Opening the dossier…
Opening the dossier…
Contractor dossier
162 projects on file, including joint ventures this contractor is part of.
Total projects
162
Total budget
₱12.6B
Average progress
86.0%
Completion rate
58.6%
Below 70%
Average risk score
64.5
High risk on average, out of 100
Flagged as unusual
12
7.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region V | 158 | ₱12.2B | 64.6 | 12 | 85.7% |
| Region VIII | 4 | ₱389.2M | 59.4 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 115 | ₱8.9B | 62.2 | 0 | 87.1% |
| Flood Control and Drainage | 16 | ₱1.1B | 59.2 | 2 | 86.7% |
| Buildings and Facilities | 14 | ₱1.1B | 60.9 | 0 | 100.0% |
| GAA 2025 OO-1 | 7 | ₱538.3M | 94.0 | 6 | 44.2% |
| OTHER | 4 | ₱289.5M | 77.9 | 1 | 75.3% |
| GAA 2025 SSP | 2 | ₱141.7M | 95.7 | 2 | 75.0% |
| GAA 2025 OO-2 | 2 | ₱253.5M | 92.4 | 0 | 93.1% |
| Bridges, Roads | 2 | ₱340.7M | 70.5 | 1 | 96.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25FK0005CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES -CONSTRUCTION OF ROAD, BARANGAY SAN PASCUAL | Region V | Sorsogon DEO | On-Going | ₱94.3M | 95% | High risk96 | Flagged0.006 |
| 25FK0014CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES -CONSTRUCTION OF BYPASS AT BAYASONG - MALBOG | Region V | Sorsogon DEO | On-Going | ₱47.4M | 55% | High risk96 | Flagged0.011 |
| 25FK0022ORGANIZAL OUTCOM 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-SORSOGON CITY COASTAL BYPASS ROAD, PACKAGE 19, SORSOGON | Region V | Sorsogon DEO | On-Going | ₱141.4M | 72% | High risk95 | Flagged0.017 |
| 25FK0023ORGANIZAL OUTCOM 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-SORSOGON CITY COASTAL BYPASS ROAD, PACKAGE 20, SORSOGON | Region V | Sorsogon DEO | On-Going | ₱141.4M | 90% | High risk95 | Flagged0.010 |
| 25F00099ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0610+909.90-K0611+595, K0624+149-K0624+999, K0631+500-K0631+670, JUBAN, IROSIN, AND MATNOG, SORSOGON (2ND LE | Region V | Region V | On-Going | ₱116.5M | 12% | High risk95 | Flagged0.029 |
| 25FL0005ASSET PRESERVATION PROGRAM - REHAB/RECONST OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERT | Region V | Sorsogon 2nd DEO | On-Going | ₱80.6M | 93% | High risk94 | —-0.002 |
| 25F00068ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0548+583.16-K0548+985, PILAR, SORSOGON (1ST LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱36M | 39% | High risk93 | Flagged0.008 |
| 25F00184ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS-MAHARLIKA HIGHWAY-K0547+083-K0547+426, PILAR, SORSOGON (1ST LEGISLATIVE DISTR | Region V | Region V | On-Going | ₱11.5M | 1% | High risk93 | Flagged0.017 |
| 25F00183ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0547+670-K0547+982, PILAR, SORSOGON (1ST LEGISLATIVE DISTRIC | Region V | Region V | On-Going | ₱10.8M | 1% | High risk93 | Flagged0.017 |
| 25FK0025ORGANIZAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR-FLOODS- FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BURGOS RIVER, CASIGURAN, SORSOGON | Region V | Sorsogon DEO | On-Going | ₱141.4M | 90% | High risk93 | —-0.005 |
| 25FK0026ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR-FLOODS- FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, TALINGA RIVER, PHASE 2, TIGBAO | Region V | Sorsogon DEO | On-Going | ₱112.1M | 96% | High risk92 | —-0.012 |
