Opening the dossier…
Opening the dossier…
Contractor dossier
133 projects on file, including joint ventures this contractor is part of.
Total projects
133
Total budget
₱7.6B
Average progress
91.0%
Completion rate
78.9%
Average risk score
47.6
Medium risk on average, out of 100
Flagged as unusual
11
8.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 97 | ₱5.6B | 43.9 | 5 | 93.0% |
| Cordillera Administrative Region | 24 | ₱1.1B | 54.8 | 3 | 93.9% |
| Region VII | 7 | ₱541.7M | 68.9 | 3 | 46.6% |
| Region I | 3 | ₱206.5M | 58.4 | 0 | 100.0% |
| Region IV-A | 1 | ₱35.3M | 66.5 | 0 | 100.0% |
| Region IV-B | 1 | ₱46.2M | 37.8 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 72 | ₱4.7B | 46.0 | 0 | 95.1% |
| Flood Control and Drainage | 21 | ₱1.1B | 38.4 | 1 | 96.1% |
| Buildings and Facilities | 16 | ₱673.7M | 41.6 | 0 | 93.6% |
| Bridges | 11 | ₱272M | 35.0 | 0 | 100.0% |
| GAA 2025 SSP | 4 | ₱294M | 94.9 | 4 | 24.2% |
| GAA 2025 OO-2 | 4 | ₱294M | 91.2 | 2 | 54.4% |
| OTHER | 3 | ₱148.1M | 79.1 | 2 | 77.2% |
| GAA 2025 OO-1 | 2 | ₱151.2M | 94.2 | 2 | 43.6% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CJ0246CONSTRUCTION OF CRUZ - CALIBUNGAN DIVERSION ROAD (SEGMENT 5), VICTORIA, TARLAC | Region III | Tarlac DEO | On-Going | ₱95.4M | 39% | High risk95 | Flagged0.023 |
| 25CJ0242CONSTRUCTION OF SAN MANUEL - BALETE DIVERSION ROAD (SEGMENT 2), TARLAC CITY, TARLAC | Region III | Tarlac DEO | On-Going | ₱95.5M | 4% | High risk95 | Flagged0.034 |
| 25CJ0307CONSTRUCTION (COMPLETION) OF TARLAC CITY GENERAL HOSPITAL, TARLAC | Region III | Tarlac DEO | On-Going | ₱78.5M | 26% | High risk95 | Flagged0.029 |
| 25HB0003ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAM REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS LOAY INTERIOR RD - K0172 + 022 - K0173 + 133, K0174 + 240 - K0175 + 164 | Region VII | Bohol 3rd DEO | On-Going | ₱54.7M | 58% | High risk94 | Flagged0.012 |
| 25CJ0154CONSTRUCTION OF ROAD AT BACULONG ECOZONE AREA (PHASE 2), VICTORIA, TARLAC | Region III | Tarlac DEO | On-Going | ₱24.5M | 28% | High risk94 | Flagged0.019 |
| 25CJ0051CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MANILA NORTH ROAD TO TARLAC SN MIGUEL VIA MACABULOS ROAD, TARLAC PHASE 1, TARLAC | Region III | Tarlac DEO | On-Going | ₱96.5M | 29% | High risk94 | Flagged0.016 |
| 25H00108OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONST. OF FLOOD CONTROL STRUCTURE, WAHIG RIVER, STA. 0 + 470.00 - STA. 0 + 944.60, PAMACSALAN AREA, | Region VII | Region VII | On-Going | ₱85.1M | 13% | High risk92 | Flagged0.011 |
| 25H00107OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONST. OF FLOOD CONTROL STRUCTURE, CASBU RIVER, STA. 0 + 385.00 - STA. 0 + 784.30, CANDIJAY, BOHOL | Region VII | Region VII | On-Going | ₱85.1M | 20% | High risk92 | Flagged0.007 |
| 25CJ0098CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG SAN ISIDRO CREEK (PHASE 5), TARLAC CITY, TARLAC | Region III | Tarlac DEO | On-Going | ₱74.3M | 84% | High risk91 | —-0.018 |
| 25CJ0092CONSTRUCTION OF BANK PROTECTION STRUCTURE ALONG TARLAC RIVER CONTROL RIGHT DIKE, SAN NICOLAS - SAN. CRUZ SECTION (SEGMENT 11), TARLAC CITY, TARLAC | Region III | Tarlac DEO | On-Going | ₱49.5M | 100% | High risk90 | —-0.022 |
| 18PK0081CONCRETING AND IMPROVEMENT OF BALINCIAGAO-AMDALAO ROAD WITH BRIDGE | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱48.5M | 100% | High risk88 | Flagged0.038 |
