Contractor dossier
4 projects on file, including joint ventures this contractor is part of.
Total projects
4
Total budget
₱125M
Average progress
99.6%
Completion rate
75.0%
Average risk score
56.9
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region V | 4 | ₱125M | 56.9 | 0 | 99.6% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| OTHER | 1 | ₱45.7M | 77.0 | 0 | 100.0% |
| Bridges | 1 | ₱50.4M | 53.5 | 0 | 100.0% |
| Roads | 1 | ₱10.5M | 51.0 | 0 | 98.5% |
| Flood Control and Drainage | 1 | ₱18.5M | 45.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 17FE0015NETWORK DEVELOPMENT: IMPROVEMENT/WIDENING OF NATIONAL ROADS TERTIARY ROADS, NAGA-CAROLINA-PANICUASON ROAD, K0439+469-K0440+549 | Region V | Camarines Sur 3rd DEO | Completed | ₱45.7M | 100% | High risk77 | —-0.009 |
| 2 | 25FF0009CLUSTER 1:001;ENSURE SAFE & RELIABLE NATL.RD. SYSTEM-NETWORK DEVT. PROG.BRIDGE PROG.-RETROFITTING/STRENGHTENING OF PERMANENT BRIDGES -1 MAGSAYSAY BR.(B00474LZ) ALONG MT VILLANUEVA AVE,.-MAGSAYSAY RD 2,PINIT GRANDE BR.(B00415LZ)ALONG PILI TIGAON ALBAY RD | Region V | Camarines Sur 3rd DEO | Completed | ₱50.4M | 100% | Medium risk53 | —-0.066 |
| 3 | 25FF0024BIP;ACCESS ROAD &/OR BRIDGES FROM THE NATL. RDS. LEADING TO MAJOR /STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF ROAD ZONE 5 TO 7,BARANGAY BINANUAANAN GRANDE CALABANGA CAMARINES SUR | Region V | Camarines Sur 3rd DEO | On-Going | ₱10.5M | 98% | Medium risk51 | —-0.075 |
| 4 | 18FE0082ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM CONSTRUCTION/REHABILITATION/IMPROVEMENT OF CREEK,BRGY.SAN JOSE,PILI CAMARINES SUR | Region V | Camarines Sur 3rd DEO | Completed | ₱18.5M | 100% | Medium risk46 | —-0.087 |