Contractor dossier
60 projects on file, including joint ventures this contractor is part of.
Total projects
60
Total budget
₱1.4B
Average progress
98.3%
Completion rate
100.0%
Average risk score
54.6
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 60 | ₱1.4B | 54.6 | 0 | 98.3% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 22 | ₱510.6M | 59.2 | 0 | 100.0% |
| Flood Control and Drainage | 20 | ₱826.4M | 67.3 | 0 | 100.0% |
| Buildings and Facilities | 16 | ₱33.8M | 30.9 | 0 | 93.8% |
| Bridges | 1 | ₱35.3M | 67.9 | 0 | 100.0% |
| Water Provision and Storage | 1 | ₱13.2M | 66.6 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 19AA0197CONCRETING OF BRGY. MALASIN FARM - TO - MARKET ROAD, BRGY. MALASIN, BANGUI, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱9.9M | 100% | High risk72 | —-0.030 |
| 19AA0195CONCRETING OF BRGY. MASIKIL - BRGY. LANAO FARM - TO - MARKET ROAD, BRGY. MASIKIL AND BRGY. LANAO, BANGUI, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱9.9M | 100% | High risk72 | —-0.029 |
| 19AA0218REPAIR/MAINTENANCE OF FLOOD CONTROL STRUCTURE ALONG BOLO RIVER, BRGY. SAN ISIDRO, DUMALNEG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱16.7M | 100% | High risk71 | —-0.018 |
| 18AA0289CONST. OF FLOOD CONTROL STRUCTURES ALONG RIOENG RIVER, STA. 0+000-STA. 0+670, BRGY. RIOENG, LAOAG CITY, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱23.6M | 100% | High risk71 | —-0.065 |
| 20A00117CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, TANGAOAN-PALLAS ROAD LEADING TO PARAISO ECOTOURISM PROJECT ECO AND REFORESTATION PROJECT, VINTAR-PIDDIG, ILOCOS NORTE | Region I | Region I | Completed | ₱9.4M | 100% | High risk71 | —-0.084 |
| 20AA0019CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, ACCESS ROAD LEADING TO BOLO RIVER BOULEVARD AND AY-AYO WATERFALLS, BRGY. SAN ISIDRO, DUMALNEG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱9.6M | 100% | High risk70 | —-0.081 |
| 18AA0141CONST. OF FC STRUCTURE ALONG STA. MARIA RIVER RIGHT BANK DOWNSTREAM STA 0+000-0+920 DUMALNEG, I.N. | Region I | Ilocos Norte 1st DEO | Completed | ₱42.2M | 100% | High risk70 | —-0.062 |
| 18AA0190CONST. OF FC STRUCTURE ALONG KALAW RIVER, STA. 0+000-0-+910, DUMALNEG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱42.1M | 100% | High risk70 | —-0.062 |
| 18AA0115CONST. OF FC STRUCTURES ALONG LAMUK RIVER, BRGY. POBLACION, DUMALNEG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱42M | 100% | High risk70 | —-0.062 |
| 18AA0102CONST. OF FC STRUCTURES ALONG BOLO RIVER, DARNA BRIDGE, BRGY. SAN ISIDRO, DUMALNEG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱28.8M | 100% | High risk70 | —-0.063 |
| 21A00060CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BANGUI BYPASS ROAD, ILOCOS NORTE | Region I | Region I | Completed | ₱8.6M | 100% | High risk70 | —-0.081 |
| 20A00047CONSTRUCTION OF MISSING LINKS/ NEW ROADS - PIDDIG-CARASI-CALANASAN ROAD, ILOCOS NORTE | Region I | Region I | Completed | ₱37.4M | 100% | High risk70 | —-0.083 |
| 20A00049CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, MARUAYA-DUPITAC-CALAMBEG ESTANCIA ROAD LEADING TO LOWLAND COFFEE CONVERGENCE INITIATIVE PROJECT, BRGY. MARUAYA, PIDDIG, ILOCOS NORTE | Region I | Region I | Completed | ₱16.4M | 100% | High risk70 | —-0.084 |