| 25CK0103REHABILITATION OF EARTH SLOPE DIKE, UPSTREAM OF BANGOT BRIDGE - BANGUT RIVER LEFT SIDE (SEGMENT E), CAPAS, TARLAC | Region III | Tarlac 2nd DEO | On-Going | ₱96.5M | 97% | High risk80 | —-0.023 |
| 24PK0082LOCAL PROGRAM (LP) BUILDINGS AND OTHER INFRASTRUCTURES - MULTIPURPOSE / FACILITIES NATIONAL BUILDING PROGRAM CONSTRUCTION (COMPLETION) OF DPWH UPPER KALINGA DISTRICT ENGINEERING OFFICE BUILDING, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱34.3M | 32% | High risk79 | Flagged0.018 |
| 21CA0060CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM - TIKAS) - CONSTRUCTION OF ABUCAY MUNICIPAL POLICE STATION BUILDI | Region III | Bataan 1st DEO | Completed | ₱56.2M | 100% | High risk77 | —-0.063 |
| 20CJ0070NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADS STA. IGNACIA - GUIMBA ROAD VIA GERONA PURA, (STA. IGNACIA SECTION), PACKAGE 2, TARLAC | Region III | Tarlac DEO | Completed | ₱65.3M | 100% | High risk70 | —-0.035 |
| 17DO0020MFO1-NATIONAL ROADS-NETWORK SERVICES-NETWORK DEVELOPMENT-IMPROVEMENT/WIDENING OF NATIONAL ROADS-TERTIARY ROADS-RODRIGUEZ SAN JOSE ROAD (SO4225LZ)-K0031+-251 - K0032+345 RODRIGUEZ RIZAL | Region IV-A | Rizal 2nd DEO | Completed | ₱35.3M | 100% | High risk67 | —-0.072 |
| 17A00019CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-WIDENING (1-LANE) OF AMBAYAOAN BRIDGE, ALONG SAN NICOLAS-SAN MANUEL ROAD, PANGASINAN | Region I | Region I | Completed | ₱83M | 100% | High risk64 | —-0.017 |
| 17CE0047CONSTRUCTION OF BY-PASSES/DIVERSION ROADS INCLUDING ROW, GUIMBA-TALUGTUG-UMINGAN ROAD, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱46.5M | 100% | High risk64 | —-0.063 |
| 17A00028CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS - WIDENING OF PERMANENT BRIDGE TO MORE THAN TWO (2) LANES, TAGAMUSING BRIDGE (B00728LZ) ALONG MANILA NORTH ROAD (PHASE II) | Region I | Region I | Completed | ₱77M | 100% | High risk64 | —-0.022 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 18PK0081CONCRETING AND IMPROVEMENT OF BALINCIAGAO-AMDALAO ROAD WITH BRIDGE | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱48.5M | 100% | High risk88 | Flagged0.038 |
| 25CJ0242CONSTRUCTION OF SAN MANUEL - BALETE DIVERSION ROAD (SEGMENT 2), TARLAC CITY, TARLAC | Region III | Tarlac DEO | On-Going | ₱95.5M | 4% | High risk95 | Flagged0.034 |
| 25CJ0307CONSTRUCTION (COMPLETION) OF TARLAC CITY GENERAL HOSPITAL, TARLAC | Region III | Tarlac DEO | On-Going | ₱78.5M | 26% | High risk95 | Flagged0.029 |
| 25CJ0246CONSTRUCTION OF CRUZ - CALIBUNGAN DIVERSION ROAD (SEGMENT 5), VICTORIA, TARLAC | Region III | Tarlac DEO | On-Going | ₱95.4M | 39% | High risk95 | Flagged0.023 |
| 25CJ0154CONSTRUCTION OF ROAD AT BACULONG ECOZONE AREA (PHASE 2), VICTORIA, TARLAC | Region III | Tarlac DEO | On-Going | ₱24.5M | 28% | High risk94 | Flagged0.019 |
| 24PK0082LOCAL PROGRAM (LP) BUILDINGS AND OTHER INFRASTRUCTURES - MULTIPURPOSE / FACILITIES NATIONAL BUILDING PROGRAM CONSTRUCTION (COMPLETION) OF DPWH UPPER KALINGA DISTRICT ENGINEERING OFFICE BUILDING, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱34.3M | 32% | High risk79 | Flagged0.018 |
| 25CJ0051CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MANILA NORTH ROAD TO TARLAC SN MIGUEL VIA MACABULOS ROAD, TARLAC PHASE 1, TARLAC | Region III | Tarlac DEO | On-Going | ₱96.5M | 29% | High risk94 | Flagged0.016 |
