Contractor dossier
30 projects on file, including joint ventures this contractor is part of.
Total projects
30
Total budget
₱1.6B
Average progress
92.4%
Completion rate
63.3%
Below 70%
Average risk score
49.4
Medium risk on average, out of 100
Flagged as unusual
2
6.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XI | 21 | ₱1.5B | 52.0 | 2 | 92.0% |
| National Capital Region | 5 | ₱59.8M | 47.7 | 0 | 87.8% |
| Region X | 2 | ₱33.8M | 39.5 | 0 | 100.0% |
| Region IV-B | 2 | ₱38.3M | 36.8 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 18 | ₱997.3M | 47.1 | 0 | 95.3% |
| Roads | 6 | ₱142.5M | 44.3 | 0 | 94.5% |
| Flood Control and Drainage | 4 | ₱214.1M | 50.4 | 0 | 84.9% |
| OTHER | 2 | ₱284.7M | 83.9 | 2 | 74.8% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24LD0213CONSTRUCTION OF CONCRETE REVETMENT ALONG PADADA-MAINIT RIVER (RIGHT SIDE DOWNSTREAM SECTION, PACKAGE A), HAGONOY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱93.6M | 93% | High risk88 | Flagged0.067 |
| 24L00203DESIGN AND CONSTRUCTION OF MULTI-PURPOSE BUILDING (DSWD WAREHOUSE), BARANGAY LA FILIPINA, TAGUM CITY, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱191.1M | 57% | High risk79 | Flagged0.048 |
| 25LD0054CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG PADADA- MAINIT RIVER, (BRIDGE TO LAPANDAY FOODS PLANTATION LEFT SIDE DOWNSTREAM SECTION), BARANGAY GUIHING, HAGONOY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱93.6M | 75% | High risk63 | —-0.026 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24LD0213CONSTRUCTION OF CONCRETE REVETMENT ALONG PADADA-MAINIT RIVER (RIGHT SIDE DOWNSTREAM SECTION, PACKAGE A), HAGONOY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱93.6M | 93% | High risk88 | Flagged0.067 |
| 24L00203DESIGN AND CONSTRUCTION OF MULTI-PURPOSE BUILDING (DSWD WAREHOUSE), BARANGAY LA FILIPINA, TAGUM CITY, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱191.1M | 57% | High risk79 | Flagged0.048 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24LD0213CONSTRUCTION OF CONCRETE REVETMENT ALONG PADADA-MAINIT RIVER (RIGHT SIDE DOWNSTREAM SECTION, PACKAGE A), HAGONOY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱93.6M | 93% | High risk88 | Flagged0.067 |
| 2 | 24L00203DESIGN AND CONSTRUCTION OF MULTI-PURPOSE BUILDING (DSWD WAREHOUSE), BARANGAY LA FILIPINA, TAGUM CITY, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱191.1M | 57% | High risk79 | Flagged0.048 |
| 3 | 25LD0054CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG PADADA- MAINIT RIVER, (BRIDGE TO LAPANDAY FOODS PLANTATION LEFT SIDE DOWNSTREAM SECTION), BARANGAY GUIHING, HAGONOY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱93.6M | 75% | High risk63 | —-0.026 |
| 4 | 24LH0086CONSTRUCTION OF DAVAO CITY UP SPORTS COMPLEX, BARANGAY BAGO OSHIRO, TUGBOK DISTRICT, DAVAO CITY | Region XI | Davao City 2nd DEO | On-Going | ₱294M | 92% | Medium risk59 | —-0.009 |
| 5 | 24LH0052CONSTRUCTION OF MULTI-PURPOSE BUILDING, DAVAO CITY UP, BARANGAY MINTAL, TUGBOK DISTRICT, DAVAO CITY | Region XI | Davao City 2nd DEO | On-Going | ₱99M | 100% | Medium risk57 | —-0.034 |
| 6 | 20LH0070CONSTRUCTION OF SPORTS COMPLEX BUILDING, UP MINDANAO CAMPUS, DAVAO CITY | Region XI | Davao City 2nd DEO | Completed | ₱96.5M | 100% | Medium risk57 | —-0.067 |
| 7 | 22LH0165CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAVAO CITY UP SPORTS COMPLEX- PHASE 10), BARANGAY BAGO OSHIRO, TUGBOK DISTRICT, DAVAO CITY | Region XI | Davao City 2nd DEO | Completed | ₱98.5M | 100% | Medium risk57 | —-0.068 |
