Contractor dossier
51 projects on file, including joint ventures this contractor is part of.
Total projects
51
Total budget
₱3.5B
Average progress
97.7%
Completion rate
92.2%
Average risk score
55.6
Medium risk on average, out of 100
Flagged as unusual
6
11.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 23 | ₱1.2B | 54.2 | 2 | 99.5% |
| Cordillera Administrative Region | 6 | ₱355.3M | 53.4 | 2 | 100.0% |
| Region IV-A | 6 | ₱281.8M | 46.1 | 0 | 83.3% |
| Region V | 5 | ₱558.3M | 62.0 | 0 | 100.0% |
| Region II | 4 | ₱249M | 62.9 | 0 | 100.0% |
| Region IV-B | 3 | ₱379.8M | 64.7 | 1 | 100.0% |
| Region VII | 1 | ₱289.5M | 63.7 | 1 | 95.5% |
| Region IX | 1 | ₱99.7M | 61.0 | 0 | 100.0% |
| Region X | 1 | ₱118.9M | 57.4 | 0 | 100.0% |
| Region XIII | 1 | ₱32.3M | 52.0 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 26 | ₱1.9B | 55.3 | 0 | 96.2% |
| Flood Control and Drainage | 14 | ₱602M | 51.0 | 2 | 100.0% |
| Buildings and Facilities | 6 | ₱436.8M | 47.1 | 1 | 99.3% |
| OTHER | 4 | ₱484.6M | 81.5 | 3 | 97.2% |
| Bridges, Roads | 1 | ₱91.7M | 71.3 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 20I00055ROAD OPENING/CONCRETING OF CONCEPTION - TAPUL - NAWL - PAGSANGHAN - ANAGASE - STO. NIÑO - MAYDOLOBE - SARAO CANVALS - CARANAS ROAD, PARANAS - MOTIONG SAMAR (PHASE I), SAMAR 2ND LD | Region VIII | Region VIII | On-Going | ₱143.9M | 92% | High risk84 | Flagged0.045 |
| 20I00065ROAD OPENING/CONCRETING OF CONCEPTION - TAPUL - NAWL - PAGSANGHAN - ANAGASE - STO. NIÑO - MAYLOBE - SARAO CANVAIS - CARANAS ROAD, PARANAS - MOTIONG, SAMAR (PHASE II), SAMAR 2ND LD | Region VIII | Region VIII | On-Going | ₱143.9M | 96% | High risk84 | Flagged0.040 |
| 18IC0035CONST. OF BY-PASS AND DIVERSION ROAD, PALO WEST BY-PASS ROAD, PALO, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱96.9M | 100% | High risk82 | —-0.025 |
| 19E00004CONST. OF MISSING LINK/NEW ROADS, MINDORO ISLAND CIRCUMFERENTIAL ROAD (PUERTO GALERA - ABRA DE ILOG), KO015+240.00 - KO015+376.00; KO015+376.00 - KO018+059.00, ORIENTAL MINDORO | Region IV-B | Region IV-B | Completed | ₱100M | 100% | High risk76 | Flagged0.002 |
| 18F00072OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS DARAGA, ALBAY DIVERSION ROAD, ALBAY, DARAGA, ALBAY PROVINCE | Region V | Region V | Completed | ₱217.8M | 100% | High risk73 | —-0.046 |
| 17BB0043CONST/IMPROV'T OF ACCESS RDS LEADING TO AIRPORTS,SEAPORT &DECLARED TOURISM DESTINATIONS CONST.OF CONC.RD, CONST.OF CONC BR & ROW ACQUISITION POBLCN STA. ANA-MAREDE-SINAGO RD LEADING TO BOACAG FALLS &SINAGO COVES- BR & ROW, STACLARA-PATUNUNGAN,STA.ANA,CAG. | Region II | Cagayan 1st DEO | Completed | ₱91.7M | 100% | High risk71 | —-0.012 |
| 17BB0001CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF PARED RIVER CONTROL PROJECT, ASASSI SECTION, BAGGAO, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱46.3M | 100% | High risk65 | —-0.017 |
| 19F00028CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS: MATNOG-BULAN-MAGALLANES TOURISM WEST COAST HIGHWAY (SECTION 3), MAGALLANES, SORSOGON, MAGALLANES, SORSOGON (1ST LEGISLATIVE DISTRICT | Region V | Region V | Completed | ₱106.2M | 100% | High risk65 | —-0.077 |
| 17BB0013MFO1-NAT'L RD NETWORK SERVICES-NETWORK DEV'T-OFF-CARRIAGEWAY IMPROV'T INCLUDING DRAINAGE-TERTIARY-OFF-CARRIAGEWAY IMPROV'T-SHOULDER PAVING/CONSTRUCTION - BBDSMR, K0524+000-K0524+730 TO K0532.635-K0533+160, CENTRO-ASSASI, BAGGAO, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱46.7M | 100% | High risk64 | —-0.039 |
