. SAN MIGUEL, CALASIAO, PANGASINAN (PHASE II) | Region I | Region I | Completed | ₱128.3M | 100% | High risk62 | —-0.050 |
| 21LB0305CONSTRUCTION OF DRAINAGE SYSTEM LEADING TO TUPAZ OUTFALL, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱96.5M | 100% | High risk61 | —-0.063 |
| 24KL0071CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ALAE RIVER (RIGHT SIDE), PACKAGE 3, BARANGAY CASINGLOT, TAGOLOAN, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | Completed | ₱125.5M | 100% | High risk61 | —-0.064 |
| 24KL0072CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ALAE RIVER (RIGHT SIDE), PACKAGE 4, BARANGAY CASINGLOT, TAGOLOAN, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | Completed | ₱125.5M | 100% | High risk61 | —-0.064 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 22LB0308CONSTRUCTION OF ROAD WITH DRAINAGE AT BARANGAY TALOMO PROPER, DAVAO CITY | Region XI | Davao City DEO | On-Going | ₱57.9M | 74% | High risk76 | Flagged0.034 |
| 25L00106CONSTRUCTION (COMPLETION) OF BUILDING INSTITUTE FOR INFECTIOUS DISEASE, SOUTHERN PHILIPPINES MEDICAL CENTER, DAVAO CITY, PHASE II | Region XI | Region XI | On-Going | ₱42M | 11% | High risk72 | Flagged0.031 |
| 25NH0061CONSTRUCTION OF BRIDGE LINKING BURGOS AND TAG-ANUNGAN BOTH OF CORTES, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | On-Going | ₱39M | 58% | High risk95 | Flagged0.028 |
| 25L00093PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - MAHARLIKA HIGHWAY (DAVAO CITY - JCT. DIGOS SECT) - (S00039MN) K1517+804 - K1518+060, K1518+231 - K1518+405, (S01455MN) CHAINAGE 2488 - CHAINAGE 3712, DAVAO CITY | Region XI | Region XI | On-Going | ₱76M | 30% | High risk94 | Flagged0.022 |
| 21LB0383CONSTRUCTION OF OFFICE BUILDING FOR THE NATIONAL PROSECUTION SERVICE IN REGION XI (PHASE III) | Region XI | Davao City DEO | On-Going | ₱49.7M | 86% | Medium risk46 | Flagged0.021 |
| 19P00045REHABILITATION OF THE FLOOD MITIGATION STRUCTURE ALONG BUED RIVER BASIN, CAMP 1 SECTION, TABAAN SUR, TUBA, BENGUET | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱144.8M | 100% | High risk67 | Flagged0.009 |
| 24LH0109CONSTRUCTION OF 3STY12CL, VINZONS ELEM. SCHOOL, DAVAO CITY, DAVAO DEL SUR | Region XI | Davao City 2nd DEO | On-Going | ₱47.6M | 86% | Medium risk47 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 17AI0657CONSTN OF TWO STRY TWELVE CL SB AT CABALAONGAN E/S, SAN QUINTIN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱23.8M | 100% | Medium risk37 | —-0.014 |
| 102 | 17AI0357CONSTN OF TWO STRY EIGHT CL SB AT LAGASIT NHS, SAN QUINTIN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱18.6M | 100% | Medium risk37 | —-0.015 |
| 103 | 25M00251PREVENTIVE MAINTENANCE - FILIPINO-AMERICAN FRIENDSHIP AVE. (S01440MN) - K1664 + 000 - K1665 + 250, GENERAL SANTOS CITY | Region XII | Region XII | On-Going | ₱65.5M | 100% | Medium risk36 | —-0.052 |
| 104 | 20CD0145CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURES, PANDAYAN - SALUYSOY CREEK, MEYCAUAYAN CITY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱22.9M | 100% | Medium risk36 | —-0.093 |
| 105 | 23M00172OFF-CARRIAGEWAY IMPROVEMENT - ALBERT MORROW BLVD, K1661+158 - K1666+000, GENERAL SANTOS CITY | Region XII | Region XII | Completed | ₱74.8M | 100% | Medium risk35 | —-0.078 |
| 106 | 24M00178OFF-CARRIAGEWAY IMPROVEMENT: CONSTRUCTION OF TRAFFIC ISLAND - COTABATO-MARBEL RD - K1714+450 - K1717+050, K1719+800 - K1722+674, BANGA, SOUTH COTABATO | Region XII | Region XII | On-Going | ₱86.8M | 100% | Medium risk35 | —-0.047 |
| 107 | 17OD0183CONSTRUCTION OF 4-STOREY 12-CLASSROOM SCHOOL BUILDING LAWANG BATO ELEMENTARY SCHOOL, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱33.8M | 100% | Medium risk34 | —-0.018 |