| 8 | 24LD0166CONSTRUCTION OF MULTI-PURPOSE BUILDING (SPORTS CENTER), DIGOS CITY, DAVAO DEL SUR (PHASE I) | Region XI | Davao del Sur DEO | On-Going | ₱57.6M | 90% | Medium risk57 | —-0.042 |
| 9 | 22LH0154CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAVAO CITY UP SPORTS COMPLEX-PHASE 7), BARANGAY BAGO OSHIRO, TUGBOK DISTRICT, DAVAO CITY | Region XI | Davao City 2nd DEO | Completed | ₱98M | 100% | Medium risk53 | —-0.017 |
| 10 | 18LD0082CONSTRUCTION OF MUNICIPAL BUILDING, STA. CRUZ, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱53.1M | 100% | Medium risk53 | —-0.079 |
| 11 | 24LD0067CONSTRUCTION OF ROAD, IBO TO TAGANSULE ROAD, MALALAG, DAVAO DEL SUR, PHASE II | Region XI | Davao del Sur DEO | On-Going | ₱49M | 83% | Medium risk52 | —-0.045 |
| 12 | 23OF0114CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BARANGAY NAGKAISANG NAYON, NOVALICHES, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱19.3M | 39% | Medium risk50 | —-0.029 |
| 13 | 21L00095CONSTRUCTION OF DAVAO DEL SUR PROVINCIAL POLICE OFFICE BUILDING WITH GROUND DEVELOPMENT AND AMENITIES, DAVAO DEL SUR | Region XI | Region XI | On-Going | ₱26.3M | 95% | Medium risk49 | —-0.024 |
| 14 | 23OF0102REHABILITATION OF MULTI-PURPOSE BUILDING IN BARANGAY SAN BARTOLOME, NOVALICHES, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱6.8M | 100% | Medium risk48 | —-0.101 |
| 15 | 23OF0097REHABILITATION / IMPROVEMENT OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY SAN AGUSTIN, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.101 |
| 16 | 20LD0110COMPLETION OF MUNICIPAL BUILDING, STA. CRUZ, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱19.8M | 100% | Medium risk48 | —-0.086 |
| 17 | 23OF0098COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY NAGKAISANG NAYON, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.100 |
| 18 | 25LD0058CONSTRUCTION OF CONCRETE ROAD, BARANGAY NEW CEBU TO BARANGAY ROXAS TO BARANGAY BUGUIS, SULOP, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱28.5M | 84% | Medium risk47 | —-0.054 |
| 19 | 25LD0065CONSTRUCTION OF FLOOD MITIGATING STRUCTURE ALONG MALALAG RIVER (IBO-PITO SECTION), BARANGAY IBO, MALALAG, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱47.5M | 64% | Medium risk47 | —-0.027 |
| 20 | 23LD0055CONSTRUCTION/CONCRETING OF BARANGAY ROAD FROM BRGY. LANGAAN TO BRGY. KAUSWAGAN OF MUNICIPALITY OF MATANAO, MATANAO, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱21.7M | 100% | Medium risk47 | —-0.090 |
| 21 | 24LD0068CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BALUTAKAY RIVER (BALABAG SECTION), DIGOS CITY, DAVAO DEL SUR, PHASE II | Region XI | Davao del Sur DEO | Completed | ₱49M | 100% | Medium risk47 | —-0.076 |
| 22 | 23LD0056CONSTRUCTION OF ROADS IN BRGY. LANGAAN TO BRGY. KAUSWAGAN, MATANAO, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱5M | 100% | Medium risk46 | —-0.085 |
| 23 | 22LH0156REHABILITATION OF MULTI-PURPOSE BUILDING (EXISTING STADIUM STRUCTURES AT DAVAO CITY UP SPORTS COMPLEX), BARANGAY BAGO OSHIRO, TUGBOK DISTRICT, DAVAO CITY | Region XI | Davao City 2nd DEO | Completed | ₱14.8M | 100% | Medium risk45 | —-0.091 |
| 24 | 23OD0202CONSTRUCTION OF FLOOD CONTROL WALL ALONG THE BANKS OF CREEKS ALONG TBWARD, BRGY. 188, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱23.9M | 100% | Medium risk45 | —-0.087 |
| 25 | 18KB0158CONSTRUCTION OF 1 UNIT, 2 STY - 10 CL SCHOOL BUILDING, MARAMAG CES, MARAMAG, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱22.5M | 100% | Medium risk41 | —-0.042 |