Contractor dossier
153 projects on file, including joint ventures this contractor is part of.
Total projects
153
Total budget
₱3.7B
Average progress
90.3%
Completion rate
78.4%
Average risk score
47.3
Medium risk on average, out of 100
Flagged as unusual
4
2.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 153 | ₱3.7B | 47.3 | 4 | 90.3% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 82 | ₱1.8B | 46.1 | 3 | 90.7% |
| Buildings and Facilities | 37 | ₱238.8M | 44.6 | 1 | 87.6% |
| Flood Control and Drainage | 22 | ₱1.1B | 49.4 | 0 | 89.7% |
| OTHER | 6 | ₱165.7M | 69.8 | 0 | 100.0% |
| Bridges | 3 | ₱74.1M | 48.7 | 0 | 100.0% |
| Water Provision and Storage | 2 | ₱15.4M | 43.1 | 0 | 100.0% |
| Bridges, Roads | 1 | ₱224.6M | 67.8 | 0 | 66.2% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DP0080CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY NAGCALBANG, NAGCARLAN, LAGUNA | Region IV-A | Laguna 3rd DEO | On-Going | ₱6.8M | 45% | High risk72 | —-0.027 |
| 25DP0065CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTIPURPOSE BUILDING, BRGY. STA. MARIA MAGDALENA, SAN PABLO, LAGUNA | Region IV-A | Laguna 3rd DEO | On-Going | ₱6.8M | 68% | High risk71 | —-0.033 |
| 19DP0016NETWORK DEVELOPMENT OFF-CARRIAGEWAY IMPROVEMENT - CALAUAN - NAGCARLAN BDRY. RD. K0088 + 590 - K0089 + 240, K0089 + 265 - K0089 + 365 | Region IV-A | Laguna 3rd DEO | Completed | ₱23.3M | 100% | High risk71 | —-0.042 |
| 19DP0010NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING INCLUDING DRAINAGE - TERTIARY ROADS - LIPA CITY - ALAMINOS RD. (S01713LZ) K0077 + 500 - K0078 + 000 | Region IV-A | Laguna 3rd DEO | Completed | ₱14.6M | 100% | High risk70 | —-0.042 |
| 22DI0078CONSTRUCTION OF ROAD, BARANGAYS PULO AND SAN ISIDRO, CABUYAO CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱49M | 100% | High risk70 | —-0.041 |
| 17DI0021REHABILITATION/ RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE -TERTIARY ROADS- MAKILING PARK ROAD, K0065+925 - K0065+1270 | Region IV-A | Laguna 2nd DEO | Completed | ₱19.4M | 100% | High risk70 | —-0.043 |
| 17DP0001NETWORK DEVELOPMENT - OFF CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE AT CALAMBA - STA. CRUZ - FAMY - JUNCTION ROAD | Region IV-A | Laguna 3rd DEO | Completed | ₱46.6M | 100% | High risk69 | —-0.043 |
| 19DI0087OFF -CARRIAGEWAY IMPROVEMENT-PRIMARY ROADS- CALAMBA- STA. CRUZ-FAMY JCT. RD., K0058 + 580- K0058 + 870, LOS BAÑOS, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱12.9M | 100% | High risk69 | —-0.042 |
| 24D00062CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ALAMINOS - SAN PABLO CITY BYPASS ROAD, PACKAGE I, LAGUNA | Region IV-A | Region IV-A | On-Going | ₱224.6M | 66% | High risk68 | —-0.009 |
| 25DI0012CONSTRUCTION OF RIVER PROTECTION STRUCTURE ALONG TUNASAN RIVER, NEAR SLEX UPSTREAM, SAN PEDRO CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱141.3M | 34% | High risk68 | —-0.016 |
| 25D00096CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ALAMINOS-SAN PABLO CITY BYPASS ROAD, LAGUNA | Region IV-A | Region IV-A | On-Going | ₱142.3M | 0% | High risk65 | —-0.026 |
| 25D00277CONSTRUCTION OF BY-PASS AND DIVERSION ROADSTAYABAS BYPASS ROAD, PACKAGE 2, QUEZON | Region IV-A | Region IV-A | On-Going | ₱280.8M | 36% | High risk65 | —-0.023 |
| 25DI0037CONSTRUCTION OF RIVER PROTECTION STRUCTURE ALONG BAY RIVER, NEAR BAY BRIDGE, BAY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱94.1M | 53% | High risk65 | —-0.030 |