| 25FL0086CONST/IMPRVT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRA. PROGRAM-T | Region V | Sorsogon 2nd DEO | On-Going | ₱121.5M | 25% | High risk81 | Flagged0.028 |
| 24FL0120CONST. OF FLOOD MITIGATION STRUCTURE (REVETMENT) ALONG BITON RIVER AT BARANGAY J. GERONA, BULAN, SOR | Region V | Sorsogon 2nd DEO | On-Going | ₱94.3M | 73% | High risk80 | Flagged0.021 |
| 24FL0116CONST. OF FLOOD MITIGATION STRUCTURES (REVETMENT) ALONG BUTAG RIVER AT BARANGAY BUTAG, BULAN, SORSOG | Region V | Sorsogon 2nd DEO | On-Going | ₱95.5M | 68% | High risk80 | Flagged0.025 |
| 25FL0052CONST/IMPRVT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM RD INFRA PROG - TRIP) | Region V | Sorsogon 2nd DEO | On-Going | ₱62.4M | 88% | High risk78 | —-0.004 |
| 25FL0044CONST/IMPRVT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM RD. INFRA. PROGRAM -) | Region V | Sorsogon 2nd DEO | On-Going | ₱62.4M | 90% | High risk78 | —-0.005 |
| 25FL0056CONST/IMPRVT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM RD INFRA PROG - TRIP) | Region V | Sorsogon 2nd DEO | On-Going | ₱43.2M | 98% | High risk75 | —-0.012 |
| 21FB0133LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS CONSTRUCTION OF BY PASS ROAD FROM MAHARLIKA HIGHWAY (LEGASPI - TABACO ROAD) TO DUTERTE HIGHWAY, LEGAZPI CITY, ALBAY | Region V | Albay 2nd DEO | On-Going | ₱186.6M | 80% | High risk73 | —-0.015 |
| 21F00024OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CLUSTER II:I-BARCELONA-CASIGURAN DIVERSION ROAD,BARCELONA SECTION,SORSOGON;II-JUBAN-BULAN DIVERSION ROAD,BULAN SECTION,SORSOGON;III- | Region V | Region V | On-Going | ₱241.9M | 96% | High risk71 | Flagged0.003 |
| 24F00263ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0513+502-K0513+870, K0515+248-K0515+493, K0516+005-K0516+596, K0529+000-K0529+311, CAMALIG, ALBAY | Region V | Region V | Completed | ₱95.7M | 100% | High risk70 | —-0.091 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25F00099ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0610+909.90-K0611+595, K0624+149-K0624+999, K0631+500-K0631+670, JUBAN, IROSIN, AND MATNOG, SORSOGON (2ND LE | Region V | Region V | On-Going | ₱116.5M | 12% | High risk95 | Flagged0.029 |
| 25FL0086CONST/IMPRVT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRA. PROGRAM-T | Region V | Sorsogon 2nd DEO | On-Going | ₱121.5M | 25% | High risk81 | Flagged0.028 |
| 24FL0116CONST. OF FLOOD MITIGATION STRUCTURES (REVETMENT) ALONG BUTAG RIVER AT BARANGAY BUTAG, BULAN, SORSOG | Region V | Sorsogon 2nd DEO | On-Going | ₱95.5M | 68% | High risk80 | Flagged0.025 |
| 24FL0120CONST. OF FLOOD MITIGATION STRUCTURE (REVETMENT) ALONG BITON RIVER AT BARANGAY J. GERONA, BULAN, SOR | Region V | Sorsogon 2nd DEO | On-Going | ₱94.3M | 73% | High risk80 | Flagged0.021 |
| 25F00184ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS-MAHARLIKA HIGHWAY-K0547+083-K0547+426, PILAR, SORSOGON (1ST LEGISLATIVE DISTR | Region V | Region V | On-Going | ₱11.5M | 1% | High risk93 | Flagged0.017 |
| 25FK0022ORGANIZAL OUTCOM 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-SORSOGON CITY COASTAL BYPASS ROAD, PACKAGE 19, SORSOGON | Region V | Sorsogon DEO | On-Going | ₱141.4M | 72% | High risk95 | Flagged0.017 |
