108 projects on file, including joint ventures this contractor is part of.
Total projects
108
Total budget
₱7.5B
Average progress
95.6%
Completion rate
82.4%
Average risk score
53.9
Medium risk on average, out of 100
Flagged as unusual
7
6.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Cordillera Administrative Region | 98 | ₱6.5B | 54.2 | 6 | 96.0% |
| Region IV-B | 8 | ₱741.7M | 50.7 | 1 | 89.2% |
| Region I | 1 | ₱154.4M | 61.9 | 0 | 100.0% |
| Region XIII | 1 | ₱49.5M | 40.6 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 78 | ₱5.9B | 51.2 | 1 | 96.6% |
| Flood Control and Drainage | 10 | ₱636.1M | 54.4 | 1 | 97.8% |
| Buildings and Facilities | 9 | ₱252.9M | 46.5 | 0 | 99.4% |
| OTHER | 5 | ₱381.4M | 77.2 | 1 | 94.8% |
| GAA 2025 OO-1 | 3 | ₱285.1M | 95.1 | 3 | 51.1% |
| Bridges | 2 | ₱55.1M | 50.4 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱4.9M | 93.8 | 1 | 92.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25P00001ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - MT PROV-ILOCOS SUR VIA TUE RD - K0388+770-K0388+870 | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱95M | 0% | High risk95 | Flagged0.027 |
| 25P00020REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - MT PROV-ILOCOS SUR VIA TUE RD - K0388 + 500 - K0388 + 635 | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱95.1M | 86% | High risk95 | Flagged0.005 |
| 25P00022REHABILITATION/ RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - BAGUIO - BONTOC RD, K0376+000 - K0391+000BONTOC, MT. PROVINCE | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱95M | 67% | High risk95 | Flagged0.011 |
| 25PI0086CONSTRUCTION/REHABILITATION OF LOCAL ROAD, ABUNGO - SUMADEL, TADIAN, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | On-Going | ₱4.9M | 92% | High risk94 | Flagged0.013 |
| 23PK0059ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM: REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS: KALINGA - ABRA RD - K0500+610 - 500+656, BALBALAN, KALI | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱96.5M | 100% | High risk82 | —-0.012 |
| 24PM0040CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF MULIANG BRIDGE A | Cordillera Administrative Region | Mountain Province 2nd DEO | On-Going | ₱72.4M | 74% | High risk78 | Flagged0.013 |
| 22P00097CONSTRUCTION OF ROAD, TINONGDAN PROPER - CAYUCO - CAWAYAN ROAD, ITOGON, BENGUET | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱96.4M | 100% | High risk77 | —-0.011 |
| 17PE0024CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS, AND DECLARED TOURISM DESTINATIONS BALLAY-TABIO-TONOMAN-BULALACAO-TAWANGAN-LUSOD ROAD LEADING TO BULALACAO LAKES AND MT. TABEO, KABAYAN, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | Completed | ₱96.5M | 100% | High risk76 | —-0.016 |
| 24PI0033CSSP-ROLL-IT, MASLA-DUAGAN ROAD IN SUPPORT OF SUGARCANE, COFFEE, FOOD PROCESSING AND FURNITURE INDUSTRIES, TADIAN, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | Completed | ₱19.6M | 100% | High risk74 | —-0.026 |
| 17PE0036CONSTRUCTION OF CHOGONG-DANAS FLOODCONTROL, KABAYAN, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | Completed | ₱4.8M | 100% | High risk67 | —-0.043 |
| 17PE0037CONSTRUCTION OF BINANGDOLAO FLOODCONTRO, KABAYAN, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | Completed | ₱9.5M | 100% | High risk65 | —-0.044 |
| 24P00024CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF LENGTAN FLOOD CONTROL ALONG CHICO RIVER, SAMOKI, BONTOC, MOUNTAIN PROVINCE | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱193M | 90% | High risk65 | Flagged0.007 |
| 17PG0026REHABILITATION/ RECONSTRUCTION OF NATIONAL ROAD WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG BANAUE-HUNGDUAN-BENGUET BOUNDARY ROAD, HUNGDUAN, IFUGAO, K0360+022 - K0360+043, K0360+089 - K0360+144, K0360+080 - K0360+193.90, K0361+418 - K0361+500,.. | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱82.5M | 100% | High risk63 | —-0.037 |