| 20AA0021CONTINUATION OF THE CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BOLO RIVER, BRGY. TARRAG, PAGUDPUD, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱28.3M | 100% | High risk70 | —-0.063 |
| 18AA0249CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SITIO AGAL-MASI, POBLACION ADAMS, ADAMS, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱28.2M | 100% | High risk70 | —-0.066 |
| 20A00062CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, NAPIDAD VIEW DECK AND WATER FALLS OF TAKULAO MATALTALA AND PAO, DUMALNEG, ILOCOS NORTE | Region I | Region I | Completed | ₱9.4M | 100% | High risk70 | —-0.083 |
| 18AA0100CONST. OF FC STRUCTURES ALONG QUIBEL RIVER, BRGY. POBLACION, DUMALNEG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱23.5M | 100% | High risk70 | —-0.066 |
| 20AA0127CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LAMUK RIVER, POBLACION, DUMALNEG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱24.1M | 100% | High risk70 | —-0.066 |
| 20AA0118CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG QUIBEL RIVER, BRGY. POBLACION, DUMALNEG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱24M | 100% | High risk70 | —-0.066 |
| 21AA0044CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG PRINCIPAL RIVER - BACARRA - VINTAR RIVER (BISLAK RIVER) STA. 17+300 - 17+622.80, BARANGAY SALSALAMAGUI, VINTAR, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱49M | 100% | High risk70 | —-0.066 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 21AA0084CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TAMDAGAN RIVER TRIBUTARIES OF BISLAK RIVER, LEFT BANK, UPSTREAM OF CABANGARAN BRIDGE, BARANGAY CABANGARAN, VINTAR, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱81.1M | 100% | High risk69 | —-0.056 |
| 27 | 21AA0081CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BISLAK RIVER, BARANGAY TAMDAGAN, SITIO NAGALANGAN, RIGHT BANK, DOWNSTREAM OF TAMDAGAN BRIDGE, VINTAR, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱81.1M | 100% | High risk69 | —-0.056 |
| 28 | 22AA0079CONSTRUCTION OF BARANGAY ROAD, BANGUI, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱14.4M | 100% | High risk69 | —-0.083 |
| 29 | 21AA0096CONSTRUCTION OF BARANGAY ROAD ALILEM-TABTABLANG-CAPCAPITAN BARANGAY ROAD BARANGAY CABARITAN, DUMALNEG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱96.5M | 100% | High risk69 | —-0.066 |
| 30 | 21AA0093CONSTRUCTION OF BRGY. ROAD STA. MARIA-DATAG-ARAPANG-SAN ISIDRO BARANGAY ROAD, BARANGAY KALAW, DUMALNEG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱96.5M | 100% | High risk69 | —-0.069 |
| 31 | 20AA0120CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES, BRGY. BUCAROT ROAD LEADING TO LOCAL WINE INDUSTRY AND LEMON GRASS FARM, ADAMS, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱9.6M | 100% | High risk69 | —-0.083 |
| 32 | 22AA0120ROAD WIDENING - PRIMARY ROADS - MANILA NORTH ROAD (S00034LZ) - K0562+262 - K0565+086 | Region I | Ilocos Norte 1st DEO | Completed | ₱45M | 100% | High risk69 | —-0.076 |
| 33 | 18AA0186CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAOI RIVER, U/S & D/S OF BALAOI BRIDGE (L&R BANK), BRGY. BALAOI, PAGUDPUD, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱23.5M | 100% | High risk69 | —-0.066 |
| 34 | 18AA0349CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC BRGY. BUCAROT INCLUDING BRIDGE LEADING TO LOCAL WINE INDUSTRY AND LEMON GRASS FARM, ADAMS, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱77.2M | 100% | High risk69 | —-0.062 |