| 25F00183ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0547+670-K0547+982, PILAR, SORSOGON (1ST LEGISLATIVE DISTRIC | Region V | Region V | On-Going | ₱10.8M | 1% | High risk93 | Flagged0.017 |
| 25FK0014CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES -CONSTRUCTION OF BYPASS AT BAYASONG - MALBOG | Region V | Sorsogon DEO | On-Going | ₱47.4M | 55% | High risk96 | Flagged0.011 |
| 25FK0023ORGANIZAL OUTCOM 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-SORSOGON CITY COASTAL BYPASS ROAD, PACKAGE 20, SORSOGON | Region V | Sorsogon DEO | On-Going | ₱141.4M | 90% | High risk95 | Flagged0.010 |
| 25F00068ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0548+583.16-K0548+985, PILAR, SORSOGON (1ST LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱36M | 39% | High risk93 | Flagged0.008 |
| 25FK0005CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES -CONSTRUCTION OF ROAD, BARANGAY SAN PASCUAL | Region V | Sorsogon DEO | On-Going | ₱94.3M | 95% | High risk96 | Flagged0.006 |
| 21F00024OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CLUSTER II:I-BARCELONA-CASIGURAN DIVERSION ROAD,BARCELONA SECTION,SORSOGON;II-JUBAN-BULAN DIVERSION ROAD,BULAN SECTION,SORSOGON;III- | Region V | Region V | On-Going | ₱241.9M | 96% | High risk71 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 25F00101ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0565+845-K0566+570, SORSOGON CITY, SORSOGON (1ST LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱50.2M | 81% | High risk60 | —-0.067 |
| 102 | 24FL0067ACCESS ROAD LEADING TO INDUSTRIES AT BRGY. MONBON, IROSIN, KAWILIHAN, BRGY. MAGSAYSAY, BULAN, SITIO | Region V | Sorsogon 2nd DEO | On-Going | ₱47.5M | 96% | High risk60 | —-0.062 |
| 103 | 25F00008ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0638+012-K0639+579, MATNOG, SORSOGON (2ND LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱103.3M | 0% | Medium risk60 | —-0.003 |
| 104 | 25FL0055CONST/IMPRVT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM RD INFRA PROG - TRIP | Region V | Sorsogon 2nd DEO | On-Going | ₱48M | 60% | Medium risk60 | —-0.058 |
| 105 | 22FK0022CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-COASTAL ROADS_CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION-CONSTRUCTION OF CASIGURAN COASTAL BYPASS ROAD, SORSOGON CASIGURAN, SORSOGON | Region V | Sorsogon DEO | Completed | ₱47.4M | 100% | Medium risk60 | —-0.098 |
| 106 | 24F00136ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0606+414-K0606+513, K0607+542-K0607+700, K0608+400-K0608+493, K0610+100-K0610+909.90, JUBAN, SORSOGON (2N | Region V | Region V | On-Going | ₱47.8M | 88% | Medium risk60 | —-0.061 |
| 107 | 25FL0021CONSTRUCTION OF ROAD, BARANGAY A. BONIFACIO TO BARANGAY SAN FRANCISCO, BULAN, SORSOGON | Region V | Sorsogon 2nd DEO | On-Going | ₱47M | 97% | Medium risk60 | —-0.070 |
| 108 | 22IJ0033OO1: CALBAYOG CITY COASTAL ROAD, PACKAGE 6A,SAMAR | Region VIII | Samar 1st DEO | Completed | ₱95.9M | 100% | Medium risk60 | —-0.084 |
| 109 | 21FL0064CONST/IMPRVT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM RD INFRA PROGRAM - T) | Region V | Sorsogon 2nd DEO | Completed | ₱47.2M | 100% | Medium risk60 | —-0.097 |
| 110 | 25FK0016CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES -CONSTRUCTION OF ROAD, BARANGAY TIGB | Region V | Sorsogon DEO | On-Going | ₱47.9M | 80% | Medium risk60 | —-0.065 |