| 24A00277CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BARORO RIVER, BARANGAY BAMBANAY, SAN JUAN, LA UNION | Region I | Region I | Completed | ₱154.4M | 100% | High risk62 | —-0.044 |
| 23E00098SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF PUERTO PRINCESA WEST COASTAL BYPASS ROAD, BRGY. BACUNGAN-SIMPOCAN, PTO. PRINCESA CITY, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱187.8M | 52% | High risk61 | Flagged0.003 |
| 23PL0059ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - MT. PROVINCE BDRY-CALANAN-PINUKPUK-ABBUT RD (CAGAL | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱95.5M | 100% | High risk60 | —-0.034 |
| 19PA0066CONSTRUCTION OF MISSING LINKS/NEW ROADS, ABRA-CERVANTES ROAD, CH 3420-CH 4670 | Cordillera Administrative Region | Abra DEO | Completed | ₱49M | 100% | High risk60 | —-0.047 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25P00001ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - MT PROV-ILOCOS SUR VIA TUE RD - K0388+770-K0388+870 | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱95M | 0% | High risk95 | Flagged0.027 |
| 25PI0086CONSTRUCTION/REHABILITATION OF LOCAL ROAD, ABUNGO - SUMADEL, TADIAN, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | On-Going | ₱4.9M | 92% | High risk94 | Flagged0.013 |
| 24PM0040CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF MULIANG BRIDGE A | Cordillera Administrative Region | Mountain Province 2nd DEO | On-Going | ₱72.4M | 74% | High risk78 | Flagged0.013 |
| 25P00022REHABILITATION/ RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - BAGUIO - BONTOC RD, K0376+000 - K0391+000BONTOC, MT. PROVINCE | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱95M | 67% | High risk95 | Flagged0.011 |
| 24P00024CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF LENGTAN FLOOD CONTROL ALONG CHICO RIVER, SAMOKI, BONTOC, MOUNTAIN PROVINCE | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱193M | 90% | High risk65 | Flagged0.007 |
| 25P00020REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - MT PROV-ILOCOS SUR VIA TUE RD - K0388 + 500 - K0388 + 635 | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱95.1M | 86% | High risk95 | Flagged0.005 |
| 23E00098SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF PUERTO PRINCESA WEST COASTAL BYPASS ROAD, BRGY. BACUNGAN-SIMPOCAN, PTO. PRINCESA CITY, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱187.8M | 52% | High risk61 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 21P00008ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIP, SLOPE COLLAPSE AND LANDSLIDES - PRIMARY ROADS, KENNON ROADKO234+910 - KO235+020, KO238+870 - KO238 | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱173.7M | 100% | Medium risk58 | —-0.053 |
| 27 | 20P00029ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS KENNON ROADKO228+067 - KO228+170KO229+090 - KO229+2 | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱243.8M | 100% | Medium risk58 | —-0.044 |
| 28 | 18PA0135REHABILITATION/IMPROVEMENT OF MADEGNAK-AGSIMAO ROAD, TINEG, ABRA | Cordillera Administrative Region | Abra DEO | Completed | ₱96.4M | 100% | Medium risk58 | —-0.071 |
| 29 | 19P00003ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES (PRIMARY ROADS) ALONG KENNON ROAD, K0233+685 - K0233+889, K0234+000 - K0 | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱144.8M | 100% | Medium risk58 | —-0.060 |
| 30 | 21P00026ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - REHABILITATION / RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS, KENNON ROAD - K0223 + 749 - K0223 + 890TUBA, BEN | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱193M | 100% | Medium risk58 | —-0.050 |
| 31 | 20P00006ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4B) | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱234.2M | 100% | Medium risk58 | —-0.048 |
| 32 | 22P00047REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - BENGUET - NUEVA VIZCAYA RD, KO284+450 - KO284+590BOKOD, BENGUET | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱144.8M | 100% | Medium risk58 | —-0.063 |
