Contractor dossier
253 projects on file, including joint ventures this contractor is part of.
Total projects
253
Total budget
₱16.3B
Average progress
92.4%
Completion rate
78.7%
Average risk score
55.1
Medium risk on average, out of 100
Flagged as unusual
28
11.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 218 | ₱15B | 56.0 | 27 | 91.6% |
| Region V | 15 | ₱521.7M | 54.0 | 1 | 100.0% |
| Region VII | 9 | ₱313.8M | 46.9 | 0 | 100.0% |
| Region IV-B | 5 | ₱186.2M | 39.5 | 0 | 100.0% |
| Region VI | 3 | ₱196.4M | 60.8 | 0 | 100.0% |
| National Capital Region | 2 | ₱67.3M | 48.6 | 0 | 58.3% |
| Region XIII | 1 | ₱926K | 18.0 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 98 | ₱5.9B | 53.1 | 2 | 98.5% |
| Flood Control and Drainage | 59 | ₱4B | 54.2 | 2 | 93.1% |
| Bridges | 39 | ₱2.4B | 52.5 | 7 | 83.9% |
| Water Provision and Storage | 20 | ₱727M | 47.4 | 0 | 100.0% |
| OTHER | 19 | ₱2.4B | 82.9 | 14 | 79.5% |
| Buildings and Facilities | 17 | ₱761.8M | 50.2 | 2 | 84.5% |
| GAA 2025 SSP | 1 | ₱98.9M | 96.4 | 1 | 11.1% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25IJ0053CSSP: CONSTRUCTION OF BUAO BRIDGE, BARANGAY BUAO, GANDARA, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱98.9M | 11% | High risk96 | Flagged0.039 |
| 24IC0174CONCRETING OF BRGY. HUPIT FMR, BRGY. HUPIT, ALANGALANG, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱11.9M | 0% | High risk89 | Flagged0.068 |
| 22I00090SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITES - CONSTRUCTION OF JUNCTION NATIONAL ROAD BRGY. CAROLINA, CAN-AVID - DOLORES - MASLOG ROAD, (BRGY. MAGSAYSAY - BRGY. MAGONGBONG - BRGY. GAP-A | Region VIII | Region VIII | On-Going | ₱238.6M | 91% | High risk85 | Flagged0.043 |
| 24I00035CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BORONGAN - GUIUAN RD. - K0945+219 - K0945+549, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱144.7M | 40% | High risk85 | Flagged0.039 |
| 24I00033CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BORONGAN - GUIUAN RD. - K0945+549 - K0945+879, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱144.6M | 50% | High risk85 | Flagged0.036 |
| 24I00037CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BORONGAN - GUIUAN RD. - K0945+879 - K0946+187, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱144.7M | 73% | High risk85 | Flagged0.030 |
| 24I00036CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BORONGAN - GUIUAN RD. - K0946+187 - K0946+517, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱144.6M | 90% | High risk85 | Flagged0.027 |
| 24I00038CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BORONGAN - GUIUAN RD. - K0946+517 - K0946+847, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱144.7M | 94% | High risk85 | Flagged0.026 |
| 24I00140CONSTRUCTION OF FLOOD CONTROL, BARANGAY ALANG-ALANG (RAWIS), BORONGAN CITY, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱168.8M | 45% | High risk84 | Flagged0.038 |
| 24I00204SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF DIVERSION COASTAL ROAD AND BRIDGE FROM SABANG SOUTH TO SABANG NORT | Region VIII | Region VIII | On-Going | ₱163.4M | 65% | High risk84 | Flagged0.028 |