| 24DI0005CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG MAITIM WATERWAYS, NEAR F.T. SAN LUIS ROAD, BAY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱93.6M | 100% | High risk65 | —-0.077 |
| 24DP0049FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SLOPE PROTECTION WORKS AT SAMPALOC LAKE, SAN PABLO CITY, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱96.5M | 100% | High risk64 | —-0.078 |
| 17DP0062REPLACEMENT AND INSTALLATION OF NEW DISTRIBUTION PIPELINES (RIZAL, LAGUNA) | Region IV-A | Laguna 3rd DEO | Completed | ₱11.1M | 100% | High risk61 | —-0.006 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23DI0182REHABILITATION OF ROAD ALONG CIRCUMFERENTIAL ROAD, BARANGAY ESTRELLA, SAN PEDRO CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱9.6M | 0% | Medium risk43 | Flagged0.023 |
| 23DI0183REHABILITATION OF ROAD ALONG CONPIL 1 SUBD., BARANGAY SAN LORENZO, SAN PEDRO CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱9.4M | 0% | Medium risk43 | Flagged0.023 |
| 23DI0181REHABILITATION OF MAIN ROAD: F. BENITO AVE. CORNER MULAWIN CIRCLE GOING TO BARANGAY ESTRELLA BOUNDARY, BARANGAY LANGGAM, SAN PEDRO CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱9.4M | 0% | Medium risk43 | Flagged0.023 |
| 23DI0176CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN ISIDRO, CABUYAO, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱4.7M | 0% | Medium risk42 | Flagged0.021 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 20DP0055LOCAL PROGRAM - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. ANTIPOLO, RIZAL, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱5M | 100% | Medium risk48 | —-0.102 |
| 52 | 25DP0076REPAIR/REHABILITATION AND CONSTRUCTION OF FARM-TO-MARKET ROADS - CONCRETING OF BRGY. SAN JOSE FMR, BRGY. SAN JOSE, SAN PABLO, LAGUNA | Region IV-A | Laguna 3rd DEO | On-Going | ₱14.9M | 100% | Medium risk48 | —-0.021 |
| 53 | 24DP0114CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SANTIAGO I, SAN PABLO CITY, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.106 |
| 54 | 23DI0026PREVENTIVE MAINTENANCE - TERTIARY ROADS - RIZAL SHRINE RD - K0052 + (-587) - K0052 + 000 | Region IV-A | Laguna 2nd DEO | Completed | ₱29.4M | 100% | Medium risk48 | —-0.104 |
| 55 | 23DI0020PREVENTIVE MAINTENANCE - TERTIARY ROADS - MAYAPA-CANLUBANG CADRE RD - K0050 + 000 - K0050 + 260, K0050 + 800 - K0050 + 855, K0051 + 205 - K0051 + 335 | Region IV-A | Laguna 2nd DEO | Completed | ₱34M | 100% | Medium risk48 | —-0.108 |
| 56 | 22DI0087PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0052 + 700 - K0053 + 380, K0056 + 978 - K0056 + 1171 | Region IV-A | Laguna 2nd DEO | Completed | ₱40.1M | 100% | Medium risk47 | —-0.104 |
| 57 | 23DP0007ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0070 + (-611) - K0070 + 035 | Region IV-A | Laguna 3rd DEO | Completed | ₱34.5M | 100% | Medium risk47 | —-0.108 |
| 58 | 22DI0098PREVENTIVE MAINTENANCE - PRIMARY ROADS - CALAMBA-STA CRUZ-FAMY JCT RD - K0058 + 425 - K0058 + 680, K0059 + 368 - K0060 + 000 | Region IV-A | Laguna 2nd DEO | Completed | ₱37.4M | 100% | Medium risk47 | —-0.109 |
| 59 | 25DP0023BRIDGE PROGRAM - RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES - PALAYAN BR. (B03138LZ) ALONG CALAUAN-NAGCARLAN BDRY RD | Region IV-A | Laguna 3rd DEO | Completed | ₱19.2M | 100% | Medium risk47 | —-0.067 |