| 108 | 20MC0026PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ON SPECIFIC LOCATION ALONG KIDAPAWAN-ILOMAVIS TOURIST ROAD - K1623+633 TO K1627+542, KIDAPAWAN CITY, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱79.4M | 100% | Medium risk34 | —-0.079 |
| 109 | 25M00085PREVENTIVE MAINTENANCE - SIMUAY LANDASAN-PARANG RD - K1866 + (-433) - K1867 + 135, SULTAN MASTURA, MAGUINDANAO DEL NORTE | Region XII | Region XII | Completed | ₱63.9M | 100% | Medium risk33 | —-0.086 |
| 110 | 19CD0214CONSTRUCTION OF FLOOD CONTROL STRUCTURES, STA. MARIA RIVER SYSTEM, STA. MARIA, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱13.9M | 100% | Medium risk32 | —-0.093 |
| 111 | 20CD0101ASSET PRESERVATION REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS STA. MARIA BY-PASS ROAD K0033+642 K0033+900 | Region III | Bulacan 2nd DEO | Completed | ₱8.9M | 100% | Medium risk32 | —-0.101 |
| 112 | 18CD0220WIDENING OF PERMANENT BRIDGES, KAY-UWAK BR. (B00329LZ) ALONG NORZAGARAY - BIGTE ROAD | Region III | Bulacan 2nd DEO | Completed | ₱26.5M | 100% | Medium risk32 | —-0.067 |
| 113 | 20MC0001PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ON SPECIFIC LOCATION ALONG PACO-ROXAS-ARAKAN VALLEY-JCT. DAVAO-BUKIDNON RD (S00701MN) K1657+040 TO K1667+069, ANTIPAS AND ARAKAN, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱61.8M | 100% | Medium risk31 | —-0.086 |
| 114 | 20M00107PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ON SPECIFIC LOCATION ALONG DAVAO-COTABATO, RD (JCT. DIGOS-COTABATO SECT) - K1635+025 TO K1639+000 | Region XII | Region XII | Completed | ₱53.3M | 100% | Medium risk30 | —-0.088 |
| 115 | 24MG0103OFF-CARRIAGEWAY IMPROVEMENT: CONSTRUCTION OF TRAFFIC ISLAND-MIDSAYAP-MARBEL RD-K1780+500-K1786+595 | Region XII | South Cotabato 2nd DEO | Completed | ₱34M | 100% | Low risk27 | —-0.088 |
| 116 | 25MD0022INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (GUARDRAILS, ROAD SIGNS, PAVEMENT MARKINGS, ROADWAY LIGHTING) ALONG BANISILAN-GUILING-ALAMADA-LIBUNGAN RD, LIBUNGAN, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱46.8M | 100% | Low risk27 | —-0.089 |
| 117 | 20MC0091CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE-ALONG PACO-ROXAS-ARAKAN VALLEY-JCT DAVAO-BUKIDNON RD - K1691+(-200) - K1691+(-112), ARAKAN, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱36.1M | 100% | Low risk26 | —-0.088 |
| 118 | 20LB0345CONSTRUCTION OF OFFICE BUILDING FOR THE NATIONAL PROSECUTION SERVICE IN REGION XI (PHASE II) | Region XI | Davao City DEO | Completed | ₱49.7M | 100% | Low risk26 | —-0.008 |
| 119 | 23MG0031CONSTRUCTION OF RIVER BANK PROTECTION ALONG ALA RIVER, SITIO PANES, BARANGAY KOLAMBOG, SANTO NIÑO, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱49M | 100% | Low risk26 | —-0.075 |
| 120 | 18MF0095CONST. OF 3-STY 6-CLASSROOMS LABORATORY BUILDING AT SAN EMMANUEL NHS, TACURONG CITY, SULTAN KUDARAT. | Region XII | Sultan Kudarat 1st DEO | Completed | ₱35.4M | 100% | Low risk21 | —-0.025 |
| 121 | 20CD0076CONSTRUCTION OF MULTI-PURPOSE BUILDING, IBA, MEYCAUAYAN CITY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱4.7M | 100% | Low risk20 | —-0.108 |
| 122 | 17LD0198CONSTRUCTION OF CLASSROOMS, 3STY 6CL SIBULAN NATIONAL HIGH SCHOOL, SANTA CRUZ, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱15.3M | 100% | Low risk19 | —-0.018 |
| 123 | 20CD0060CONSTRUCTION OF ROADS, PANDAYAN, MEYCAUAYAN CITY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱4.7M | 100% | Low risk16 | —-0.106 |
| 124 | 19LA0273CONSTRUCTION (COMPLETION) OF MPB AT ANDILI NHS, MAWAB, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱2M | 100% | Low risk13 | —-0.088 |
| 125 | 19LA0224CONSTRUCTION OF MULTI-PURPOSE BUILDING (MINI GYM) PANGUTUSAN ES, NABUNTURAN, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱2M | 100% | Low risk13 | —-0.087 |