Contractor dossier
127 projects on file, including joint ventures this contractor is part of.
Total projects
127
Total budget
₱3.5B
Average progress
94.0%
Completion rate
86.6%
Average risk score
46.7
Medium risk on average, out of 100
Flagged as unusual
6
4.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 127 | ₱3.5B | 46.7 | 6 | 94.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 58 | ₱1.5B | 47.6 | 3 | 93.6% |
| Buildings and Facilities | 35 | ₱246.3M | 39.7 | 1 | 93.2% |
| Flood Control and Drainage | 28 | ₱1.2B | 51.7 | 1 | 97.7% |
| Bridges, Roads | 3 | ₱348.2M | 59.7 | 1 | 71.3% |
| OTHER | 2 | ₱178.8M | 71.2 | 0 | 100.0% |
| Water Provision and Storage | 1 | ₱1.9M | 22.1 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24A00478REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS- PRIMARY ROADS, MANILA NORTH ROAD - K0491 + 700 - K0492 + 000 | Region I | Region I | On-Going | ₱5.8M | 100% | High risk78 | —-0.001 |
| 24AA0402CONCRETING OF BRGY. NALBO FMR, BRGY. NALBO, LAOAG CITY, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱19.1M | 72% | High risk76 | Flagged0.023 |
| 23A00095CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURES, SAMAC SWIP, BUGNAY SWIP, BINGAO SWIP SMALL WATER IMPOUNDING PROJECTS BRGYS. STA ASUNCION, SAN AGUSTIN AND SAN PEDRO, SAN NICOLAS, ILO | Region I | Region I | Completed | ₱193M | 100% | High risk74 | —-0.033 |
| 24A00485CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LAOAG-SAN NICOLAS BY-PASS ROAD, SAN NICOLAS ROAD SECTION, SAN NICOLAS, ILOCOS NORTE | Region I | Region I | On-Going | ₱123M | 93% | High risk71 | —-0.027 |
| 22A00066CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LAOAG-SAN NICOLAS BYPASS ROAD (SAN NICOLAS SECTION), ILOCOS NORTE | Region I | Region I | Completed | ₱43.2M | 100% | High risk70 | —-0.080 |
| 25A00168CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - LAOAG-SAN NICOLAS BY-PASS ROAD, (SAN NICOLAS SECTION), PACKAGE B, ILOCOS NORTE | Region I | Region I | On-Going | ₱46.8M | 20% | High risk70 | —-0.020 |
| 23AA0026CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BUAGAO RIVER (LEFT AND RIGHT BANK) BARANGAY SAN LORENZO AND ABACA, BANGUI, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱29.4M | 100% | High risk70 | —-0.064 |
| 25AA0038FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BANBAN RIVER, BARANGAY TAGUIPORO, BANGUI, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱37.6M | 92% | High risk70 | —-0.029 |
| 25AA0122FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BANBAN RIVER, BARANGAY BARUYEN, BANGUI, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱37.6M | 100% | High risk70 | —-0.064 |
| 23AB0089CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-PRIMARY ROADS, MANILA NORTH RD K0483+440 - K0484+000 | Region I | Ilocos Norte 2nd DEO | Completed | ₱5.8M | 100% | High risk70 | —-0.084 |
| 23AB0072CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY ROOT, DINGRAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱39.2M | 100% | High risk70 | —-0.074 |
| 25AB0162BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. MAGLAOI NORTE, CURRIMAO ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | On-Going | ₱4.9M | 0% | High risk69 | Flagged0.011 |
| 23AA0057FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BANBAN RIVER, SITIO TALNA, BARANGAY TAGUIPORO, BANGUI, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱49M | 100% | High risk69 | —-0.064 |
| 18AA0376CONST./IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATION, VIRBIRA-BARBAQUEZO ROAD NETWORK LEADING TO SABO DAM, BRGY. BARBAQUEZO, CARASI, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱29.3M | 100% | High risk69 | —-0.080 |
