Opening the dossier…
Opening the dossier…
Contractor dossier
170 projects on file, including joint ventures this contractor is part of.
Total projects
170
Total budget
₱6.8B
Average progress
78.3%
Completion rate
66.5%
Below 70%
Average risk score
50.5
Medium risk on average, out of 100
Flagged as unusual
24
14.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 170 | ₱6.8B | 50.5 | 24 | 78.3% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 99 | ₱3.7B | 46.2 | 3 | 80.5% |
| Bridges | 25 | ₱779.4M | 46.6 | 5 | 74.3% |
| Flood Control and Drainage | 20 | ₱1.3B | 54.5 | 4 | 80.4% |
| Buildings and Facilities | 7 | ₱154M | 50.2 | 0 | 63.4% |
| OTHER | 6 | ₱243.8M | 73.8 | 5 | 81.0% |
| GAA 2025 OO-1 | 3 | ₱129.2M | 91.6 | 3 | 57.0% |
| GAA 2025 SSP | 3 | ₱56.5M | 88.4 | 2 | 63.0% |
| Water Provision and Storage | 3 | ₱53.7M | 38.0 | 0 | 100.0% |
| GAA 2025 OO-2 | 2 | ₱188M | 92.1 | 2 | 41.5% |
| Bridges, Roads | 2 | ₱259.3M | 61.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25AH0092INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES(ROADWAY LIGHTING)ALONG PANG.-ZAM.RD.-K0358+(-910) | Region I | Pangasinan 2nd DEO | On-Going | ₱48.1M | 89% | High risk95 | Flagged0.017 |
| 25AH0098CONSTRUCTION OF DRAINAGE STRUCTURE,BARANGAY BAAY, LINGAYEN, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱4.8M | 0% | High risk95 | Flagged0.041 |
| 25AH0088CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG AGNO RIVER,BRGY. PANGAPISAN NORTE TO BRGY. POBL | Region I | Pangasinan 2nd DEO | On-Going | ₱93.4M | 0% | High risk93 | Flagged0.022 |
| 25AH0081WIDENING OF PERMANENT BRIDGES AT GODOY BR.(B00672LZ) ALONG PANGASINAN-TARLAC RD.(PHASE II),MANGATARE | Region I | Pangasinan 2nd DEO | On-Going | ₱48M | 63% | High risk93 | Flagged0.009 |
| 25AH0089CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG AGNO RIVER BASIN,BARANGAY BUNLALACAO,MANGATAREM | Region I | Pangasinan 2nd DEO | On-Going | ₱94.6M | 83% | High risk92 | Flagged0.000 |
| 25AH0084WIDENING OF PERMANENT BRIDGES AT CURAMBENG BR.(B02147LZ)ALONG PANGASINAN-ZAMBALES RD.(PHASE II),BINM | Region I | Pangasinan 2nd DEO | On-Going | ₱42.8M | 71% | High risk91 | Flagged0.006 |
| 25AH0082WIDENING OF PERMANENT BRIDGES AT CARPIO BR.(B00674LZ)ALONG PANGASINAN-TARLAC RD.(PHASE II),MANGATARE | Region I | Pangasinan 2nd DEO | On-Going | ₱38.4M | 37% | High risk91 | Flagged0.014 |
| 24AH0165CONST'N. OF FOUR(4) STOREY,TWENTY FOUR(24) CL, S/B. AT MANGATAREM 1 CENTRAL SCHOOL,MANGATAREM, PANGA | Region I | Pangasinan 2nd DEO | On-Going | ₱71.6M | 84% | High risk88 | Flagged0.052 |
| 23A00151CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LINGAYEN-BINMALEY BYPASS ROAD, BINMALEY SIDE, PANGASINAN | Region I | Region I | On-Going | ₱100.4M | 50% | High risk79 | Flagged0.034 |
| 25AH0093INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES(OFF-CARRIAGEWAY IMPRV'T.PAVEMENT MARKINGS,ROAD SI | Region I | Pangasinan 2nd DEO | Completed | ₱3.6M | 100% | High risk75 | —-0.021 |
| 23AH0082CONSTRUCTION (CONCRETING) OF ROAD, BRGY. CALOOCAN NORTE, BINMALEY, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱9.9M | 100% | High risk74 | Flagged0.003 |
| 24AH0131CONSTRUCTION(COMPLETION)OF MPB,MANGATAREM CENTRAL SCHOOL BLDG.MANGATAREM, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱39.6M | 100% | High risk73 | —-0.004 |
| 24AH0085CONST'N./IMPROV'T.OF ACCESS RD.LEADING TO MANIBOC-PANGAPISAN NORTH RD.CONNECTING ALVEAR ST.(PROV'L.R | Region I | Pangasinan 2nd DEO | On-Going | ₱19M | 52% | High risk72 | Flagged0.018 |