| 18IA0062ROAD WIDENING - BILIRAN CIRCUMFERENTIAL ROAD, K1008+360-K1010+490, K1011+480-K1011+690, K1011+740-K1012+093,K1012+134-K1013+490 (11.4738, 124.4695-11.4788, 124.5436, 11.4862, 124.4503-11.4878, 124.4495, 11.4882, 124.4494-11.4912,..,PROVINCE OF BILIRAN | Region VIII | Biliran DEO | Completed | ₱139.6M | 100% | High risk64 | —-0.073 |
| 22H00042LOCAL PROGRAM, NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER STRUCTURES - MULTI-PURPOSE/FACILITIES, CONSTRUCTION OF PCOO VISAYAS HUB BUILDING IN BARANGAY SUBANGDAKU, MANDAUE CITY | Region VII | Region VII | On-Going | ₱289.5M | 96% | High risk64 | Flagged0.003 |
| 19F00043OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, JUBAN-BULAN DIVERSION ROAD (JUBAN SECTION), SORSOGON, STA. 606+460.00-STA.607+625.32, JUBAN, SORSOGON (2ND LEGISLATIVE DISTRICT) | Region V | Region V | Completed | ₱71.5M | 100% | High risk62 | —-0.080 |
| 19J00102WIDENING OF JOLO-TAGLIBI - TIPTIPON NATIONAL ROAD, PANAMAO, SULU | Region IX | Region IX | Completed | ₱99.7M | 100% | High risk61 | —-0.060 |
| 18E00054WIDENING OF PUERTO PRINCESA SOUTH ROAD FROM TWO(2) TO SIX (6) LANES INCL DRAINAGE STRUCTRES AND OTHER ANCILLARY WORKS K0110+400-K0110+740; K0111+300-K0111+439; K0111+455-K0111+677; K0111+693-K0113+714; K0113+736-K0113+770, NARRA, PALAWAN | Region IV-B | Region IV-B | Completed | ₱144.8M | 100% | High risk60 | —-0.039 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 20I00055ROAD OPENING/CONCRETING OF CONCEPTION - TAPUL - NAWL - PAGSANGHAN - ANAGASE - STO. NIÑO - MAYDOLOBE - SARAO CANVALS - CARANAS ROAD, PARANAS - MOTIONG SAMAR (PHASE I), SAMAR 2ND LD | Region VIII | Region VIII | On-Going | ₱143.9M | 92% | High risk84 | Flagged0.045 |
| 20I00065ROAD OPENING/CONCRETING OF CONCEPTION - TAPUL - NAWL - PAGSANGHAN - ANAGASE - STO. NIÑO - MAYLOBE - SARAO CANVAIS - CARANAS ROAD, PARANAS - MOTIONG, SAMAR (PHASE II), SAMAR 2ND LD | Region VIII | Region VIII | On-Going | ₱143.9M | 96% | High risk84 | Flagged0.040 |
| 17PL0218PACKAGE 5: A) MALIN-AWA FLOOD CONTROL ALONG CHICO RIVER, B) ISLA BADO DANGWA FLOOD CONTROL ALONG CHICO RIVER, C) PUGO FLOOD CONTROL ALONG CHICO RIVER | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱81M | 100% | Medium risk58 | Flagged0.023 |
| 17PL0185PACKAGE 17: A) TOMIAGAN FLOOD CONTROL ALONG PASIL RIVER, B) DAO CREEK FLOOD CONTROL, C) NANENG FLOOD CONTROL ALONG CHICO RIVER, D) PINAGAN FLOOD CONTROL ALONG CHICO RIVER | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱78.8M | 100% | Medium risk58 | Flagged0.016 |
| 22H00042LOCAL PROGRAM, NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER STRUCTURES - MULTI-PURPOSE/FACILITIES, CONSTRUCTION OF PCOO VISAYAS HUB BUILDING IN BARANGAY SUBANGDAKU, MANDAUE CITY | Region VII | Region VII | On-Going | ₱289.5M | 96% | High risk64 | Flagged0.003 |
| 19E00004CONST. OF MISSING LINK/NEW ROADS, MINDORO ISLAND CIRCUMFERENTIAL ROAD (PUERTO GALERA - ABRA DE ILOG), KO015+240.00 - KO015+376.00; KO015+376.00 - KO018+059.00, ORIENTAL MINDORO | Region IV-B | Region IV-B | Completed | ₱100M | 100% | High risk76 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 17DJ0100CONSTRUCTION OF FOUR (4) STOREY REGULAR WORKSHOP AT LUCENA DALAHICAN NATIONAL HIGH SCHOOL, LUCENA CITY | Region IV-A | Quezon 2nd DEO | Completed | ₱24.7M | 100% | Medium risk40 | —-0.021 |