| 21AB0137LOCAL INFRASTRUCTURE PROGRAM, REHABILITATION/IMPROVEMENT OF BADOC-APATOT ROAD (KM 449.501 - 453.080) BADOC, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱15.4M | 100% | High risk68 | —-0.083 |
| 19A00089CONSTRUCTION/ REPAIR/ REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCL. LOCAL PROJECTS (VIILP), IMPROVEMENT/ CONCRETING OF PAOAY LAKE CIRCUMFERENTIAL ROAD AND MALACAÑANG TO AMIANAN, PAOAY, ILOCOS NORTE | Region I | Region I | Completed | ₱115.8M | 100% | High risk68 | —-0.066 |
| 18AA0417REHAB. OF MUNICIPAL AUDITORIUM, CARASI, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱15M | 100% | High risk67 | —-0.081 |
| 25A00223CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN), ILOCOS FLY-IN CRUISE ROAD, CURRIMAO AND PAOAY, ILOCOS NORTE | Region I | Region I | On-Going | ₱181.8M | 14% | High risk65 | Flagged0.017 |
| 23A00279CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LAOAG-SAN NICOLAS BYPASS ROAD (SAN NICOLAS SECTION), ILOCOS NORTE | Region I | Region I | Completed | ₱173M | 100% | High risk65 | —-0.019 |
| 17AB0031ROAD IMPROVEMENT/CONCRETING OF CIRCUMFERENTIAL ROAD LEADING TO JUAN LUNA SHRINE, LA VIRGEN MILAGROSA SHRINE AND OTHER ACCESS ROADS, BADOC, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱44.7M | 100% | High risk64 | —-0.048 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24AA0402CONCRETING OF BRGY. NALBO FMR, BRGY. NALBO, LAOAG CITY, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱19.1M | 72% | High risk76 | Flagged0.023 |
| 25A00223CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN), ILOCOS FLY-IN CRUISE ROAD, CURRIMAO AND PAOAY, ILOCOS NORTE | Region I | Region I | On-Going | ₱181.8M | 14% | High risk65 | Flagged0.017 |
| 25AB0162BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. MAGLAOI NORTE, CURRIMAO ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | On-Going | ₱4.9M | 0% | High risk69 | Flagged0.011 |
| 17AB0054CONCRETING OF BRGY. STA. CRUZ FMR, BRGY. STA. CRUZ, BADOC, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱1.9M | 100% | Low risk17 | Flagged0.004 |
| 17AB0249REPAIR AND MAINTENANCE OF EXISTING DIKE ALONG SOLSONA RIVER, LEFT SIDE,SOLSONA,ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱4.5M | 100% | Low risk23 | Flagged0.004 |
| 17AB0053CONCRETING OF BRGY. MADUPAYAS-CAMANGA FMR, BRGY. MADUPAYAS, BADOC, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱1.9M | 100% | Low risk17 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 25AB0015SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, IMPROVEMENT OF ROAD AT BARANGAY LILIPUTEN, PINILI, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | On-Going | ₱9.6M | 73% | Medium risk50 | —-0.040 |
| 52 | 20A00053CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS - ILOCOS FLY-IN CRUISE ROAD, CURRIMAO AND PAOAY, ILOCOS NORTE | Region I | Region I | Completed | ₱78.7M | 100% | Medium risk50 | —-0.079 |
| 53 | 19AB0097CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES, ECONOMIC ZONES, BRGY. BINACAG ROAD CONNECTING TO COFFEE PROCESSING INDUSTRY, BANNA, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱41.2M | 100% | Medium risk50 | —-0.079 |
| 54 | 25AB0092SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY CAMANGA, BADOC, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | On-Going | ₱21.7M | 21% | Medium risk50 | —-0.022 |
| 55 | 19AB0082CONSTRUCTION/ REPAIR/ REHABILITATION /IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO COFFEE PROCESSING INDUSTRY, BRGY. BINACAG, BANNA, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱19.6M | 100% | Medium risk49 | —-0.083 |
| 56 | 23A00086CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BADOC RIVER, BARANGAY BALBALDEZ, BADOC, ILOCOS NORTE | Region I | Region I | Completed | ₱48.2M | 100% | Medium risk49 | —-0.065 |