| 35 | 22AA0043WIDENING OF PERMANENT BRIDGES - PANCIAN BR. (B00549LZ) ALONG MANILA NORTH ROAD | Region I | Ilocos Norte 1st DEO | Completed | ₱35.3M | 100% | High risk68 | —-0.040 |
| 36 | 18AA0185CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CAUNAYAN RIVER, U/S & D/S OF CAUNAYAN BRIDGE (L&R BANK), PAGUDPUD, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱24.5M | 100% | High risk67 | —-0.066 |
| 37 | 21AA0057CONSTRUCTION OF LEVEL III WATER SUPPLY PROJECT, DUMALNEG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱13.2M | 100% | High risk67 | —-0.042 |
| 38 | 21AA0021CONCRETING OF ROAD IN BRGY. PASALENG, PAGUDPUD, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱13.7M | 100% | High risk65 | —-0.082 |
| 39 | 20AA0242CONSTRUCTION OF CLASSROOM, 1 STOREY 3 CLASSROOM, BANBAN ELEMENTARY SCHOOL, BANGUI, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱6.2M | 100% | High risk62 | —-0.040 |
| 40 | 18AA0459COMPLETION OF RHU BUILDING, DUMALNEG RHU, DUMALNEG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱4.9M | 100% | High risk60 | —-0.041 |
| 41 | 21AA0103CONSTRUCTION/IMPROVEMENT/REHABILITATION/COMPLETION OF MULTI PURPOSE BUILDINGS IN DUMALNEG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱2.8M | 100% | Medium risk38 | —-0.080 |
| 42 | 22AA0105CONSTRUCTION (COMPLETION) OF MULTI PURPOSE BUILDING, BARANGAY 16 SAN ROQUE II, BACARRA, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱2M | 0% | Medium risk36 | —-0.038 |
| 43 | 22AA0060CONSTRUCTION (COMPLETION) OF MULTI PURPOSE BUILDING, BARANGAY 27-A PUNGTO, BACARRA, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱2M | 100% | Medium risk34 | —-0.080 |
| 44 | 21A00048CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - NAPIDAD VIEW DECK AND WATER FALLS OF TAKULAO MATALTALA AND PAO, DUMALNEG, ILOCOS NORTE | Region I | Region I | Completed | ₱3.4M | 100% | Medium risk33 | —-0.083 |
| 45 | 22A00117CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS ( TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP ), NAPIDAD VIEW DECK AND WATER FALLS OF TAKULAO MATALTALA AND PAO, DUMALNEG, ILOCOS NORTE | Region I | Region I | Completed | ₱3.9M | 100% | Medium risk32 | —-0.079 |
| 46 | 22AA0034CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, ACCESS ROAD LEADING TO BOLO RIVER BOULEVARD AND AY-AYO WATERFALLS, BRGY. SAN ISIDRO, DUMALNEG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱3.9M | 100% | Medium risk32 | —-0.081 |
| 47 | 21AA0035CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFASTRUCTURE PROGRAM ROLL-IT) BRGY. BUCAROT ROAD LEADING TO LOCAL WINE INDUSTRY AND LEMON GRASS FARM ADAMS, I.N. | Region I | Ilocos Norte 1st DEO | Completed | ₱2.4M | 100% | Medium risk32 | —-0.080 |
| 48 | 21AA0043CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, ACCESS ROAD LEADING TO BOLO RIVER BOULEVARD AND AY-AYO WATERFALLS, BRGY. SAN ISIDRO, DUMALNEG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱2.4M | 100% | Medium risk30 | —-0.078 |
| 49 | 22AA0117CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAUD, PAGUDPUD, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱2M | 100% | Low risk30 | —-0.071 |
| 50 | 22AA0110CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY CAPARISPISAN, PAGUDPUD, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱2M | 100% | Low risk30 | —-0.079 |