Opening the dossier…
Opening the dossier…
Contractor dossier
180 projects on file, including joint ventures this contractor is part of.
Total projects
180
Total budget
₱6.3B
Average progress
94.7%
Completion rate
78.3%
Average risk score
52.8
Medium risk on average, out of 100
Flagged as unusual
22
12.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Cordillera Administrative Region | 176 | ₱6.2B | 53.0 | 22 | 94.6% |
| Region II | 3 | ₱55.1M | 42.0 | 0 | 100.0% |
| Region I | 1 | ₱34.2M | 45.3 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 97 | ₱4B | 50.9 | 1 | 96.3% |
| Flood Control and Drainage | 35 | ₱1.1B | 50.0 | 5 | 97.5% |
| Buildings and Facilities | 15 | ₱85.7M | 34.0 | 0 | 94.7% |
| OTHER | 11 | ₱621M | 80.4 | 8 | 90.0% |
| Bridges | 11 | ₱58.8M | 42.7 | 0 | 100.0% |
| GAA 2025 SSP | 4 | ₱42.9M | 94.5 | 4 | 67.6% |
| GAA 2025 OO-1 | 4 | ₱418.9M | 94.1 | 4 | 59.1% |
| GAA 2025 OO-2 | 2 | ₱33.3M | 87.8 | 0 | 87.5% |
| Water Provision and Storage | 1 | ₱994.6K | 18.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25PK0012CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC BUILDINGS/FACILITIES - CONSTRUCTION OF BALBALAN-PINUKPUK ROAD JCT.-BALANT | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱19.5M | 72% | High risk96 | Flagged0.018 |
| 25PK0060BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF (COMPLETION) OF BALBALASANG MULTI-PURPOSE BUILDING, BRGY. BALBALASANG, BALBALAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱14.7M | 27% | High risk96 | Flagged0.026 |
| 25PK0032BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROAD AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES CONSTRUCTION OF SALTAN INALANGAN ROAD, BRGY. BALBALASANG, BALBALAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱4.8M | 83% | High risk96 | Flagged0.014 |
| 25PK0003ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT - PAVING OF UNPAVED ROADS - TERTIARY ROADS - LUBUAGAN-BATONG BUHAY-ABRA BDRY RD - K0461+854 - K0462+0032, K0464+023 - K0464+123, K0464+211 - K0464+284, K0465+157 | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱139.9M | 65% | High risk95 | Flagged0.021 |
| 25PK0016ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONTRUCTION OF MISSING LINKS / NEW ROADS - ABRA-KALINGA-APAYAO ROAD ALONG ACIGA (PINUKPUK)-TAWANG-BUAYA-MABACA (BALBALAN SECTION, KALINGA) GAWAAN BRIDGE | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱120M | 56% | High risk95 | Flagged0.016 |
| 25PK0005ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS / NEW ROADS: ABRA-KALINGA-APAYAO ROAD ALONG ACIGA (PINUKPUK)-TAWANG-BUAYA-MABACA (BALBALAN SECTION, KALINGA) KALINGA. | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱120.5M | 64% | High risk95 | Flagged0.016 |
| 25PK0021ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS: SECONDARY ROADS - KALINGA-ABRA RD (K0496+850 - K0499+015) | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱38.4M | 52% | High risk93 | Flagged0.007 |
| 25PK0034BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE GYM, BARANGAY BALANTOY (BULO AND BULO-NAWOY), BALBALAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱3.8M | 89% | High risk90 | Flagged0.013 |
| 25PK0037ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF FLOOD CONTROL STRUCTURE, TAWANG, BALBALAN, KALINGA. | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱23.8M | 83% | High risk88 | —-0.002 |
| 25PL0037ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE A | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱9.5M | 92% | High risk88 | —-0.004 |
| 24PK0020ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS / NEW ROADS: ABRA-KALINGA-APAYAO ROAD ALONG ACIGA (PINUKPUK)-TAWANG-BUAYA-MABACA (BALBALAN SECTION), KALINGA. | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱97.2M | 96% | High risk83 | Flagged0.017 |
| 23PK0026CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES: CONSTRUCTION OF ABLEG-MOLAYONG-AMDALAO RD | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱96M | 100% | High risk82 | —-0.002 |
| 24PL0111ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF CUDAL RIVER FLOOD CONTROL MITIGATION STRUCTURE ALONG MAGABANGON BRIDGE, STA. 1+86 | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱95.1M | 70% | High risk82 | Flagged0.019 |