| 19I00120ASSET PRESERVATION / REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS, CATBALOGAN DIVERSION RD. - KO801+(-850) - KO801+510, SAMAR | Region VIII | Region VIII | Completed | ₱236.4M | 100% | High risk84 | Flagged0.009 |
| 23I00140ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS -LEYTE-SAMAR INTER PROV'L. RD. - K0908+000 - K0909+460, K0911+140 - K0912+040, K0912+420 - K0912+603, LEYTE 1ST LD | Region VIII | Region VIII | On-Going | ₱144.6M | 90% | High risk83 | Flagged0.030 |
| 22I00070SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES CONSTRUCTION OF ROAD, BURAUEN, LEYTE | Region VIII | Region VIII | On-Going | ₱286.3M | 91% | High risk83 | Flagged0.049 |
| 24IJ0050(RE-ADVERTISED) OO1: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CALBAYOG CITY COASTAL ROAD, PACKAGE 5A, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱144.2M | 81% | High risk83 | Flagged0.022 |
| 23I00109ASSET PRESERVATION - PREVENTIVE MAINTENANCE - SECONDARY ROADS - BDRY. SOUTHERN LEYTE - MAASIN - MACROHON - SOGOD - JCT. DAANG MAHARLIKA - K1206+604 - K1209+000, K1212+046 - K1213+199, SOUTHERN LEYTE DISTRICT-SUB | Region VIII | Region VIII | Completed | ₱96.5M | 100% | High risk82 | —-0.020 |
| 20GI0017ACCESS ROAD INCLUDING ALTERNATE ROUTE LEADING TO SEVEN CITIES AGRI TOURISM SITE, ALIMODIAN, ILOILO | Region VI | Iloilo 4th DEO | Completed | ₱75.3M | 100% | High risk81 | —-0.019 |
| 23IJ0061(RE-ADVERTISED) CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CALBAYOG CITY COASTAL ROAD, PACKAGE B, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱48.5M | 100% | High risk80 | —-0.029 |
| 18II0063CONSTRUCTION OF MISSING LINKS/NEW ROADS, ARTECHE - BRGY. CATUMSAN - JIPAPAD - LAS NAVAS - CATUBIG - RAWIS ROAD (NORTHERN SAMAR SIDE), INCL. ROW, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Terminated | ₱14.5M | 100% | High risk79 | Flagged0.011 |
| 18IM0015ROAD WIDENING - RIZAL AVENIDA EXT. ROAD K0905+(-909)-K0905+(-733), K0905+(-733)-K0905+(-705), K0905+(-480)-K0905+(-471),K0905+(-471)-K0905+(-440), TACLOBAN CITY | Region VIII | Tacloban City DEO | Completed | ₱8.1M | 100% | High risk77 | —-0.037 |
| 17FK0009CLUSTER II-CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NAT'L. ROADS REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES IN FIRST DISTRICT OF SORSOGON | Region V | Sorsogon DEO | Completed | ₱41.9M | 100% | High risk75 | —-0.030 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24IC0174CONCRETING OF BRGY. HUPIT FMR, BRGY. HUPIT, ALANGALANG, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱11.9M | 0% | High risk89 | Flagged0.068 |
| 22I00070SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES CONSTRUCTION OF ROAD, BURAUEN, LEYTE | Region VIII | Region VIII | On-Going | ₱286.3M | 91% | High risk83 | Flagged0.049 |
| 22I00090SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITES - CONSTRUCTION OF JUNCTION NATIONAL ROAD BRGY. CAROLINA, CAN-AVID - DOLORES - MASLOG ROAD, (BRGY. MAGSAYSAY - BRGY. MAGONGBONG - BRGY. GAP-A | Region VIII | Region VIII | On-Going | ₱238.6M | 91% | High risk85 | Flagged0.043 |
| 24I00035CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BORONGAN - GUIUAN RD. - K0945+219 - K0945+549, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱144.7M | 40% | High risk85 | Flagged0.039 |