| 17A00044NETWORK DEVELOPMENT - IMPROVEMENT/ WIDENING OF NATIONAL ROADS ALONG URDANETA JCT - DAGUPAN RD, K0197+268 - K0198+960; K0199+320 - K0200+870 | Region I | Region I | Completed | ₱96.4M | 100% | High risk68 | —-0.044 |
| 17A00001NETWORK DEVELOPMENT, IMPROVEMENT/ WIDENING OF NATIONAL ROADS ALONG MANILA NORTH ROAD, K0212+(-490) - K0213+537; K0218+000 - K0218+503; K0218+559 - K0221+085 | Region I | Region I | Completed | ₱144.8M | 100% | High risk68 | —-0.028 |
| 24A00056CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LINGAYEN BYPASS ROAD | Region I | Region I | On-Going | ₱67.1M | 14% | High risk68 | Flagged0.006 |
| 17A00034REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM / HIGHWAY DEVELOPMENT ALONG PANGASINAN - ZAMBALES ROAD, K0 268+(-814) - K0 268+000; K0 271+878 - K0 272+000; K0 274+000 - K0 | Region I | Region I | Completed | ₱57.4M | 100% | High risk68 | —-0.048 |
| 25A00446ROAD WIDENING - TERTIARY ROADS, LINGAYEN-CADRE RD - CHAINAGE 0 - CHAINAGE 549 | Region I | Region I | On-Going | ₱53.3M | 0% | High risk68 | Flagged0.004 |
| 17AJ0045CONSTRUCTION OF PROTECTION WORKS ALONG AGNO RIVER, BRGY. GUELEW, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱4.9M | 100% | High risk67 | —-0.046 |
| 17AJ0041CONSTRUCTION OF PROTECTION WORKS ALONG SINUCALAN RIVER, MINIEN SECTION, STA. BARBARA, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱19M | 100% | High risk65 | —-0.047 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24AH0165CONST'N. OF FOUR(4) STOREY,TWENTY FOUR(24) CL, S/B. AT MANGATAREM 1 CENTRAL SCHOOL,MANGATAREM, PANGA | Region I | Pangasinan 2nd DEO | On-Going | ₱71.6M | 84% | High risk88 | Flagged0.052 |
| 25AH0098CONSTRUCTION OF DRAINAGE STRUCTURE,BARANGAY BAAY, LINGAYEN, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱4.8M | 0% | High risk95 | Flagged0.041 |
| 23A00151CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LINGAYEN-BINMALEY BYPASS ROAD, BINMALEY SIDE, PANGASINAN | Region I | Region I | On-Going | ₱100.4M | 50% | High risk79 | Flagged0.034 |
| 25AH0088CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG AGNO RIVER,BRGY. PANGAPISAN NORTE TO BRGY. POBL | Region I | Pangasinan 2nd DEO | On-Going | ₱93.4M | 0% | High risk93 | Flagged0.022 |
| 24AH0085CONST'N./IMPROV'T.OF ACCESS RD.LEADING TO MANIBOC-PANGAPISAN NORTH RD.CONNECTING ALVEAR ST.(PROV'L.R | Region I | Pangasinan 2nd DEO | On-Going | ₱19M | 52% | High risk72 | Flagged0.018 |
| 24A00363SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF BRIDGE CONNECTING BARANGAY PANGAPISAN NORTH AND BARANGAY CAPANDANAN, LINGAYEN, PANGASINAN | Region I | Region I | On-Going | ₱93.6M | 0% | High risk62 | Flagged0.017 |
| 25AH0092INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES(ROADWAY LIGHTING)ALONG PANG.-ZAM.RD.-K0358+(-910) | Region I | Pangasinan 2nd DEO | On-Going | ₱48.1M | 89% | High risk95 | Flagged0.017 |
| 23A00325CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD MITIGATION FACILITIES AT MANGATAREM, PANGASINAN | Region I | Region I | On-Going | ₱107.8M | 0% | High risk62 | Flagged0.014 |
| 25AH0082WIDENING OF PERMANENT BRIDGES AT CARPIO BR.(B00674LZ)ALONG PANGASINAN-TARLAC RD.(PHASE II),MANGATARE | Region I | Pangasinan 2nd DEO | On-Going | ₱38.4M | 37% | High risk91 | Flagged0.014 |
| 25AH0081WIDENING OF PERMANENT BRIDGES AT GODOY BR.(B00672LZ) ALONG PANGASINAN-TARLAC RD.(PHASE II),MANGATARE | Region I | Pangasinan 2nd DEO | On-Going | ₱48M | 63% | High risk93 | Flagged0.009 |
| 23AH0016ASSET PRESERVATION-CONST'N./UPGRADING/REHAB.OF DRAINAGE ALONG PANG.-TARLAC RD.K0178+315,MANGATAREM,P | Region I | Pangasinan 2nd DEO | On-Going | ₱3.2M | 100% | Medium risk58 | Flagged0.009 |