| 111 | 21FL0065CONST/IMPRVT. OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRA. PROGRAM | Region V | Sorsogon 2nd DEO | Completed | ₱47.2M | 100% | Medium risk60 | —-0.097 |
| 112 | 22IJ0029OO1: CALBAYOG CITY COASTAL ROAD, PACKAGE A, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱96.4M | 100% | Medium risk60 | —-0.084 |
| 113 | 22IJ0087(RE-ADVERTISE) CONSTRUCTION OF CROSS COUNTRY ROAD, FROM OQUINDO O NORTHERN SAMAR (PHSE 2), CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱98.5M | 100% | Medium risk59 | —-0.074 |
| 114 | 22IJ0086(RE-ADVERTISE) CSSP: CONSTRUCTION OF CROSS-COUNTRY ROAD, FROM OQUINDO TO NORTHERN SAMAR (PHASE 1), CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱98.5M | 100% | Medium risk59 | —-0.081 |
| 115 | 24FK0061CLUSTER XVII-CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP) -MULTI PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES 1.) CONST. OF MULTI-PURPOSE FACILITIES BALOGO SPORTS COMPLEX, BRGY. BALOGO, SOR. CITY 2.) REHABIL | Region V | Sorsogon DEO | Completed | ₱54.2M | 100% | Medium risk59 | —-0.090 |
| 116 | 21FL0019(RE-ADVERTISEMENT) - CONSTRUCTION OF BY-PASS ROAD, BARANGAY CARRIEDO-LIANG-HIDHID,IROSIN-MATNOG, SOR | Region V | Sorsogon 2nd DEO | Completed | ₱49.5M | 100% | Medium risk59 | —-0.097 |
| 117 | 25FK0049CONVERGENCE AND SPECIAL SUPPORT (CSSP)-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-REHABILITATION OF ROAD AT STA. CRUZ-RIZAL VIA YA | Region V | Sorsogon DEO | On-Going | ₱48.2M | 20% | Medium risk59 | —-0.048 |
| 118 | 25FK0068CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-REHABILITATION OF PAVED ROAD, BRGY. LUMBANG, PILAR, SORSOGON | Region V | Sorsogon DEO | On-Going | ₱19.2M | 4% | Medium risk58 | —-0.044 |
| 119 | 22FL0002NETWORK DEV'T. PROGRAM - OFF CARRIAGEWAY IMPRV'T. - SECONDARY ROADS - GATE-BULAN-AIRPORT ROAD - K063 | Region V | Sorsogon 2nd DEO | Completed | ₱33.3M | 100% | Medium risk58 | —-0.098 |
| 120 | 22FK0023NETWORK DEVELOPMENT-OFF-CARRIAGEWAY IMPROVEMENT-TERTIRARY ROADS-BACON-SAWANGA-PTO. DIAZ ROA-KO594+216-KO595+000, KO597+460-KO598+000, KO598+717-KO599+000, KO600+226-KO600+534, KO600+681-KO601+005 BACON DISTRICT, SORSOGON CITY | Region V | Sorsogon DEO | Completed | ₱47.9M | 100% | Medium risk58 | —-0.098 |
| 121 | 23FL0035CONSTRUCTION OF ROAD AT JUBAN AND BARCELONA, SORSOGON (CLUSTER IX), BRGY. GURUYAN, JUBAN, SOR. & BRG | Region V | Sorsogon 2nd DEO | Completed | ₱33.6M | 100% | Medium risk58 | —-0.097 |
| 122 | 23FL0031CONSTRUCTION OF POBLACION ROAD NETWORK, GUBAT, SORSOGON | Region V | Sorsogon 2nd DEO | Completed | ₱48M | 100% | Medium risk58 | —-0.098 |
| 123 | 24F00083ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0631+670-K0632+470, MATNOG, SORSOGON (2ND LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱39M | 81% | Medium risk58 | —-0.062 |
| 124 | 21FL0062ASSET PRESERVATION PROGRAM - PREVENTIVE MAINT. - TERTIARY RDS - ARIMAN-JCT. BULUSAN LAKE RD - K0616+ | Region V | Sorsogon 2nd DEO | Completed | ₱47.5M | 100% | Medium risk58 | —-0.094 |
| 125 | 24F00082ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0611+595-K0612+261, K0615+500-K0615+699, K0618+000-K0618+325, JUBAN AND IROSIN, SORSOGON (2ND LEGISLATIVE | Region V | Region V | On-Going | ₱41.4M | 89% | Medium risk58 | —-0.065 |