| 23PK0025CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES : CONSTRUCTION OF DAOANGAN-POSWOY-ABABAAN | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱76M | 57% | High risk81 | Flagged0.026 |
| 23PK0038CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE DEVELOPMENT INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES: CONSTRUCTION OF BANAT FLOOD CONTROL STRUCTURE, BALBALASANG, BALBAL | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱96.5M | 95% | High risk80 | Flagged0.024 |
| 25PK0022CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT): BALANTOY-DAO-ANGAN-POSWOY-ABABA-AN ROA | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱20.2M | 86% | High risk80 | Flagged0.005 |
| 22PK0030ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE: TERTIARY ROADS - BALBALAN-PINUKPUK RD - K0491+478 - K0491+504, K0492+251 | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱9.9M | 100% | High risk80 | —-0.025 |
| 24PK0008ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF LAPOC RIVER FLOOD CONTROL ST | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱29.4M | 99% | High risk80 | Flagged0.009 |
| 21PK0085ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, NATIONAL ROAD SYSTEM ALONG KALINGA-ABRA ROAD (BALBALAN SECTION), KO487+ | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱56.6M | 100% | High risk79 | —-0.023 |
| 24PK0056ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM: REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS: KALINGA-ABRA ROAD - K0510+877-K0511+477, BALBALAN, KAL | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱19.6M | 100% | High risk79 | Flagged0.003 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25PK0060BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF (COMPLETION) OF BALBALASANG MULTI-PURPOSE BUILDING, BRGY. BALBALASANG, BALBALAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱14.7M | 27% | High risk96 | Flagged0.026 |
| 23PK0025CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES : CONSTRUCTION OF DAOANGAN-POSWOY-ABABAAN | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱76M | 57% | High risk81 | Flagged0.026 |
| 23PK0038CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE DEVELOPMENT INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES: CONSTRUCTION OF BANAT FLOOD CONTROL STRUCTURE, BALBALASANG, BALBAL | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱96.5M | 95% | High risk80 | Flagged0.024 |
| 25PK0003ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT - PAVING OF UNPAVED ROADS - TERTIARY ROADS - LUBUAGAN-BATONG BUHAY-ABRA BDRY RD - K0461+854 - K0462+0032, K0464+023 - K0464+123, K0464+211 - K0464+284, K0465+157 | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱139.9M | 65% | High risk95 | Flagged0.021 |
| 24PL0111ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF CUDAL RIVER FLOOD CONTROL MITIGATION STRUCTURE ALONG MAGABANGON BRIDGE, STA. 1+86 | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱95.1M | 70% | High risk82 | Flagged0.019 |
| 25PK0012CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC BUILDINGS/FACILITIES - CONSTRUCTION OF BALBALAN-PINUKPUK ROAD JCT.-BALANT | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱19.5M | 72% | High risk96 | Flagged0.018 |
| 17PL0183AMMACIAN FLOOD CONTROL ALONG CAL-OWAN RIVER, AMMACIAN, PINUKPUK, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱52M | 100% | Medium risk55 | Flagged0.018 |
| 17PL0184AMMACIAN FLOOD CONTROL ALONG CAL-OWAN RIVER, AMMACIAN, PINUKPUK, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱57.1M | 100% | Medium risk57 | Flagged0.018 |
| 17PL0181WAGUD FLOOD CONTROL ALONG CAL-OWAN RIVER, BRGY. WAGUD, PINUKPUK, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱49.7M | 100% | Medium risk55 | Flagged0.018 |
| 17PL0182WAGUD FLOOD CONTROL ALONG CAL-OWAN RIVER | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱48.9M | 100% | Medium risk54 | Flagged0.018 |
| 24PK0020ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS / NEW ROADS: ABRA-KALINGA-APAYAO ROAD ALONG ACIGA (PINUKPUK)-TAWANG-BUAYA-MABACA (BALBALAN SECTION), KALINGA. | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱97.2M | 96% | High risk83 | Flagged0.017 |