| 24A00168CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, REHABILITATION OF FLOOD MITIGATION STRUCTURE, LIMAHONG RIVER CHANNEL, PHASE III, LINGAYEN, PANGASINAN | Region I | Region I | On-Going | ₱93.6M | 11% | High risk63 | Flagged0.008 |
| 24AH0155CONCRETING OF BRGY. POLONG FMR, BRGY. POLONG, BUGALLON, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱14.9M | 95% | Medium risk45 | Flagged0.007 |
| 25AH0084WIDENING OF PERMANENT BRIDGES AT CURAMBENG BR.(B02147LZ)ALONG PANGASINAN-ZAMBALES RD.(PHASE II),BINM | Region I | Pangasinan 2nd DEO | On-Going | ₱42.8M | 71% | High risk91 | Flagged0.006 |
| 23AH0023WIDENING OF PERMANENT BRIDGES AT BONGALON BR.(B02137LZ)ALONG PANG.-ZAM.RD.LABRADOR,PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱33.9M | 60% | Medium risk54 | Flagged0.006 |
| 24A00056CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LINGAYEN BYPASS ROAD | Region I | Region I | On-Going | ₱67.1M | 14% | High risk68 | Flagged0.006 |
| 25AH0083WIDENING OF PERMANENT BRIDGES AT BONGALON BR.(B02137LZ)ALONG PANGASINAN-ZAMBALES RD.(PHASE III),LABR | Region I | Pangasinan 2nd DEO | On-Going | ₱27.5M | 0% | Medium risk47 | Flagged0.006 |
| 25A00446ROAD WIDENING - TERTIARY ROADS, LINGAYEN-CADRE RD - CHAINAGE 0 - CHAINAGE 549 | Region I | Region I | On-Going | ₱53.3M | 0% | High risk68 | Flagged0.004 |
| 24AH0120CONSTRUCTION OF BRIDGE, BARANGAY LAWAK LANGKA, MANGATAREM, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱19.1M | 3% | Medium risk47 | Flagged0.003 |
| 23AH0082CONSTRUCTION (CONCRETING) OF ROAD, BRGY. CALOOCAN NORTE, BINMALEY, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱9.9M | 100% | High risk74 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 21A00045CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF SHORE PROTECTION/SEAWALL, PHASE 2 (FROM SITE AGOO MUNICIPAL PORT NORTHWARD TO ARINGAY) BRGY. BALAWARTE-BRGY. STA. RITA SUR, AGOO, LA UNION | Region I | Region I | Completed | ₱48.2M | 100% | Medium risk48 | —-0.070 |
| 77 | 21AJ0072WIDENING OF PERMANENT BRIDGES-NANSANGAAN BR. (B01994LZ) ALONG VILLASIS-MALASIQUI-SN CARLOS RD, MALASIQUI, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱42.7M | 100% | Medium risk48 | —-0.050 |
| 78 | 24AH0120CONSTRUCTION OF BRIDGE, BARANGAY LAWAK LANGKA, MANGATAREM, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱19.1M | 3% | Medium risk47 | Flagged0.003 |
| 79 | 25AH0083WIDENING OF PERMANENT BRIDGES AT BONGALON BR.(B02137LZ)ALONG PANGASINAN-ZAMBALES RD.(PHASE III),LABR | Region I | Pangasinan 2nd DEO | On-Going | ₱27.5M | 0% | Medium risk47 | Flagged0.006 |
| 80 | 25A00451WIDENING OF PERMANENT BRIDGES - CAGUBAY BR. (B00679LZ) ALONG PANGASINAN-TARLAC RD | Region I | Region I | On-Going | ₱28.1M | 22% | Medium risk47 | —-0.005 |
| 81 | 22AG0010BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - MAGUNAO BR. (B00694LZ) ALONG PANGASINAN-ZAMBALES RD. AT DASOL, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱39.2M | 100% | Medium risk47 | —-0.040 |
| 82 | 22A00083CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, ROSARIO BYPASS ROAD, LA UNION | Region I | Region I | Completed | ₱38.2M | 100% | Medium risk47 | —-0.049 |
| 83 | 22AJ0002WIDENING OF PERMANENT BRIDGES-NANSANGAAN BR. (B01994LZ) ALONG VILLASIS-MALASIQUI-SN CARLOS RD (PHASE II) | Region I | Pangasinan 4th DEO | Completed | ₱19.6M | 100% | Medium risk47 | —-0.051 |
| 84 | 22AJ0013WIDENING OF PERMANENT BRIDGES -SAPANG BR. 2 (B00891LZ) ALONG CAMILING-WAWA-BAYAMBANG-MALASIQUI-STA. BARBARA RD | Region I | Pangasinan 4th DEO | Completed | ₱19M | 100% | Medium risk46 | —-0.050 |