| 33 | 22P00048REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - BENGUET - NUEVA VIZCAYA RD, KO281+(-050) - KO281+155BOKOD, BENGUET | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱135.1M | 100% | Medium risk58 | —-0.066 |
| 34 | 18PA0099CONSTRUCTION OF MISSING LINKS / NEW ROADS (ROAD OPENING), BESAO - TUBO (VIA TAMBOAN), ABRA | Cordillera Administrative Region | Abra DEO | Completed | ₱96.2M | 100% | Medium risk57 | —-0.073 |
| 35 | 24P00026REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BAGUIO - BONTOC RD, KO390+410 - K0390+550BONTOC, MT. PROVINCE | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱96.5M | 100% | Medium risk56 | —-0.075 |
| 36 | 18PE0007CONSTRUCTION OF SLOPE PROTECTION STRUCTURE -BENGUET-NUEVA VIZCAYA ROAD, K0271+780 - 0271+824, ITOGON, BENGUET, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | Completed | ₱96.3M | 100% | Medium risk56 | —-0.071 |
| 37 | 24P00027REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BAGUIO - BONTOC RD, K0390+286 - K0390+410BONTOC, MT. PROVINCE | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱96.5M | 100% | Medium risk56 | —-0.077 |
| 38 | 22P00001ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS KENNON ROAD, KO241+650 - KO241+790CAMP 7, BAGUIO CI | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱118.6M | 100% | Medium risk56 | —-0.063 |
| 39 | 21P00037ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS GOV. BADO DANGWA NATIONAL ROADK0315 + 721 - K0315 | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱115.8M | 100% | Medium risk56 | —-0.072 |
| 40 | 22P00045REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - BENGUET - NUEVA VIZCAYA RD, KO293+245 - KO293+308BOKOD, BENGUET | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱115.8M | 100% | Medium risk56 | —-0.074 |
| 41 | 23E00051ASSET PRESERVATION PROGRAM- REHAB./RECONST. OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE- SECONDARY ROADS, PTO. PRINCESA NORTH ROAD, K0150+030-K0150+140, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱117.2M | 98% | Medium risk56 | —-0.023 |
| 42 | 21P00056ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - MT. PROVINCE - ILOCOS SUR VIA TUE ROAD, KO387+(- | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱96.5M | 100% | Medium risk56 | —-0.076 |
| 43 | 21P00057ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - MT. PROVINCE - ILOCOS SUR VIA TUE ROAD, KO389+87 | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱96.5M | 100% | Medium risk56 | —-0.076 |
| 44 | 21P00058ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - MT. PROVINCE - ILOCOS SUR VIA TUE ROAD, KO389+38 | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱96.5M | 100% | Medium risk56 | —-0.077 |
| 45 | 21P00028ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS CONG. ANDRES ACOP COSALAN ROAD K0315 + 115 - K0315 | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱96.5M | 100% | Medium risk56 | —-0.078 |
| 46 | 23P00019ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS - KENNON ROAD, K0241+798 -K0241+920BAGUIO CITY | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱96.5M | 100% | Medium risk56 | —-0.069 |
| 47 | 20PL0037CONSTRUCTION OF THREE-STOREY NATIONAL COMMISSION ON INDIGENOUS PEOPLE (NCIP) OFFICE BUILDING IN TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱34.3M | 100% | Medium risk56 | —-0.066 |
| 48 | 18PA0150REHABILITATION/IMPROVEMENT (WITH ROAD OPENING) OF MUDENG LIGUIS ROAD, LA PAZ, ABRA | Cordillera Administrative Region | Abra DEO | Completed | ₱77.1M | 100% | Medium risk55 | —-0.074 |
| 49 | 18PA0145ROAD OPENING OF STO TOMAS-LUZONG ROAD, MANABO AND LUBA, ABRA | Cordillera Administrative Region | Abra DEO | Completed | ₱77.1M | 100% | Medium risk55 | —-0.075 |
| 50 | 22PG0042CONSTRUCTION OF 14 SPECIL ACTION BATALLION (SAB) HEADQUARTERS, LAMUT, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱48.7M | 95% | Medium risk54 | —-0.026 |