| 25IJ0053CSSP: CONSTRUCTION OF BUAO BRIDGE, BARANGAY BUAO, GANDARA, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱98.9M | 11% | High risk96 | Flagged0.039 |
| 24I00140CONSTRUCTION OF FLOOD CONTROL, BARANGAY ALANG-ALANG (RAWIS), BORONGAN CITY, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱168.8M | 45% | High risk84 | Flagged0.038 |
| 24I00033CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BORONGAN - GUIUAN RD. - K0945+549 - K0945+879, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱144.6M | 50% | High risk85 | Flagged0.036 |
| 24I00037CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BORONGAN - GUIUAN RD. - K0945+879 - K0946+187, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱144.7M | 73% | High risk85 | Flagged0.030 |
| 23I00140ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS -LEYTE-SAMAR INTER PROV'L. RD. - K0908+000 - K0909+460, K0911+140 - K0912+040, K0912+420 - K0912+603, LEYTE 1ST LD | Region VIII | Region VIII | On-Going | ₱144.6M | 90% | High risk83 | Flagged0.030 |
| 24I00204SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF DIVERSION COASTAL ROAD AND BRIDGE FROM SABANG SOUTH TO SABANG NORT | Region VIII | Region VIII | On-Going | ₱163.4M | 65% | High risk84 | Flagged0.028 |
| 24I00036CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BORONGAN - GUIUAN RD. - K0946+187 - K0946+517, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱144.6M | 90% | High risk85 | Flagged0.027 |
| 24I00038CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BORONGAN - GUIUAN RD. - K0946+517 - K0946+847, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱144.7M | 94% | High risk85 | Flagged0.026 |
| 24IJ0050(RE-ADVERTISED) OO1: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CALBAYOG CITY COASTAL ROAD, PACKAGE 5A, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱144.2M | 81% | High risk83 | Flagged0.022 |
| 25I00112BRIDGE PROGRAM - REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES - PEÑA BR. (B00333SM) ALONG MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR.), SAMAR 1ST DEO | Region VIII | Region VIII | On-Going | ₱38.6M | 0% | Medium risk51 | Flagged0.016 |
| 18II0063CONSTRUCTION OF MISSING LINKS/NEW ROADS, ARTECHE - BRGY. CATUMSAN - JIPAPAD - LAS NAVAS - CATUBIG - RAWIS ROAD (NORTHERN SAMAR SIDE), INCL. ROW, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Terminated | ₱14.5M | 100% | High risk79 | Flagged0.011 |
| 19I00120ASSET PRESERVATION / REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS, CATBALOGAN DIVERSION RD. - KO801+(-850) - KO801+510, SAMAR | Region VIII | Region VIII | Completed | ₱236.4M | 100% | High risk84 | Flagged0.009 |
| 24I00032CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BORONGAN - GUIUAN RD. - K0944+882 - K0945+219, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱144.6M | 0% | High risk69 | Flagged0.009 |
| 17I00046CONSTRUCTION OF WESTERN LEYTE PROVINCIAL HOSPITAL IN BAYBAY, LEYTE, WESTERN LEYTE PROVINCIAL HOSPITAL, BRGY. COGON, BAYBAY CITY, LEYTE | Region VIII | Region VIII | Completed | ₱149M | 100% | Medium risk55 | Flagged0.008 |
| 17IJ0123CONCRETING OF GANDARA-MATUGUINAO ACCESS ROAD(PHASE III) SAMAR 1ST LD | Region VIII | Samar 1st DEO | Completed | ₱90.9M | 100% | High risk62 | Flagged0.007 |