| 25PK0016ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONTRUCTION OF MISSING LINKS / NEW ROADS - ABRA-KALINGA-APAYAO ROAD ALONG ACIGA (PINUKPUK)-TAWANG-BUAYA-MABACA (BALBALAN SECTION, KALINGA) GAWAAN BRIDGE | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱120M | 56% | High risk95 | Flagged0.016 |
| 25PK0005ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS / NEW ROADS: ABRA-KALINGA-APAYAO ROAD ALONG ACIGA (PINUKPUK)-TAWANG-BUAYA-MABACA (BALBALAN SECTION, KALINGA) KALINGA. | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱120.5M | 64% | High risk95 | Flagged0.016 |
| 25PK0032BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROAD AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES CONSTRUCTION OF SALTAN INALANGAN ROAD, BRGY. BALBALASANG, BALBALAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱4.8M | 83% | High risk96 | Flagged0.014 |
| 25PK0045CONCRETING OF BRGY. MABACA FMR, BRGY. MABACA, BALBALAN, KALINGA. | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱14.5M | 46% | Medium risk51 | Flagged0.013 |
| 25PK0034BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE GYM, BARANGAY BALANTOY (BULO AND BULO-NAWOY), BALBALAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱3.8M | 89% | High risk90 | Flagged0.013 |
| 17PL0211TAGA FLOOD CONTROL ALONG BALBALAN-PINUKPUK ROAD | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱79.3M | 100% | Medium risk58 | Flagged0.012 |
| 24PK0008ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF LAPOC RIVER FLOOD CONTROL ST | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱29.4M | 99% | High risk80 | Flagged0.009 |
| 24PK0071BASIC INFRASTRUCTURE PROGRAM MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BALBALASANG, BALBALAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱24.5M | 87% | High risk78 | Flagged0.007 |
| 25PK0021ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS: SECONDARY ROADS - KALINGA-ABRA RD (K0496+850 - K0499+015) | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱38.4M | 52% | High risk93 | Flagged0.007 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 19PK0033BRIDGE RETROFITTING /STRENGTHENING OF BINWAAN BRIDGE (B00964LZ) ALONG KALINGA-ABRA ROAD. | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱4.8M | 100% | Medium risk51 | —-0.044 |
| 102 | 23PK0060ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES: BINWAAN BRIDGE (B00964LZ) ALONG KALINGA-ABRA ROAD. BALBALAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱4.8M | 100% | Medium risk51 | —-0.043 |
| 103 | 19PK0022CONSTRUCTION /IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS; UGUID SUBTERRANEAN TOURISM DESTINATION ACCESS ROAD, BRGY. MALING (KABUGAO), BALBALAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱14.4M | 100% | Medium risk51 | —-0.075 |
| 104 | 20PL0104CONSTRUCTION OF PINUKPUK-BALBALAN ROAD (BAL - ABA-ABA SECTION), BRGY. BALLAYANGON, PINUKPUK, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱19.4M | 100% | Medium risk51 | —-0.082 |
| 105 | 20PK0053LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS; CONSTRUCTION/IMPROVEMENT OF POBLACION SALEGSEG-GAWAAN ROAD, BALBALAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱9.6M | 100% | Medium risk51 | —-0.079 |
| 106 | 22PK0060ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS KALINGA-ABRA RD- KO464+622-KO464+677, KO465+124-KO465+ | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱41M | 100% | Medium risk51 | —-0.080 |
| 107 | 20PK0049CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES: TALALANG BARANGAY ROAD CONNECTING TO THE NATIONAL ROAD IN SUPPORT OF POTTERY AND JEWELRY INDUSTRY, BALBALAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱14.3M | 100% | Medium risk51 | —-0.081 |
| 108 | 24PK0070CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE ALLEVIATING GAPS: SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - IMPROVEMENT OF ROAD, BARANGAY GAANG, BALBALAN, KALI | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱24M | 0% | Medium risk51 | —-0.018 |
| 109 | 18PK0025PAVING OF UNPAVED ROADS - KALINGA-ABRA ROAD - KO494+414-KO494+534, KO494+843-KO495+000, KO496+569-KO496+716 | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱16M | 100% | Medium risk51 | —-0.076 |
