Contractor dossier
1 project on file, including joint ventures this contractor is part of.
Total projects
1
Total budget
₱96.5M
Average progress
100.0%
Completion rate
100.0%
Average risk score
69.0
High risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 1 | ₱96.5M | 69.0 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 1 | ₱96.5M | 69.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24CJ0368CONSTRUCTION OF SLOPE PROTECTION WITH STEEL SHEET PILE FOUNDATION ALONG MORIONES RIVER, PACKAGE I, TIBAGAN SECTION, TIBAGAN, TARLAC CITY, TARLAC | Region III | Tarlac DEO | Completed | ₱96.5M | 100% | High risk69 | —-0.013 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24CJ0368CONSTRUCTION OF SLOPE PROTECTION WITH STEEL SHEET PILE FOUNDATION ALONG MORIONES RIVER, PACKAGE I, TIBAGAN SECTION, TIBAGAN, TARLAC CITY, TARLAC | Region III | Tarlac DEO | Completed | ₱96.5M | 100% | High risk69 | —-0.013 |