| 25I00101BRIDGE - WIDENING OF PERMANENT BRIDGES - MAWO PARALLEL BR. (B00599SM) ALONG MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR.) (PHASE II) | Region VIII | Region VIII | On-Going | ₱159.2M | 35% | High risk67 | Flagged0.006 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 22IG0038CONSTRUCTION OF MARAO FLOOD CONTROL STRUCTURE, MARAO RIVER BASIN,RIGHT SIDE BANK, BRGY.GUINSANGAAN,INOPACAN, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱95.5M | 100% | High risk63 | —-0.069 |
| 52 | 17IJ0046IMPROVEMENT/WIDENING OF DAANG MAHARLIKA (SM)(SAN ISIDRO-SAN JUANICO BRIDGE)K0742+000-K0742+0054;K0742+086-K0742+798;K0742+820-K0743+374;K0759+000-K0760+769;K0760+813-K0761+693 (INCLUDING RROW PAYMENT)SAMAR 1ST LD | Region VIII | Samar 1st DEO | Completed | ₱114M | 100% | High risk62 | —-0.045 |
| 53 | 24IJ0104OO1: WIDENING OF PERMANENT BRIDGES: GANDARA 2 PARALLEL BR. ALONG GANDARA DIVERSION ROAD (PHASE II) | Region VIII | Samar 1st DEO | On-Going | ₱92.6M | 15% | High risk62 | Flagged0.003 |
| 54 | 23IJ0110(RE-ADVERTISED) OO1: WIDENING OF PERMANENT BRIDGES: GANDARA 2 PARALLEL BR. ALONG GANDARA DIVERSION ROAD | Region VIII | Samar 1st DEO | On-Going | ₱92.3M | 30% | High risk62 | Flagged0.000 |
| 55 | 17IJ0123CONCRETING OF GANDARA-MATUGUINAO ACCESS ROAD(PHASE III) SAMAR 1ST LD | Region VIII | Samar 1st DEO | Completed | ₱90.9M | 100% | High risk62 | Flagged0.007 |
| 56 | 17IL0006REHABILITATION/CONSTRUCTION OF ZONE 3 FLOOD REVETMENT CONTROL, ALONG SUBANG DAKU RIVER, STA. 0+000-STA. 0+920, ZONE 3, SOGOD, SOUTHERN LEYTE, LONE DISTRICT, BRGY. ZONE 3, SOGOD, SOUTHERN LEYTE | Region VIII | Southern Leyte 1st DEO | Completed | ₱46.7M | 100% | High risk62 | —-0.048 |
| 57 | 17IJ0093WIDENING OF DAANG MAHARLIKA (SM) (SN ISIDRO-SN JUANICO BRIDGE), K0695+020 K0696+183; K0696+307 K0697+000; K0699+000 K0699+039; K0699+071 K0702+800 (INCLUDING RROW PAYMENT) SAMAR 1ST LD | Region VIII | Samar 1st DEO | Completed | ₱148.4M | 100% | High risk62 | —-0.038 |
| 58 | 17FL0041CONST./WIDENING OF DOLOS-CALMAYON-CATANUSAN-CALATEO-SIPAYA ROAD, BULAN/JUBAN, SORSOGON, BULAN/JUBAN, | Region V | Sorsogon 2nd DEO | Completed | ₱29.4M | 100% | High risk61 | —-0.061 |
| 59 | 18IJ0052CONSTRUCTION OF CALBAYOG COASTAL - DIVERSION ROAD (PACKAGE A) AND SLOPE PROTECTION, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱132.5M | 100% | High risk61 | —-0.063 |
| 60 | 17FL0052CONSTRUCTION/WIDENING OF CORONCORON-CALPI-TAROMATA-GATE-STA. TERESITA ROAD, MATNOG/BULAN, SORSOGON | Region V | Sorsogon 2nd DEO | Completed | ₱29.4M | 100% | High risk61 | —-0.061 |
| 61 | 17IC0046NETWORK DEVELOPMENT-IMPROVEMENT/WIDENING OF NATIONAL ROADS-PRIMARY ROADS, PALO-CARIGARA-ORMOC ROAD, K0933+150 - K0935+382, K0935+460 - K0937+560, K0937+560 - K0938+076, K0929+920 - K0931+320, ALANGALANG, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱146.2M | 100% | High risk61 | —-0.038 |
| 62 | 17IJ0040IMPROVEMENT/WIDENING OF CALBAYOG DIVERSION ROAD(S00085SM) K0734+100 - K0736+957, SAMAR 1ST LD | Region VIII | Samar 1st DEO | Completed | ₱88.2M | 100% | High risk61 | —-0.049 |
| 63 | 21IL0134FLOOD CONTROL AND DRAINAGE - DRAINAGE / PROTECTION WORKS - CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - CONSTRUCTION OF ROAD SLOPE PROTECTION ALONG ROAD LEADING TO LIMASAWA HERITAGE SITE, LIMASA | Region VIII | Southern Leyte 1st DEO | Completed | ₱96.5M | 100% | High risk60 | —-0.063 |