| 110 | 21PK0016CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - BALANTOY - DAO-ANGAN - POSWOY - ABABA-AN ROAD IN SUPPORT OF COFFEE PROCESSING INDUSTRY, HOMESTYLES INDUSTRY (BASKETRY AND | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱14.7M | 100% | Medium risk51 | —-0.080 |
| 111 | 21PK0042LOCAL ROADS AND BRIDGES - LOCAL ROADS - LOCAL INFRASTUCTURE PROGRAM CONSTRUCTION OF GA-ANG LOCAL ROAD, TALALANG, BALBALAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱19.8M | 100% | Medium risk51 | —-0.082 |
| 112 | 21PK0056CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS: UGUID SUBTERRANEAN TOURISM DESTINATION ACCESS ROAD BRGY. MALING, BALBALAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱9.6M | 100% | Medium risk51 | —-0.076 |
| 113 | 19PK0036CONSTRUCTION /IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS /BULO-NAWOY ROAD LEADING TO BULO-NAWOY RICE TERRACES | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱9.6M | 100% | Medium risk51 | —-0.076 |
| 114 | 22PK0032CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS: UGUID SUBTERRANEAN TOURISM DESTINATION ACCESS ROAD, BRGY. MALING (KABUGAO), BALBALAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱9.6M | 100% | Medium risk51 | —-0.080 |
| 115 | 20PK0054CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS: BULO-NAWOY ROAD LEADING TO BULO-NAWOY RICE TERRACES, BRGY. BALANTOY, BALBALAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱20.1M | 100% | Medium risk50 | —-0.072 |
| 116 | 23PK0003ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION - PREVENTIVE MAINTENANCE: SECONDARY ROADS - KALINGA-ABRA ROAD, K0485+1394 - K0487+708, BALBALAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱21.3M | 100% | Medium risk50 | —-0.084 |
| 117 | 20PL0038ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS ALONG BALBALAN-PINUKPUK ROAD (S00537LZ) - CHAINAGE 2972-CHAINAGE 2991, CHAINAGE 5610-CHAINAGE 5675, CHAINAGE 5843-CHAINAGE 5889, | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱25.2M | 100% | Medium risk50 | —-0.082 |
| 118 | 23PK0008CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP): UGUID SUBTERRANEAN TOURISM DESTINATION ACCESS ROAD, BRGY. MALING (KABUGAO), BALBALAN, KAL | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱9.6M | 100% | Medium risk50 | —-0.080 |
| 119 | 19PK0010CONSTRUCTION /IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES; BALANTOY-DAO-ANGAN-POSWOY-ABAB-AN ROAD IN SUPPORT OF COFFEE PROCESSING INDUSTRY, HOMESTYLES INDUSTRY (BASKETRY AND SOFTBROOM MAKING) AND FOOD PROCESSING INDUSTRY, | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱9.6M | 100% | Medium risk50 | —-0.080 |
| 120 | 22PK0010CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES BALANTOY - DAO-ANGAN - POSWOY - ABABA-AN ROAD IN SUPPORT OF COFFIE PROCESSING INDUSTRY, HOMESTYLES INDUSTRY (BASKETRY AND SOF | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱9.5M | 100% | Medium risk50 | —-0.080 |
| 121 | 20PK0008ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE: TERTIARY ROADS - BALBALAN-PINUKPUK ROAD - (S00536LZ) CHAINAGE 5117 TO CH | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱15.8M | 100% | Medium risk50 | —-0.079 |
| 122 | 20PK0019CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES: BALANTOY - DA-ANGAN - POSWOY - AB-ABAAN ROAD IN SUPPORT OF COFFEE PROCESSING, HOMESTYLES INDUSTRY (BASKETRY AND SOFTBROOM M | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱14.7M | 100% | Medium risk50 | —-0.080 |
| 123 | 23PK0012ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - BALBALAN-PINUKPUK RD - K0480+163-K0480+195, K0483+341 | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱25.4M | 100% | Medium risk50 | —-0.082 |
| 124 | 18PK0030CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS /UGUID SUBTERRANEAN TOURISM DESTINATION ACCESS ROAD, BRGY. MALING (KABUGAO), BALBALAN, KALINGA. | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱25.2M | 100% | Medium risk50 | —-0.070 |
| 125 | 19PK0031BRIDGE - RETROFITTING /STRENGTHENING /MALCAGAO BRIDGE (B04385LZ) ALONG KALINGA-ABRA ROAD. | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱9.6M | 100% | Medium risk50 | —-0.044 |