| 85 | 22AJ0010WIDENING OF PERMANENT BRIDGES-SAPANG BR. 1 (B04602LZ) ALONG CAMILING-WAWA-BAYAMBANG-MALASIQUI-STA. BARBARA RD | Region I | Pangasinan 4th DEO | Completed | ₱19M | 100% | Medium risk46 | —-0.050 |
| 86 | 23AH0025WIDENING OF PERMANENT BRIDGES AT DUMOLOC BR. (B00682LZ) ALONG PANGASINAN-TARLAC RD (PHASE II) | Region I | Pangasinan 2nd DEO | Completed | ₱8.2M | 100% | Medium risk46 | —-0.046 |
| 87 | 18AF0048WIDENING OF TUBOD BRIDGE (B02630LZ) ALONG MANILA NORTH RD K0226+173, STO TOMAS LU | Region I | La Union 2nd DEO | Completed | ₱17.7M | 100% | Medium risk46 | —-0.050 |
| 88 | 18AG0107BRIDGE-WIDENING OF PERMANENT BRIDGES-MATALIKITIK 1BR. (B00712LZ) ALONG PANGASINAN-ZAMBALES ROAD KO334+500, BRGY. CAOAYAN , SUAL, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱11.2M | 100% | Medium risk46 | —-0.048 |
| 89 | 21A00224LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF BRIDGE AT PAIYAS, BRGY. SAN JOSE SUR, AGOO, LA UNION | Region I | La Union 2nd DEO | Completed | ₱5M | 100% | Medium risk46 | —-0.050 |
| 90 | 24A00015CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - PANGASINAN - ZAMBALES ROAD TO JUDGE JOSE DE VENECIA BOULEVARD EXT'N ROAD (BINMALEY SECTION), PACKAGE 1, PANGASINAN | Region I | Region I | On-Going | ₱37.1M | 6% | Medium risk46 | —-0.016 |
| 91 | 25A00162CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - PANGASINAN-ZAMBALES ROAD TO JUDGE JOSE DE VENECIA BOULEVARD EXT'N ROAD (BINMALEY SECTION), PACKAGE 2, PANGASINAN | Region I | Region I | On-Going | ₱46.2M | 9% | Medium risk46 | —-0.022 |
| 92 | 25A00161CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - PANGASINAN - ZAMBALES ROAD TO JUDGE JOSE DE VENECIA BOULEVARD EXT'N ROAD (BINMALEY SECTION), PACKAGE 1, PANGASINAN | Region I | Region I | On-Going | ₱46.1M | 11% | Medium risk46 | —-0.024 |
| 93 | 24AH0081NETWORK DEVELOPMENT-ROAD WIDENING-PANGASINAN-ZAMBALES RD=K0367+978=K0369+000,BINMALEY,PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱33.7M | 27% | Medium risk46 | —-0.025 |
| 94 | 24AH0126CONSTRUCTION OF ROAD, LINGAYEN, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱39.2M | 38% | Medium risk46 | —-0.033 |
| 95 | 25AH0095INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES(ROADWAY LIGHTING)ALONG LINGAYEN-LABRADOR DIV.RD.- | Region I | Pangasinan 2nd DEO | On-Going | ₱43.7M | 90% | Medium risk46 | —-0.048 |
| 96 | 24A00038CONSTRUCTION OF MISSING LINKS/ NEW ROADS, MANGATAREM -STA CRUZ ROAD, PANGASINAN | Region I | Region I | On-Going | ₱45.2M | 29% | Medium risk46 | —-0.023 |
| 97 | 23AG0011NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PANGASINAN-ZAMBALES RD - K0279 + 905 - K0280 + 134, K0281 + 257 - K0282 + 036 AT DASOL, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱29.4M | 100% | Medium risk45 | —-0.081 |
| 98 | 18AG0051NETWORK DEVELOPMENT-ROAD WIDENING SECONDARY ROADS PANGASINAN-ZAMBALES ROAD AT (KO288+886-KO289+905) DASOL, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱30M | 100% | Medium risk45 | —-0.082 |
| 99 | 21A00088CONSTRUCTION OF BY-PASS AND DIVERSION ROADS- DAGUPAN-MANGALDAN-CALASIAO CIRCUMFERENTIAL ROAD (CALASIAO SECTION), PANGASINAN | Region I | Region I | Completed | ₱33.8M | 100% | Medium risk45 | —-0.086 |
| 100 | 21A00033CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - PANDAN AVENUE AND FIRE TREE AVENUE LEADING TO MINOR BASILICA OF OUR LADY OF MANAOAG SHRINE, BRGY. NILOMBOT, MAPANDAN, PANGASI | Region I | Region I | Completed | ₱33.7M | 100% | Medium risk45 | —-0.088 |