| 64 | 22IK0008CONSTRUCTION OF BURI CIRCUMFERENTIAL ROAD AT BURI ISLAND, STA. 0+265.00 - STA. 0+590.00, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱96.5M | 100% | High risk60 | —-0.085 |
| 65 | 22IG0062ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - DAANG MAHARLIKA (LT) - K1000+888-K1000+920, K1002+810-K1002+939 | Region VIII | Leyte 5th DEO | Completed | ₱95.3M | 100% | High risk60 | —-0.082 |
| 66 | 22IG0059ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - DAANG MAHARLIKA (LT) - K0979+915-K0979+985 | Region VIII | Leyte 5th DEO | Completed | ₱95.3M | 100% | High risk60 | —-0.084 |
| 67 | 19I00098NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROAD, DAANG MAHARLIKA (SM) (SAN ISIDRO - SAN JUANICO BR.) - KO697+201.80 - KO697+216.10, KO697+216.10 - KO697+635, KO703+724 - KO704+000, KO705+000 - KO705+816, KO705+867 - KO706+000, SAMAR 1ST DEO | Region VIII | Region VIII | Completed | ₱94.6M | 100% | Medium risk60 | —-0.079 |
| 68 | 19I00018NETWORK DEVELOPMENT - ROAD WIDENING - TERTIARY ROADS, BAGAHUPI-BABATNGON-STA. CRUZ-BARUGO-CARIGARA ROAD, KO915+745 - KO918+559, LEYTE 1ST LD | Region VIII | Region VIII | Completed | ₱106.1M | 100% | Medium risk60 | —-0.082 |
| 69 | 23II0030PREVENTIVE MAINTENANCE, SECONDARY ROADS, PANGPANG-PALAPAG-MAPANAS-GAMAY-LAPINIG RD., K0809+480-K0817+000, 2ND DISTRICT, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱129.2M | 100% | Medium risk60 | —-0.076 |
| 70 | 17I00004IMPROVT./WIDENING OF NATIONAL ROADS, DAANG MAHARLIKA (S00002SM) (SAN ISIDRO-SAN JUANICO BRIDGE),KO686+700-KO688+370; KO685+000-KO686+000; KO691+690-KO692+000; KO688+370-KO688+500, NORTHERN SAMAR, 1ST LD | Region VIII | Region VIII | Completed | ₱120.4M | 100% | Medium risk60 | —-0.033 |
| 71 | 24IM0125CONSTRUCTION OF THREE-STOREY BUILDING, TESDA REGION VIII, REGIONAL OFFICE, TACLOBAN CITY | Region VIII | Tacloban City DEO | On-Going | ₱48.2M | 40% | Medium risk60 | —-0.033 |
| 72 | 17IG0096NETWORK DEVELOPMENT - IMPROVEMENT/WIDENING OF NATIONAL ROADS - PRIMARY ROADS - ALONG N1, DAANG MAHARLIKA (LT) - K0959+ (-205) - K0960+253, K0960+272 - K0960+304, K0965+491-K0965+492, K0965+586-K0965+628, K0966+100-K0967+193, K0967+209-K0969+000, K0972+857 | Region VIII | Leyte 5th DEO | Completed | ₱144.8M | 100% | Medium risk60 | —-0.040 |
| 73 | 17IJ0043IMPROVEMENT/WIDENING OF DAANG MAHARLIKA (SM)(SAN ISIDRO -SAN JUANICO BRIDGE) J0078+400.2-K0778+442;K0778+442-K0778+590;K0778-590-K0779+100;K0780+566-K0782+000;K0782+310-K0782+344;K0782+368-K0782+476;K0782+524-K0782+905;K0782+947-K0783+600;K0782+000-K0783+ | Region VIII | Samar 1st DEO | Completed | ₱88.9M | 100% | Medium risk60 | —-0.051 |
| 74 | 17IJ0034IMPROVEMENT/WIDENING OF DAANG MAHARLIKA (SM) (SAN ISIDRO-SAN JUANICO BR.) K0691+000 - K0691+510;K0692+548 - K0693+000;K0693+736 - K0694+000, SAMAR 1ST LD | Region VIII | Samar 1st DEO | Completed | ₱63.1M | 100% | Medium risk59 | —-0.058 |
| 75 | 21IB0044REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE SECONDARY ROADS, WRIGHT-TAFT - BORONGAN ROAD K0914+680 - K0914+780 | Region VIII | Eastern Samar DEO | On-Going | ₱89.7M | 98% | Medium risk59 | —-0.019 |