| 57 | 23A00067CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG QUIAOIT RIVER (UPSTREAM OF NALASIN BRIDGE) BARANGAY NALASIN, PAOAY, ILOCOS NORTE | Region I | Region I | Completed | ₱48.2M | 100% | Medium risk49 | —-0.065 |
| 58 | 23A00025CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, DARAYDAY ROAD (LAOAG CITY SECTION), ILOCOS NORTE | Region I | Region I | Completed | ₱21.9M | 100% | Medium risk49 | —-0.083 |
| 59 | 25AB0093SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY NAGREBCAN TO BARANGAY BALBALDEZ, BADOC, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | On-Going | ₱21.7M | 30% | Medium risk49 | —-0.027 |
| 60 | 18AB0073CONCRETING OF BRGY. MABUTI FMR, BRGY. MABUTI, MARCOS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱5M | 100% | Medium risk48 | —-0.031 |
| 61 | 19AB0124CONCRETING OF BRGY. ESCODA FMR, BRGY. ESCODA, MARCOS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱5M | 100% | Medium risk48 | —-0.029 |
| 62 | 21AB0033CONSTRUCTION/IMPROVEMENT OF CIRCUMFERENCIAL ROAD LEADING TO JUAN LUNA SHRINE, LA VIRGEN MILAGROSA SHRINE AND OTHER ACCESS ROADS, BADOC, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱49M | 100% | Medium risk48 | —-0.080 |
| 63 | 23AB0014REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS, PINILI-NUEVA ERA RD - K0456 + 930 - K0457 + 035, K0467 + 000 - K0467 + 174 | Region I | Ilocos Norte 2nd DEO | Completed | ₱9.6M | 100% | Medium risk48 | —-0.083 |
| 64 | 24AB0094CONCRETING OF BRGY. UPON FMR, BRGY. UPON, PINILI, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱14.9M | 100% | Medium risk48 | —-0.027 |
| 65 | 23AB0112CONSTRUCTION OF CONCRETE PAVING, PAOAY-SIDEG-BATAC ROAD, BRGY. NO. 31, SIDEG, PAOAY, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱29.7M | 100% | Medium risk48 | —-0.078 |
| 66 | 19AB0096IMPROVEMENT/CONCRETING OF ROAD LEADING SAND DUNES (ONSE REEF), PAOAY, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱46M | 100% | Medium risk47 | —-0.077 |
| 67 | 22AB0145CONCRETING OF SITIO BUGA TO CURRIMAO ROAD, BRGY. SIDEG FMR, BRGY. SIDEG, PAOAY, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱19.9M | 100% | Medium risk47 | —-0.028 |
| 68 | 24A00424BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BADOC RIVER, BARANGAY MABUSAG SUR, BADOC, ILOCOS NORTE | Region I | Region I | Completed | ₱53.5M | 100% | Medium risk47 | —-0.065 |
| 69 | 18AB0074CONCRETING OF SITIO CABITNUNGAN-CAGOOT, UPON FMR, BRGY. UPON, PINILI, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱6M | 100% | Medium risk47 | —-0.032 |
| 70 | 22AB0006REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS, PINILI-NUEVA ERA ROAD, K0456+473 - K0456+930 | Region I | Ilocos Norte 2nd DEO | Completed | ₱9.8M | 100% | Medium risk46 | —-0.084 |
| 71 | 21AB0106REHABILITATION/IMPROVEMENT OF BADOC-NAGREBCAN ROAD (KM449.616 - 457.095), BADOC, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱6.8M | 100% | Medium risk46 | —-0.084 |
| 72 | 23A00102CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BADOC RIVER, BARANGAY LUBIGAN, BADOC, ILOCOS NORTE | Region I | Region I | Completed | ₱48.2M | 100% | Medium risk46 | —-0.065 |
| 73 | 20AB0106REPAIR/REHABILITATION OF PROVINCIAL ROAD ALONG PALTIT-BALBALDEZ INTERMITTENT SECTION, BRGY. PALTIT & BALBALDEZ, BADOC, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱19M | 100% | Medium risk46 | —-0.084 |
| 74 | 23AB0150CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG NAGRANGTAYAN CREEK (UPSTREAM AND DOWNSTREAM OF NAGRANTAYAN BRIDGE), PAOAY, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱9.7M | 100% | Medium risk46 | —-0.067 |
| 75 | 23A00072CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BADOC RIVER, BARANGAY SAN JULIAN, BADOC, ILOCOS NORTE | Region I | Region I | Completed | ₱48.2M | 100% | Medium risk46 | —-0.065 |