| 60 | 24D00107PREVENTIVE MAINTENANCE - PRIMARY ROADS DAANG MAHARLIKA (LZ) - K0079 + 726 - K0080 + 209 | Region IV-A | Region IV-A | On-Going | ₱40.7M | 49% | Medium risk47 | —-0.052 |
| 61 | 24DP0036ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - SN PABLO-CALAUAN RD - K0073 + (-100) - K0074 + 430 | Region IV-A | Laguna 3rd DEO | Completed | ₱36.3M | 100% | Medium risk47 | —-0.102 |
| 62 | 25DP0003ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - CALAMBA-STA CRUZ-FAMY JCT RD - K0070 + 450 - K0071 + 514 | Region IV-A | Laguna 3rd DEO | Completed | ₱31.6M | 100% | Medium risk47 | —-0.103 |
| 63 | 23DP0015ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0083 + 050 - K0083 + 586, K0084 + 886 - K0085 + 000, K0085 + 150 - K0085 + 178 | Region IV-A | Laguna 3rd DEO | Completed | ₱40.1M | 100% | Medium risk47 | —-0.103 |
| 64 | 23DP0005ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - LIPA - ALAMINOS RD - K0079 + 340 - K0080 + 060 | Region IV-A | Laguna 3rd DEO | Completed | ₱29.2M | 100% | Medium risk47 | —-0.103 |
| 65 | 23DP0019ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - LIPA CITY - ALAMINOS RD - K0076 + (-699) - K0076 + (-341) | Region IV-A | Laguna 3rd DEO | Completed | ₱28.6M | 100% | Medium risk47 | —-0.106 |
| 66 | 24DP0014NETWORK DEVELOPMENT- ROAD WIDENING - TERTIARY ROADS - LIPA CITY - ALAMINOS RD - K0079 + 000 - K0079 + 593 | Region IV-A | Laguna 3rd DEO | Completed | ₱29M | 100% | Medium risk47 | —-0.109 |
| 67 | 25DP0011BRIDGE PROGRAM - RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES - PATAY NA TUBIG BR. (B03140LZ) ALONG SN PABLO-CALAUAN RD | Region IV-A | Laguna 3rd DEO | Completed | ₱6.7M | 100% | Medium risk47 | —-0.068 |
| 68 | 23DP0003ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - SN PABLO-RIZAL-NAGCARLAN-LILIW RD - K0095 + 465 - K0096 + 852 | Region IV-A | Laguna 3rd DEO | Completed | ₱36.3M | 100% | Medium risk47 | —-0.105 |
| 69 | 23DI0007CONSTRUCTION OF REVETMENT ALONG SAN JUAN RIVER, BARANGAY 4, CALAMBA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱44.1M | 100% | Medium risk47 | —-0.089 |
| 70 | 18DI0108LIP - FLOOD CONTROL AND DRAINAGE - FLOOD CONTROL STRUCTURES/ FACILITIES - CONSTRUCTION/ REHABILITATION OF A GROUTED SLOPE PROTECTION ALONG PETANG CREEK FROM RSBS UP TO ROSEVILLE SUBD., CITY OF STA. ROSA, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱38.1M | 87% | Medium risk47 | —-0.009 |
| 71 | 18DI0043FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION/ IMPROVEMENT OF REVETMENT/ RIVER CONTROL IN BIÑAN RIVER, PUROK 5, BRGY. STO. TOMAS, BIÑAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱33.9M | 100% | Medium risk47 | —-0.088 |
| 72 | 18DI0030FLOOD MANAGEMENT PROGRAM -CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL ALONG DAMPALIT WATERWAYS, LOS BAÑOS, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱29.4M | 100% | Medium risk47 | —-0.089 |
| 73 | 18DI0028FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL ALONG MAITIM WATERWAYS, BRGY. PACIANO RIZAL, BAY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱29.4M | 100% | Medium risk47 | —-0.089 |
| 74 | 19DI0010CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURES - CONSTRUCTION OF RIVER CONTROL ALONG MAITIM WATERWAYS, BAY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱39.2M | 100% | Medium risk47 | —-0.089 |
| 75 | 23DI0055CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS - MANILA SOUTH RD - K0038 + 720 - K0039 + 430 | Region IV-A | Laguna 2nd DEO | Completed | ₱19.1M | 100% | Medium risk47 | —-0.109 |