| 17PL0236PACKAGE 10: A) TALOCTOC FLOOD CONTROL ALONG TANUDAN RIVER, TANUDAN, B) ALINANAG FLOOD CONTROL ALONG MANGLIG RIVER, TABUK CITY, C) CUDAL FLOOD CONTROL ALONG MANGLIG RIVER, TABUK CITY, D) LAY-ASAN FLOOD CONTROL, TANUDAN | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱58M | 100% | Medium risk58 | Flagged0.012 |
| 25HB0003ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAM REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS LOAY INTERIOR RD - K0172 + 022 - K0173 + 133, K0174 + 240 - K0175 + 164 | Region VII | Bohol 3rd DEO | On-Going | ₱54.7M | 58% | High risk94 | Flagged0.012 |
| 25H00108OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONST. OF FLOOD CONTROL STRUCTURE, WAHIG RIVER, STA. 0 + 470.00 - STA. 0 + 944.60, PAMACSALAN AREA, | Region VII | Region VII | On-Going | ₱85.1M | 13% | High risk92 | Flagged0.011 |
| 25H00107OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONST. OF FLOOD CONTROL STRUCTURE, CASBU RIVER, STA. 0 + 385.00 - STA. 0 + 784.30, CANDIJAY, BOHOL | Region VII | Region VII | On-Going | ₱85.1M | 20% | High risk92 | Flagged0.007 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 18CJ0147NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MNR TO TARLAC-SAN MIGUEL VIA. MACABULOS ROAD, INCL. DRAINAGE, TARLAC | Region III | Tarlac DEO | Completed | ₱46.6M | 100% | Medium risk34 | —-0.098 |
| 102 | 25CJ0243CONSTRUCTION OF ROAD IN IT PARK, SAN ISIDRO, TARLAC CITY, TARLAC | Region III | Tarlac DEO | On-Going | ₱29.7M | 70% | Medium risk33 | —-0.062 |
| 103 | 24CE0184ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS, JCT PINAGPANAAN - RIZAL - PANTABANGAN RD - K0128+800 - K0130+000, K0132+000 - K0132+478 | Region III | Nueva Ecija 1st DEO | Completed | ₱41.8M | 100% | Medium risk33 | —-0.102 |
| 104 | 20CA0033CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO DECLARED TOURISM DESTINATIONS CONCRETING OF OLD SAN JOSE ROAD LEADING TO ANGELES-PORAC-FLORIDABLANCA-DINALUPIHAN ROAD BARANGAY OLD SAN JOSE, DINALUPIHAN, BATAAN | Region III | Bataan 1st DEO | Completed | ₱9.8M | 100% | Medium risk33 | —-0.102 |
| 105 | 20CJ0094CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS CONSTRUCTION OF FLOOD CONTROL STRUCTURES WITHIN AGNO RIVER BASIN SYSTEM ALONG TARLAC RIVER CONTROL ,RANG-AYAN-NANCAMARINAN SECTION, PANIQUI, TARLAC | Region III | Tarlac DEO | Completed | ₱47.5M | 100% | Medium risk33 | —-0.087 |
| 106 | 19CE0134NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, GUIMBA - TALUGTUG - UMINGAN ROAD, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱45.3M | 100% | Medium risk33 | —-0.102 |
| 107 | 20CJ0076LOCAL INFRASTRUCTURE PROGRAM CONSTRUCTION OF MULTI- PURPOSE BUILDING (REHABILITATION BUILDING), ENRIQUE HENRY M. COJUANGCO MEMORIAL DISTRICT HOSPITAL, SAN JULIAN, MONCADA, TARLAC | Region III | Tarlac DEO | Completed | ₱14.1M | 100% | Medium risk33 | —-0.099 |
| 108 | 19CJ0164LOCAL INFRASTRUCTURE PROGRAM CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. POBLACION SUR, PANIQUI, TARLAC | Region III | Tarlac DEO | Completed | ₱14.3M | 100% | Medium risk33 | —-0.100 |
| 109 | 23CJ0090NETWORK DEVELOPMENT PROGRAM ROAD WIDENING STA. IGNACIA-GERONA-PURA-GUIMBA RD (S05056LZ) - CHAINAGE 19255 - CHAINAGE 21115, CHAINAGE 21795 - CHAINAGE 22211 | Region III | Tarlac DEO | Completed | ₱44.4M | 100% | Medium risk33 | —-0.099 |
