Contractor dossier
11 projects on file, including joint ventures this contractor is part of.
Total projects
11
Total budget
₱949.6M
Average progress
100.0%
Completion rate
81.8%
Average risk score
64.7
High risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 8 | ₱618.7M | 64.4 | 0 | 99.9% |
| National Capital Region | 3 | ₱330.9M | 65.5 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 11 | ₱949.6M | 64.7 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24CC0149CONSTRUCTION/IMPROVEMENT OF SLOPE PROTECTION STRUCTURE AND WATERWAYS, BRGY. BAMBANG, BOCAUE, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱99M | 100% | High risk80 | —-0.050 |
| 24CC0268CONSTRUCTION/IMPROVEMENT OF SLOPE PROTECTION STRUCTURE AND WATERWAYS, BRGY. MANATAL, PANDI, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱99M | 100% | High risk80 | —-0.021 |
| 24CC0267CONSTRUCTION/IMPROVEMENT OF SLOPE PROTECTION STRUCTURE AND WATERWAYS, BARANGAY BAGBAGUIN, PANDI, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱99M | 100% | High risk80 | —-0.021 |
| 24CC0057CONSTRUCTION OF SLOPE PROTECTION STRUCTURE AND WATERWAYS, BARANGAY MALIS, GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱59.4M | 100% | High risk75 | —-0.061 |
| 23CC0508CONSTRUCTION (IMPROVEMENT) OF SLOPE PROTECTION STRUCTURE AND WATERWAYS AT BRGY. SANTO CRISTO, PULILAN, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱48.2M | 100% | High risk74 | —-0.007 |
| 24OB0186CONSTRUCTION OF SLOPE PROTECTION AT LAKESHORE, BARANGAY HAGONOY, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱141.8M | 100% | High risk67 | —-0.066 |
| 24OB0193CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG C-6 OPEN CHANNEL, (PHASE 7), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱94.6M | 100% | High risk65 | —-0.076 |
| 24OB0194CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG C-6 OPEN CHANNEL, (PHASE 8), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱94.6M | 100% | High risk65 | —-0.076 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24CC0149CONSTRUCTION/IMPROVEMENT OF SLOPE PROTECTION STRUCTURE AND WATERWAYS, BRGY. BAMBANG, BOCAUE, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱99M | 100% | High risk80 | —-0.050 |
| 2 | 24CC0268CONSTRUCTION/IMPROVEMENT OF SLOPE PROTECTION STRUCTURE AND WATERWAYS, BRGY. MANATAL, PANDI, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱99M | 100% | High risk80 | —-0.021 |
| 3 | 24CC0267CONSTRUCTION/IMPROVEMENT OF SLOPE PROTECTION STRUCTURE AND WATERWAYS, BARANGAY BAGBAGUIN, PANDI, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱99M | 100% | High risk80 | —-0.021 |
| 4 | 24CC0057CONSTRUCTION OF SLOPE PROTECTION STRUCTURE AND WATERWAYS, BARANGAY MALIS, GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱59.4M | 100% | High risk75 | —-0.061 |
| 5 | 23CC0508CONSTRUCTION (IMPROVEMENT) OF SLOPE PROTECTION STRUCTURE AND WATERWAYS AT BRGY. SANTO CRISTO, PULILAN, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱48.2M | 100% | High risk74 | —-0.007 |
| 6 | 24OB0186CONSTRUCTION OF SLOPE PROTECTION AT LAKESHORE, BARANGAY HAGONOY, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱141.8M | 100% | High risk67 | —-0.066 |
| 7 | 24OB0193CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG C-6 OPEN CHANNEL, (PHASE 7), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱94.6M | 100% | High risk65 | —-0.076 |
| 8 | 24OB0194CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG C-6 OPEN CHANNEL, (PHASE 8), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱94.6M | 100% | High risk65 | —-0.076 |
| 9 | 23CC0481CONSTRUCTION OF RIVER PROTECTION STRUCTURE ALONG BOCAUE RIVER STA. 03+237 TO STA. 03+437), BARANGAY CAINGIN, BOCAUE, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱72.4M | 100% | Medium risk48 | —-0.028 |
| 10 | 23CC0482CONSTRUCTION OF RIVER PROTECTION STRUCTURE ALONG GUIGUINTO RIVER (STA. 05+707 TO STA. 05+907), BARANGAY DAUNGAN, GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱72.4M | 100% | Medium risk44 | —-0.026 |
| 11 | 24CC0054CONSTRUCTION OF SLOPE PROTECTION STRUCTURE AND WATERWAYS, BARANGAY DAUNGAN, GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱69.3M | 100% | Medium risk35 | —-0.090 |