| 110 | 20CL0058CONSTRUCTION OF MULTI-PURPOSE BUILDING, BOTOLAN NORTH CENTRAL ES, BRGY. TAMPO, BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱4.9M | 100% | Medium risk33 | —-0.094 |
| 111 | 24CJ0063CONTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG TARLAC RIVER (LEFT DIKE), BRILLANTE-ADUAS (PACKAGE L), PANIQUI, TARLAC | Region III | Tarlac DEO | Completed | ₱49.5M | 100% | Medium risk32 | —-0.087 |
| 112 | 22CK0003ASSET PRESERVATION PROGRAM: PREVENTIVE MAINTENANCE ALONG CONCEPCION - CAPAS ROAD, CONCEPCION, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱33.1M | 100% | Medium risk32 | —-0.103 |
| 113 | 23CJ0035BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SANTA MONICA, MONCADA, TARLAC | Region III | Tarlac DEO | Completed | ₱5.9M | 100% | Medium risk32 | —-0.101 |
| 114 | 20CE0005CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG LABONG RIVER, BRGY. CAINGIN TABING ILOG, GUIMBA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱49M | 100% | Medium risk32 | —-0.089 |
| 115 | 20CE0003CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG RIO CHICO RIVER, BRGY. MACAMIAS, GUIMBA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱49M | 100% | Medium risk32 | —-0.089 |
| 116 | 22CK0005ASSET PRESERVATION PROGRAM: PREVENTIVE MAINTENANCE ALONG CONCEPCION - LA PAZ ROAD, LA PAZ, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱23.2M | 100% | Medium risk31 | —-0.103 |
| 117 | 20CJ0013BRIDGE PROGRAM RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES MALICU BR. (B03439LZ) ALONG MANILA NORTH RD | Region III | Tarlac DEO | Completed | ₱6.4M | 100% | Medium risk31 | —-0.063 |
| 118 | 20CJ0012BRIDGE PROGRAM RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES LEGASPI BR. (B03157LZ) ALONG MANILA NORTH RD | Region III | Tarlac DEO | Completed | ₱5.1M | 100% | Medium risk31 | —-0.063 |
| 119 | 22CL0071CONSTRUCTION OF FLOOD MITIGATION STRUCTURE , BAYTO RIVER (UPSTREAM NORTH APPROACH), STA. CRUZ, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱29.7M | 100% | Medium risk31 | —-0.082 |
| 120 | 23CJ0328CONSTRUCTION/IMPROVEMENT OF CAMILING PUBLIC MARKET (PACKAGE B), CAMILING, TARLAC | Region III | Tarlac DEO | Completed | ₱48.3M | 100% | Medium risk30 | —-0.031 |
| 121 | 19CJ0120BRIDGE PROGRAM RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES SALUMAGUE BR. (B01380LZ) ALONG ROMULO H-WAY | Region III | Tarlac DEO | Completed | ₱5.4M | 100% | Medium risk30 | —-0.061 |
| 122 | 19CJ0091BRIDGE PROGRAM WIDENING OF PERMANENT BRIDGES BIGBIGA BR. 2 (B03432LZ) ALONG CAPAS-SAN JOSE-MAYANTOC-MALACAMPA RD | Region III | Tarlac DEO | Completed | ₱32.7M | 100% | Low risk30 | —-0.065 |
| 123 | 19CJ0092BRIDGE PROGRAM WIDENING OF PERMANENT BRIDGES BIGBIGA BR.3 (B03433LZ) ALONG CAPAS-SAN JOSE-MAYANTOC-MALACAMPA RD | Region III | Tarlac DEO | Completed | ₱17.8M | 100% | Low risk29 | —-0.065 |
| 124 | 22CJ0108BASIC INFRASTRUCTURE PROGRAM (BIP) FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES FLOOD CONTROL STRUCTURE ALONG TARLAC RIVER CONTROL RIGHT DIKE, COLIBANGBANG-NANCAMARINAN SECTION, PANIQUI, TARLAC | Region III | Tarlac DEO | Completed | ₱34M | 100% | Low risk29 | —-0.087 |
| 125 | 19CJ0090BRIDGE PROGRAM WIDENING OF PERMANENT BRIDGES BIGBIGA BR.1 (B03431LZ) ALONG CAPAS-SAN JOSE-MAYANTOC-MALACAMPA RD | Region III | Tarlac DEO | Completed | ₱11.4M | 100% | Low risk29 | —-0.065 |